# 242101405987
Unscheduled inspection
Start date: 2021-12-01, end date: —, duration: 10
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This inspection is carried out in order to verify the fulfillment of the previously issued to the person being checked instruction No. 2165-ONS-2 dated 09/16/2021 on the elimination of identified violations at the specified capital construction facility, the deadline for which expires on 11/30/2021.
The objectives of this audit are: to establish the fact of the elimination of previously identified violations, to verify the actual work performed in accordance with the prescribed measures within the prescribed period.
7. The subject of this audit is the fulfillment of the instructions of the body carrying out regional state construction supervision.
# 242101408528
Unscheduled inspection
Start date: 2021-11-29, end date: —, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection:
# 242101291393
Unscheduled inspection
Start date: 2021-11-01, end date: —, duration: 20
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility, in connection with the onset of completion dates, which are subject to verification in accordance with the approved program of 23.01.2019 inspections during the construction of the capital construction facility.;
The objectives of this audit are to prevent, identify and suppress violations of legislation on urban development, including project documentation.
7. The subject of this audit is:
7.1. Verification of compliance of the work performed and the construction materials used during the construction of a capital construction facility, as well as the results of such work, with the requirements of the design documentation approved in accordance with Parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation (subject to changes made to the design documentation in accordance with parts 3.8 and 3.9 of Article 49 Urban Planning Code of the Russian Federation) and (or) an information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of the Urban Planning Code of the Russian Federation);
7.2. Requirements for a construction permit, as well as the parameters of a capital construction facility under construction or reconstruction specified in the construction permit;
7.3. Requirements established by Parts 2 and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation;
7.4. Requirements to the construction control procedure established by the Urban Planning Code of the Russian Federation and other regulatory legal acts.
# 242101293298
Unscheduled inspection
Start date: 2021-11-01, end date: —, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection:
# 242101242217
Unscheduled inspection
Start date: 2021-10-18, end date: —, duration: —
Authority: —
Purpose of inspection:
# 242100560954
Unscheduled inspection
Start date: 2021-09-01, end date: —, duration: —
Authority: —
Purpose of inspection:
# 242100314039
Unscheduled inspection
Start date: 2021-08-09, end date: —, duration: 17
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility, in connection with the onset of completion dates, which are subject to verification in accordance with the approved program of 05.10.2020 inspections during the construction of the capital construction facility.;
The objectives of this audit are to prevent, identify and suppress violations of legislation on urban development, including project documentation.
7. The subject of this audit is:
7.1. Verification of compliance of the work performed and the construction materials used during the construction of a capital construction facility, as well as the results of such work, with the requirements of the design documentation approved in accordance with Parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation (subject to changes made to the design documentation in accordance with parts 3.8 and 3.9 of Article 49 Urban Development Code of the Russian Federation) and (or) an information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of the Urban Development Code of the Russian Federation), including energy efficiency requirements (with the exception of capital construction facilities, which are not subject to energy efficiency requirements) and equipment requirements of the capital construction facility metering devices for used energy resources;
7.2. Meeting the requirements set out in Parts 2, 3 and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation;
7.3. Verification of the construction permit.
# 242100325074
Unscheduled inspection
Start date: 2021-07-01, end date: —, duration: —
Authority: —
Purpose of inspection:
# 242100242955
Unscheduled inspection
Start date: 2021-06-01, end date: —, duration: —
Authority: —
Purpose of inspection:
# 242100203831
Unscheduled inspection
Start date: 2021-05-11, end date: —, duration: 10
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: Establish that:
This inspection is carried out in order to verify the fulfillment of the instruction No. 265-ons-1 dated 02/26/2021 issued earlier to the person being checked on the elimination of identified violations at the specified capital construction facility, the deadline for which expires on 05/07/2021.
The objectives of this audit are: to establish the fact of the elimination of previously identified violations, to verify the actual work performed in accordance with the prescribed measures within the prescribed period.
7. The subject of this audit is the fulfillment of the instructions of the body carrying out regional state construction supervision.
# 242100101212
Unscheduled inspection
Start date: 2021-04-01, end date: —, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection:
# 242105335021
Unscheduled inspection
Start date: 2021-02-01, end date: 2021-02-12, duration: 10
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: Establish that:This inspection is carried out in order to verify the fulfillment of the previously issued to the person being checked instruction No. 312-ONS-2 dated 03/17/2020 on the elimination of identified violations at the specified capital construction facility, the deadline for which expires on 05/15/2020.The objectives of this audit are: to establish the fact of the elimination of previously identified violations, to verify the actual work performed in accordance with the prescribed measures within the prescribed period. 7. The subject of this audit is the fulfillment of the instructions of the body carrying out regional state construction supervision.
# 242105338827
Unscheduled inspection
Start date: 2021-02-01, end date: —, duration: —
Authority: —
Purpose of inspection:
# 242105334288
Unscheduled inspection
Start date: 2021-02-01, end date: —, duration: —
Authority: —
Purpose of inspection:
# 242105335153
Unscheduled inspection
Start date: 2021-02-01, end date: 2021-02-12, duration: 10
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: Establish that:This inspection is carried out in order to verify the fulfillment of the previously issued to the person being checked instruction No. 312-ONS-2 dated 03/17/2020 on the elimination of identified violations at the specified capital construction facility, the deadline for which expires on 05/15/2020.The objectives of this audit are: to establish the fact of the elimination of previously identified violations, to verify the actual work performed in accordance with the prescribed measures within the prescribed period. 7. The subject of this audit is the fulfillment of the instructions of the body carrying out regional state construction supervision.
# 242105337329
Unscheduled inspection
Start date: 2021-02-01, end date: —, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection:
# 242105337315
Unscheduled inspection
Start date: 2021-02-01, end date: —, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection:
# 242105342069
Unscheduled inspection
Start date: 2021-02-02, end date: 2021-02-26, duration: 18
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: Establish that:this inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility, in connection with the onset of completion dates, which are subject to inspection in accordance with the approved program dated 05.10.2020 for inspections during the construction of a capital construction facility; the objectives of this inspection are to prevent, identify and suppress violations of legislation on urban development, in particular including the project documentation.7. The subject of this audit is:7.1. Verification of compliance of the work performed and the construction materials used during the construction of a capital construction facility, as well as the results of such work, with the requirements of the design documentation approved in accordance with Parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation (subject to changes made to the design documentation in accordance with parts 3.8 and 3.9 of Article 49 Urban Development Code of the Russian Federation) and (or) an information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of the Urban Development Code of the Russian Federation), including energy efficiency requirements (with the exception of capital construction facilities, which are not subject to energy efficiency requirements) and equipment requirements of the capital construction facility metering devices for used energy resources; 7.2. Fulfillment of the requirements established by Parts 2, 3 and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation; 7.3. Verification of the availability of a building permit.
# 242004439213
Unscheduled inspection
Start date: 2020-07-01, end date: 2020-07-28, duration: 20
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility in connection with the timing of completion of work that is subject to inspection in accordance with the approved program of 2007-2018 inspections during the construction of the capital construction facility the objectives of this inspection are to prevent identify and suppress violations of legislation on urban development, including design documentation7 The subject of this audit is71 Verification of the compliance of the work performed and the building materials used during the construction of a capital construction facility, as well as the results of such work, with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation and or an information model, if the formation and maintenance of an information model are mandatory in accordance with the requirements of the Urban Planning Code of the Russian Federation, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply and the requirements for equipping the capital construction facility with metering devices for energy resources used72 Compliance with the requirements set out in Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation73 Verification of a building permit
# 242004420625
Unscheduled inspection
Start date: 2020-06-01, end date: —, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection:
# 242004376022
Unscheduled inspection
Start date: 2020-04-01, end date: 2020-04-28, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this audit is conducted in order to carry out regional state construction supervision during the construction of the specified capital construction facility in connection with the timing of completion of work that is subject to verification in accordance with the approved program of 2007-2018 inspections during the construction of the capital construction facility the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including project documentation
# 242004286472
Unscheduled inspection
Start date: 2020-03-02, end date: 2020-03-30, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility in connection with the timing of completion of work that is subject to inspection in accordance with the approved program of 20062019 inspections during the construction of the capital construction facility the objectives of this inspection are to prevent identify and suppress violations of legislation on urban development, including design Documentation
# 242004286431
Unscheduled inspection
Start date: 2020-03-02, end date: 2020-03-30, duration: 20
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility in connection with the deadline for completion of work that is subject to inspection in accordance with the approved program dated January 23, 2019 for inspections during the construction of a capital construction facility the objectives of this inspection are to prevent identify and suppress violations of legislation on urban planning, including design Documentation
# 242004286385
Unscheduled inspection
Start date: 2020-03-02, end date: —, duration: —
Authority: —
Purpose of inspection:
# 242004263483
Unscheduled inspection
Start date: 2020-02-07, end date: 2020-02-28, duration: 15
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility in connection with the timing of completion of work that is subject to inspection in accordance with the approved program of 09042019 inspections during the construction of the capital construction facility the objectives of this inspection are to prevent identify and suppress violations of legislation on urban development, including design Documentation
# 241903824449
Unscheduled inspection
Start date: 2019-10-18, end date: 2019-10-31, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This inspection is carried out in order to verify the fulfillment of the instruction previously issued to the person being checked dated 28082019 2183/12 on the elimination of identified violations at the specified capital construction facility, the deadline for which expires on 17102019the objectives of this inspection are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed period
# 241903824422
Unscheduled inspection
Start date: 2019-10-18, end date: 2019-10-31, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This inspection is carried out in order to verify the fulfillment of the instruction dated 28082019 2248-2 on the elimination of identified violations at the specified capital construction facility, which expires on 17102019the objectives of this inspection are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed period.
# 24190803476973
Unscheduled inspection
Start date: 2019-08-16, end date: 2019-08-29, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: The purpose of the audit is to verify the fulfillment of the 1999C2 instruction dated 16072019 on the elimination of identified violations at the specified capital construction facility, which expires on 15082019. The objectives of the audit are to establish the fact of elimination of previously identified violations, to verify the work actually performed in accordance with the prescribed measures within the time period established by the regulation. The subject of the audit is to comply with the lawful order of the body carrying out regional state construction supervision
# 24190803476972
Unscheduled inspection
Start date: 2019-08-16, end date: —, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection:
# 24190803467551
Unscheduled inspection
Start date: 2019-08-01, end date: —, duration: —
Authority: —
Purpose of inspection:
# 24190803466238
Unscheduled inspection
Start date: 2019-08-01, end date: 2019-08-28, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: The purpose of checking the implementation of regional state construction supervision during the construction of the specified capital construction facility in connection with the deadline for completion of work that is subject to verification in accordance with the approved program dated January 23, 2019 for inspections during the construction of the capital construction facility The objectives of the audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation The subject of the audit is verification compliance of the work performed and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations and design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for the energy resources used. verification of the certificate of admission to the types of work on the construction of the capital construction facility that affect the safety of the facility capital construction
# 24190803449331
Unscheduled inspection
Start date: 2019-07-03, end date: —, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection:
# 24190803449330
Unscheduled inspection
Start date: 2019-07-03, end date: 2019-07-30, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: The purpose of checking the implementation of regional state construction supervision during the construction of the specified capital construction facility in connection with the timing of completion of work that is subject to verification in accordance with the approved program from 31072017 for inspections during the construction of the capital construction facility The objectives of the inspection are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation The subject of the inspection is verification compliance of the work performed and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations and design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for the energy resources used. verification of the certificate of admission to the types of work on the construction of the capital construction facility that affect the safety of the facility capital construction
# 24190803439448
Unscheduled inspection
Start date: 2019-06-21, end date: 2019-07-04, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: The purpose of the audit is to verify the fulfillment of the previously issued to the person being audited Regulation No. 925OZHS dated 30042019 on the elimination of identified violations at the specified capital construction facility, the deadline for which expires 20062019 The objectives of the audit are to establish the fact of elimination of previously identified violations, to verify the actual work performed in accordance with the prescribed measures within the time period prescribed by the regulation The subject of the audit is to comply with the lawful order of the body carrying out regional state construction supervision
# 24190803439447
Unscheduled inspection
Start date: 2019-06-21, end date: 2019-07-04, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: The purpose of the audit is to verify the fulfillment of the previously issued to the person being checked Regulation No. 875OZHS dated 30042019 on the elimination of identified violations at the specified capital construction facility, the deadline for which expires 20062019 The objectives of the audit are to establish the fact of elimination of previously identified violations, to verify the actual work performed in accordance with the prescribed measures within the time period prescribed by the regulation The subject of the audit is to comply with the lawful order of the body carrying out regional state construction supervision
# 24190803439446
Unscheduled inspection
Start date: 2019-06-21, end date: 2019-07-04, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: The purpose of the audit is to verify the fulfillment of the instruction 881OZHS dated 30042019, previously issued to the person being checked, on the elimination of identified violations at the specified capital construction facility, the deadline for which expires 20062019. The objectives of the audit are to establish the fact of elimination of previously identified violations, to verify the work actually performed in accordance with the prescribed measures within the time period established by the regulation. The subject of the audit is to comply with the lawful instruction of the body carrying out regional state construction supervision
# 24190803431249
Unscheduled inspection
Start date: 2019-06-07, end date: 2019-06-21, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: The purpose of the audit is to verify the fulfillment of the previously issued to the person being audited Regulation No. 933OZHS dated 30042019 on the elimination of identified violations at the specified capital construction facility, the deadline for which expires 06062019 The objectives of the audit are to establish the fact of elimination of previously identified violations, to verify the actual work performed in accordance with the prescribed measures within the time period prescribed by the regulation The subject of the audit is to comply with the lawful order of the body carrying out regional state construction supervision
# 24190803427826
Unscheduled inspection
Start date: 2019-05-24, end date: —, duration: —
Authority: —
Purpose of inspection:
# 24190803377923
Unscheduled inspection
Start date: 2019-04-01, end date: 2019-04-26, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: The purpose of checking the implementation of regional state construction supervision during the construction of the specified capital construction facility in connection with the timing of completion of work that is subject to verification in accordance with the approved program from 31072017 for inspections during the construction of the capital construction facility The objectives of the inspection are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation The subject of the inspection is verification compliance of the work performed and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations and design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for the energy resources used. verification of the certificate of admission to the types of work on the construction of the capital construction facility that affect the safety of the facility capital construction
# 24190803377924
Unscheduled inspection
Start date: 2019-04-03, end date: —, duration: —
Authority: —
Purpose of inspection:
# 24190803377713
Unscheduled inspection
Start date: 2019-04-03, end date: —, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection:
# 24190803377915
Unscheduled inspection
Start date: 2019-04-03, end date: —, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection:
# 24190803377698
Unscheduled inspection
Start date: 2019-04-03, end date: 2019-04-30, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: The purpose of checking the implementation of regional state construction supervision during the construction of the specified capital construction facility in connection with the deadline for completion of work that is subject to verification in accordance with the approved program dated January 23, 2019 for inspections during the construction of the capital construction facility The objectives of the audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation The subject of the audit is verification compliance of the work performed and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations and design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for the energy resources used. verification of the certificate of admission to the types of work on the construction of the capital construction facility that affect the safety of the facility capital construction
# 24190803377692
Unscheduled inspection
Start date: 2019-04-03, end date: —, duration: —
Authority: —
Purpose of inspection:
# 241902428902
Unscheduled inspection
Start date: 2019-01-15, end date: —, duration: —
Authority: —
Purpose of inspection:
# 241802152518
Unscheduled inspection
Start date: 2018-12-03, end date: 2018-12-14, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this audit is carried out in order to verify the fulfillment of the instruction dated 02102018 3790DPO previously issued to the person being checked on the elimination of identified violations at the specified capital construction facility, the deadline for which expires on 30112018. The objectives of this audit are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed period 7. The subject of this audit is to comply with the instructions of the authority carrying out regional state construction supervision
# 241802145207
Unscheduled inspection
Start date: 2018-11-27, end date: —, duration: —
Authority: —
Purpose of inspection:
# 241801731942
Unscheduled inspection
Start date: 2018-10-01, end date: —, duration: —
Authority: —
Purpose of inspection:
# 241801928982
Unscheduled inspection
Start date: 2018-10-16, end date: 2018-10-29, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This inspection is carried out in order to verify the fulfillment of the instruction dated 27082018 2947SENiEK previously issued to the person being checked on the elimination of identified violations at the specified capital construction facility, the deadline for which expires on 15102018. The objectives of this inspection are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the time period established by the regulation. 7 The subject of this inspection is the fulfillment of the instruction of the authority carrying out regional state construction supervision
# 241801928973
Unscheduled inspection
Start date: 2018-10-16, end date: 2018-10-29, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This audit is carried out in order to verify the fulfillment of the instruction issued earlier to the person being checked by the ENIEK dated 27082018 2949 on the elimination of identified violations at the specified capital construction facility, the deadline for which expires on 15102018. The objectives of this audit are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the time period established by the regulation. 7 The subject of this audit is the fulfillment of the instruction of the authority carrying out regional state construction supervision
# 241801928964
Unscheduled inspection
Start date: 2018-10-16, end date: 2018-10-29, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this inspection is carried out in order to verify the fulfillment of the instruction issued earlier to the person being checked from 27082018 2985SENiEK on the elimination of identified violations at the specified capital construction facility, the deadline for which expires on 15102018. The objectives of this inspection are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed period 7. The subject of this inspection is the fulfillment of the instruction of the authority carrying out regional state construction supervision
# 241801548847
Unscheduled inspection
Start date: 2018-09-24, end date: —, duration: —
Authority: —
Purpose of inspection:
# 241800668878
Unscheduled inspection
Start date: 2018-09-03, end date: 2018-09-28, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this audit is conducted in order to carry out regional state construction supervision during the construction of the specified capital construction facility in connection with the timing of completion of work that is subject to verification in accordance with the approved program of 2007-2018 inspections during the construction of the capital construction facility the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation 7 The subject of this audit is 71 Verification of the compliance of the work performed and the building materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used 72 Compliance with the requirements established by parts 2 3 and 31 of the Article 52 of the Urban Planning Code of the Russian Federation 73 Checking the availability of a building permit
# 241800586153
Unscheduled inspection
Start date: 2018-08-03, end date: —, duration: —
Authority: —
Purpose of inspection:
# 241800594173
Unscheduled inspection
Start date: 2018-08-06, end date: —, duration: —
Authority: —
Purpose of inspection:
# 241800594138
Unscheduled inspection
Start date: 2018-08-06, end date: 2018-08-17, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This audit is carried out in order to verify the fulfillment of the instruction dated 28062018 2268DPO on the elimination of identified violations at the specified capital construction facility, which expires on 03082018. The objectives of this audit are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed period 7. The subject of this audit is to comply with the instructions of the authority carrying out regional state construction supervision
# 241800585957
Unscheduled inspection
Start date: 2018-08-06, end date: —, duration: —
Authority: —
Purpose of inspection:
# 241800585925
Unscheduled inspection
Start date: 2018-08-06, end date: —, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection:
# 241800465687
Unscheduled inspection
Start date: 2018-06-18, end date: 2018-06-29, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this audit is carried out in order to verify the fulfillment of the instruction dated 28042018 921DPO previously issued to the person being checked on the elimination of identified violations at the specified capital construction facility, the deadline for which expires 15062018. The objectives of this audit are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed period 7. The subject of this audit is to comply with the instructions of the authority carrying out regional state construction supervision
# 241800465715
Unscheduled inspection
Start date: 2018-06-18, end date: 2018-06-29, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this audit is carried out in order to verify the fulfillment of the instruction previously issued to the person being checked from 04052018 1247DPO on the elimination of identified violations at the specified capital construction facility, the deadline for which expires 15062018 the objectives of this audit are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed period 7 The subject of this audit is to comply with the instructions of the authority carrying out regional state construction supervision
# 241800466590
Unscheduled inspection
Start date: 2018-06-19, end date: 2018-07-02, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This inspection is carried out in order to verify the fulfillment of the instruction dated 18052018 1382DPO on the elimination of identified violations at the specified capital construction facility, which expires on 18062018, previously issued to the person being checked. The objectives of this inspection are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed period 7 The subject of this inspection is the fulfillment of the instruction of the authority carrying out regional state construction supervision
# 241800391771
Unscheduled inspection
Start date: 2018-06-01, end date: 2018-06-29, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility in connection with the timing of completion of work that is subject to inspection in accordance with the approved program of 2007-2017 inspections during the construction of the capital construction facility the objectives of this inspection are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation 7 The subject of this audit is 71 Verification of the compliance of the work performed and the building materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used 72 Compliance with the requirements established by parts 2 3 and 31 of the Article 52 of the Urban Planning Code of the Russian Federation 73 Checking the availability of a building permit
# 241800307840
Unscheduled inspection
Start date: 2018-05-03, end date: 2018-05-31, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility in connection with the timing of completion of work that is subject to inspection in accordance with the approved program of 2007-2017 inspections during the construction of the capital construction facility the objectives of this inspection are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation 7 The subject of this audit is 71 Verification of the compliance of the work performed and the building materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used 72 Compliance with the requirements established by parts 2 3 and 31 of the Article 52 of the Urban Planning Code of the Russian Federation 73 Checking the availability of a building permit
# 241800276103
Unscheduled inspection
Start date: 2018-04-24, end date: 2018-05-10, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This inspection is carried out in order to verify the fulfillment of the instruction previously issued to the person being checked from 02032018 452DPO on the elimination of identified violations at the specified capital construction facility, the deadline for which expires on 23042018. The objectives of this inspection are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed period 7. The subject of this inspection is the fulfillment of the instruction of the authority carrying out regional state construction supervision
# 241800227654
Unscheduled inspection
Start date: 2018-04-02, end date: 2018-04-27, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility in connection with the timing of completion of work that is subject to inspection in accordance with the approved program of 2007-2017 inspections during the construction of the capital construction facility the objectives of this inspection are to prevent identify and suppress violations of legislation on urban development, including technical regulations and Verification of compliance of the work performed and the building materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, Compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation, Verification of the availability of building permits
# 241800080230
Unscheduled inspection
Start date: 2018-02-20, end date: 2018-03-06, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this audit is carried out in order to verify the fulfillment of the previously issued to the person being audited order dated 25122017 5183DPO on the elimination of identified violations at the specified capital construction facility, the deadline for which expires 19022018 the objectives of this audit are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed period 7 The subject of this audit is to comply with the instructions of the authority carrying out regional state construction supervision
# 241800079660
Unscheduled inspection
Start date: 2018-02-20, end date: 2018-03-06, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: establishment of the fact of elimination of previously identified violations verification of the work actually performed in accordance with the prescribed measures within the prescribed period
# 24170802900960
Unscheduled inspection
Start date: 2017-12-01, end date: 2017-12-28, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility in connection with the timing of completion of work that is subject to inspection in accordance with the approved program of 2007-2017 inspections during the construction of the capital construction facility the objectives of this inspection are to prevent identify and suppress violations of legislation on urban development, including technical regulations and Verification of compliance of the work performed and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations and design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, Compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation, Verification of the availability of building permits
# 24170802960963
Unscheduled inspection
Start date: 2017-12-13, end date: 2017-12-26, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This inspection is carried out in order to verify the fulfillment of the instruction dated 18102017 4538DPO on the elimination of identified violations at the specified capital construction facility, which expires on 12122017. The objectives of this inspection are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed period. The subject of this inspection is the fulfillment of the instruction of the body carrying out Regional State construction supervision
# 24170802721012
Unscheduled inspection
Start date: 2017-10-13, end date: 2017-10-26, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This inspection is carried out in order to verify the fulfillment of the instruction dated 28092017 3659TN previously issued to the person being checked on the elimination of identified violations at the specified capital construction facility, the deadline for which expires on 12102017the objectives of this inspection are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed period 7 The subject of this inspection is the fulfillment of the instruction of the body carrying out Regional State construction supervision
# 24170802720435
Unscheduled inspection
Start date: 2017-10-13, end date: 2017-10-26, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This inspection is carried out in order to verify the fulfillment of an instruction previously issued to the person being checked from 28092017 3659DPO on the elimination of identified violations at the specified capital construction facility, the deadline for which expires on 12102017the objectives of this inspection are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed period 7 The subject of this inspection is to comply with the instructions of the body carrying out Regional State construction supervision
# 24170801912891
Unscheduled inspection
Start date: 2017-09-04, end date: —, duration: —
Authority: —
Purpose of inspection:
# 24170802405467
Unscheduled inspection
Start date: 2017-09-21, end date: 2017-10-04, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This inspection is carried out in order to verify the fulfillment of the instruction previously issued to the person being checked from 22082017 3503DPO on the elimination of identified violations at the specified capital construction facility, the deadline for which expires in 2009-2017. The objectives of this inspection are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed period. The subject of this inspection is the fulfillment of the instruction of the body carrying out Regional State construction supervision
# 24170701861367
Unscheduled inspection
Start date: 2017-08-07, end date: —, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection:
# 24170701842893
Unscheduled inspection
Start date: 2017-08-01, end date: —, duration: —
Authority: —
Purpose of inspection:
# 24170701841827
Unscheduled inspection
Start date: 2017-08-01, end date: 2017-08-28, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility in connection with the timing of completion of work that is subject to inspection in accordance with the approved program of 23032017 inspections during the construction of the capital construction facility the objectives of this inspection are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation7 The subject of this audit is71 Checking the compliance of the work performed and the building materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for used energy resources 72 Checking the availability of a construction permit 73 Checking the availability of a certificate of admission to the types of works on the construction of a capital construction facility that have an impact on the safety of the capital construction facility