Found 9 inspections:

# 162005207235
Unscheduled inspection
Start date: 2020-11-02, end date: —, duration:
Authority:
Purpose of inspection:


# 162005207263
Unscheduled inspection
Start date: 2020-11-02, end date: —, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:


# 162004374907
Unscheduled inspection
Start date: 2020-03-24, end date: 2020-03-26, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the fact of fulfillment of the order dated 19112019 1212125801, the deadline for which expired 10012020 30122019 1212148701, the deadline for which expired 16032020 and drawing up an act based on the results of the inspection. The objectives of this inspection are to prevent, identify and suppress violations of conformity committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer performed during the construction of the facility The subject of this audit is the fulfillment of the requirements of the state control bodies supervision of municipal control bodies and the requirements of the technical regulations of other regulatory legal acts and project documentation.


# 162004380412
Unscheduled inspection
Start date: 2020-01-27, end date: —, duration:
Authority:
Purpose of inspection:


# 161904160603
Unscheduled inspection
Start date: 2019-12-28, end date: 2019-12-30, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed, the construction materials used during the construction of the capital construction facility, as well as the results of such work with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used at the completion stage, as well as to draw up an inspection report on the completed construction of the facility in accordance with the received by notification dated 23/122019 13546 to the Inspection on the completion of the construction of the capital construction facility, the objectives of this inspection are to prevent, identify and prevent violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. mandatory requirements and or requirements established by municipal legal acts


# 161904160593
Unscheduled inspection
Start date: 2019-12-28, end date: 2019-12-30, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the eliminated violations with the requirements of technical regulations, project documentation, other regulations, norms and rules, as well as to draw up an act on the elimination of violations based on the Inspection notice dated 23/122019 13546 on the elimination of violations during the construction of the reconstruction of the capital construction facility, which was ordered to be eliminated within the time limit set by the regulation from 19/12/2019 12/12125801 to 10012020 The objectives of this audit are to prevent as well as identify and suppress violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other regulatory legal acts, and project documentation committed by the developer, the customer, or the person carrying out construction on the basis of a contract with the developer or the customer. The subject of this audit is to comply with the instructions of state control bodies, supervision bodies, and municipal control bodies


# 161903967174
Unscheduled inspection
Start date: 2019-11-15, end date: —, duration:
Authority:
Purpose of inspection:


# 161802164147
Unscheduled inspection
Start date: 2018-11-01, end date: 2018-11-16, duration:
Authority: Ispolnitelnyi komitet Municipalnogo obrazovaniya goroda Kazani
Purpose of inspection: The objectives of this audit are to carry out state control and supervision in the field of shared-equity construction of apartment buildings and or other real estate objects, to assess the compliance of the activities carried out by the developer and the work performed by him with the requirements of federal laws and regulatory legal acts of the Russian Federation and the Republic of Tatarstan adopted in accordance with them, as well as the requirements of municipal legal acts. The purpose of this audit is to identify violations of the legislation of the Russian Federation In the field of shared-equity construction of apartment buildings, the subject of this audit is the compliance of RTK LLC with the requirements of current legislation in the field of shared-equity construction, including the accuracy of information submitted to the Housing Policy Department of the Executive Committee of the State Committee for Housing and Communal Services, the targeted use of funds raised by participants in shared-equity construction, as well as information contained in the developer's documents on the progress of construction


# 16170802937168
Unscheduled inspection
Start date: 2017-12-08, end date: 2017-12-12, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the work performed, the materials used, the results of the work with the requirements of technical regulations, compliance with mandatory requirements and or requirements established by municipal legal acts, Prevention, as well as identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations and other regulatory legal acts acts and project documentation


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.