Found 71 inspection:

# 00160601464760
Unscheduled inspection
Start date: 2016-01-18, end date: 2016-02-01, duration:
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: State construction supervision


# 00150600068831
Unscheduled inspection
Start date: 2015-08-03, end date: 2015-08-13, duration:
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Proverka faktov izlozhennyh v sluzhebnoi zapiske nachalnika otdela gosudarstvennogo stroitelnogo nadzora ot 20 iyulya 2015 g 4255G3328


# 77190803416618
Unscheduled inspection
Start date: 2019-05-17, end date: 2019-05-30, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, fulfillment by the person carrying out the construction requirements of part 3 of Article 52 of the Urban Planning Code


# 77190803395616
Unscheduled inspection
Start date: 2019-04-12, end date: 2019-04-25, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, fulfillment by the person carrying out the construction requirements of part 3 of Article 52 of the Urban Planning Code


# 77190803378423
Unscheduled inspection
Start date: 2019-03-25, end date: 2019-03-29, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: the fulfillment by the person carrying out the construction of the requirements of part 3 of Article 52 of the Urban Planning Code is the compliance of the work and the construction materials used in the construction process of the reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for used energy resources


# 77190803327800
Unscheduled inspection
Start date: 2019-02-07, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803320264
Unscheduled inspection
Start date: 2019-01-25, end date: 2019-01-31, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803264943
Unscheduled inspection
Start date: 2018-11-01, end date: 2018-11-16, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803283443
Unscheduled inspection
Start date: 2018-11-26, end date: —, duration:
Authority:
Purpose of inspection:


# 771802173750
Unscheduled inspection
Start date: 2018-11-30, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803240497
Unscheduled inspection
Start date: 2018-10-01, end date: 2018-10-26, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803215708
Unscheduled inspection
Start date: 2018-09-03, end date: 2018-09-28, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803237276
Unscheduled inspection
Start date: 2018-09-26, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


# 77180803204961
Unscheduled inspection
Start date: 2018-08-17, end date: 2018-08-30, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803193865
Unscheduled inspection
Start date: 2018-08-06, end date: 2018-08-31, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803187366
Unscheduled inspection
Start date: 2018-07-26, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803183408
Unscheduled inspection
Start date: 2018-07-23, end date: 2018-07-25, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803170300
Unscheduled inspection
Start date: 2018-07-02, end date: 2018-07-04, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803168736
Unscheduled inspection
Start date: 2018-06-28, end date: 2018-06-29, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803161143
Unscheduled inspection
Start date: 2018-06-06, end date: 2018-06-08, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803159810
Unscheduled inspection
Start date: 2018-06-25, end date: 2018-07-20, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803138247
Unscheduled inspection
Start date: 2018-05-14, end date: 2018-05-16, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803144082
Unscheduled inspection
Start date: 2018-05-23, end date: 2018-06-01, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803148119
Unscheduled inspection
Start date: 2018-05-25, end date: 2018-05-31, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803132086
Unscheduled inspection
Start date: 2018-05-03, end date: 2018-05-17, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803121503
Unscheduled inspection
Start date: 2018-04-12, end date: 2018-04-25, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803121486
Unscheduled inspection
Start date: 2018-04-16, end date: 2018-04-30, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803127152
Unscheduled inspection
Start date: 2018-04-20, end date: 2018-05-11, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803102880
Unscheduled inspection
Start date: 2018-03-16, end date: 2018-03-22, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803102777
Unscheduled inspection
Start date: 2018-03-16, end date: 2018-03-22, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803104221
Unscheduled inspection
Start date: 2018-03-21, end date: 2018-03-23, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803089675
Unscheduled inspection
Start date: 2018-02-21, end date: 2018-02-22, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77170802452578
Unscheduled inspection
Start date: 2017-09-15, end date: 2017-10-12, duration:
Authority: Gosudarstvennaya inspekciya truda v gorode Moskve
Purpose of inspection: Zaschita prav i interesov rabotnikov v svyazi s postupleniem v Inspekciyu obrascheniya ot 03072017 g 72708117OB po voprosam oplaty truda


# 77170801965587
Unscheduled inspection
Start date: 2017-09-01, end date: 2017-09-04, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170701856382
Unscheduled inspection
Start date: 2017-08-03, end date: —, duration:
Authority:
Purpose of inspection:


# 77170701793157
Unscheduled inspection
Start date: 2017-07-11, end date: —, duration:
Authority:
Purpose of inspection:


# 77170701784563
Unscheduled inspection
Start date: 2017-07-11, end date: —, duration:
Authority:
Purpose of inspection:


# 77170701784562
Unscheduled inspection
Start date: 2017-07-07, end date: 2017-07-10, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170701689647
Unscheduled inspection
Start date: 2017-06-13, end date: —, duration:
Authority:
Purpose of inspection:


# 77170701603024
Unscheduled inspection
Start date: 2017-05-10, end date: 2017-05-12, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170701645694
Unscheduled inspection
Start date: 2017-05-23, end date: 2017-06-09, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170701549897
Unscheduled inspection
Start date: 2017-04-19, end date: —, duration:
Authority:
Purpose of inspection:


# 77170701546848
Unscheduled inspection
Start date: 2017-04-17, end date: 2017-04-17, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170701541691
Unscheduled inspection
Start date: 2017-04-17, end date: 2017-04-21, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170701526541
Unscheduled inspection
Start date: 2017-04-10, end date: 2017-04-17, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77170701526897
Unscheduled inspection
Start date: 2017-04-07, end date: 2017-05-05, duration:
Authority: Gosudarstvennaya inspekciya truda v gorode Moskve
Purpose of inspection: protection of the rights and interests of employees


# 77170701586054
Unscheduled inspection
Start date: 2017-04-28, end date: —, duration:
Authority:
Purpose of inspection:


# 77170701437765
Unscheduled inspection
Start date: 2017-03-06, end date: 2017-03-24, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77170701437862
Unscheduled inspection
Start date: 2017-03-06, end date: 2017-03-24, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77170701477291
Unscheduled inspection
Start date: 2017-03-21, end date: —, duration:
Authority:
Purpose of inspection:


# 77170701398211
Unscheduled inspection
Start date: 2017-02-21, end date: —, duration:
Authority:
Purpose of inspection:


# 77170701297035
Unscheduled inspection
Start date: 2017-01-13, end date: 2017-01-20, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77170701300050
Unscheduled inspection
Start date: 2017-01-13, end date: 2017-01-20, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170701302633
Unscheduled inspection
Start date: 2017-01-09, end date: 2017-01-20, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170701322832
Unscheduled inspection
Start date: 2017-01-24, end date: —, duration:
Authority:
Purpose of inspection:


# 77160701243592
Unscheduled inspection
Start date: 2016-12-15, end date: 2016-12-22, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77160701242508
Unscheduled inspection
Start date: 2016-12-16, end date: —, duration:
Authority:
Purpose of inspection:


# 77160701213052
Unscheduled inspection
Start date: 2016-12-07, end date: 2016-12-30, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77160701194716
Unscheduled inspection
Start date: 2016-12-02, end date: 2016-12-12, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77160701115199
Unscheduled inspection
Start date: 2016-11-15, end date: —, duration:
Authority:
Purpose of inspection:


# 77160701073821
Unscheduled inspection
Start date: 2016-11-07, end date: 2016-11-18, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: To establish that this audit is carried out in order to ensure that the capital construction facility meets the requirements of technical regulations and design documentation on the basis of an approved verification program, the objectives of this audit are to prevent identify and suppress violations of technical regulations and design documentation committed by the person being audited. The subject of this audit is the compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work the requirements of the technical regulations of the project documentation, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for energy resources used


# 77160701073437
Unscheduled inspection
Start date: 2016-11-03, end date: 2016-11-18, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: To establish that this audit is carried out in order to ensure that the capital construction facility meets the requirements of technical regulations and design documentation on the basis of an approved verification program, the objectives of this audit are to prevent identify and suppress violations of technical regulations and design documentation committed by the person being audited. The subject of this audit is the compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work the requirements of the technical regulations of the project documentation, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for energy resources used


# 77160701128658
Unscheduled inspection
Start date: 2016-11-22, end date: —, duration:
Authority:
Purpose of inspection:


# 77160700990874
Unscheduled inspection
Start date: 2016-10-13, end date: —, duration:
Authority:
Purpose of inspection:


# 77160700777719
Unscheduled inspection
Start date: 2016-09-19, end date: 2016-09-23, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: Ustanovit chto nastoyaschaya proverka provoditsya s celyu ustranenie narushenii ukazannyh v predpisanii vydannom Mosgosstroinadzorom na osnovanii istecheniya sroka ispolneniya yuridicheskim licom individualnym predprinimatelem vydannogo organom gosudarstvennogo stroitelnogo nadzora predpisaniya ob ustranenii vyyavlennogo narusheniya obyazatelnyh trebovaniiZadachami nastoyaschei proverki yavlyayutsya preduprezhdenie vyyavlenie i presechenie dopuschennyh proveryaemym licom narushenii tehnicheskih reglamentov i proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsya proverka ustraneniya narushenii ukazannyh v predpisanii vydannom Mosgosstroinadzorom 930416 ot 05092016


# 77160700084376
Unscheduled inspection
Start date: 2016-08-29, end date: —, duration:
Authority:
Purpose of inspection:


# 77160601798857
Unscheduled inspection
Start date: 2016-08-15, end date: 2016-08-18, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: Ustanovit chto nastoyaschaya proverka provoditsya s celyu ustranenie narushenii ukazannyh v predpisanii vydannom Mosgosstroinadzorom na osnovanii istecheniya sroka ispolneniya yuridicheskim licom individualnym predprinimatelem vydannogo organom gosudarstvennogo stroitelnogo nadzora predpisaniya ob ustranenii vyyavlennogo narusheniya obyazatelnyh trebovaniiZadachami nastoyaschei proverki yavlyayutsya preduprezhdenie vyyavlenie i presechenie dopuschennyh proveryaemym licom narushenii tehnicheskih reglamentov i proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsya proverka ustraneniya narushenii ukazannyh v predpisanii vydannom Mosgosstroinadzorom 182716 ot 18032016


# 77160601740199
Unscheduled inspection
Start date: 2016-07-22, end date: 2016-07-28, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: Ustanovit chto nastoyaschaya proverka provoditsya s celyu ustranenie narushenii ukazannyh v predpisanii vydannom Mosgosstroinadzorom na osnovanii postupivshego izvescheniya ot zastroischika zakazchika ili lica osuschestvlyayuschego stroitelstvo ob ustranenii narusheniiZadachami nastoyaschei proverki yavlyayutsya preduprezhdenie vyyavlenie i presechenie dopuschennyh proveryaemym licom narushenii tehnicheskih reglamentov i proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsya proverka ustraneniya narushenii ukazannyh v predpisanii vydannom Mosgosstroinadzorom 639116 ot 30062016


# 77160601700106
Unscheduled inspection
Start date: 2016-07-07, end date: 2016-07-29, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: Nastoyaschaya proverka provoditsya s celyu ustranenie narushenii ukazannyh v predpisanii vydannom Mosgosstroinadzorom na osnovanii postupivshego izvescheniya ot zastroischika zakazchika ili lica osuschestvlyayuschego stroitelstvo ob ustranenii narusheniiZadachami nastoyaschei proverki yavlyayutsya preduprezhdenie vyyavlenie i presechenie dopuschennyh proveryaemym licom narushenii tehnicheskih reglamentov i proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsya proverka ustraneniya narushenii ukazannyh v predpisanii vydannom Mosgosstroinadzorom 341316 ot 13052016


# 00160601464760
Unscheduled inspection
Start date: 2016-01-18, end date: 2016-02-01, duration:
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: State construction supervision


# 00150600068831
Unscheduled inspection
Start date: 2015-08-03, end date: 2015-08-13, duration:
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Proverka faktov izlozhennyh v sluzhebnoi zapiske nachalnika otdela gosudarstvennogo stroitelnogo nadzora ot 20 iyulya 2015 g 4255G3328


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.