Found 6 inspections:

# 742100771317
Unscheduled inspection
Start date: 2021-09-22, end date: —, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection:


# 742100242492
Unscheduled inspection
Start date: 2021-06-10, end date: 2021-06-18, duration: 6
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1. Compliance of the work on the device of the profiled roofing sheet, the device of the parapets of the ABC building, the brickwork of the exterior walls of the building. and the construction materials used in the process of construction, reconstruction of the capital construction facility, as well as the results of such work to the requirements of the project documentation approved in accordance with Parts 15, 15.2 and 15.3 of Article 48 of this Code (taking into account the changes made to the project documentation in accordance with parts 3.8 and 3.9 of Article 49 of this Code) and (or) an information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of this Code), including energy efficiency requirements (with the exception of capital construction projects, to which energy efficiency requirements do not apply) and the requirements for equipping the capital construction facility with metering devices for energy resources used. 2. Availability of a building permit. 3. Compliance with the requirements of Parts 2.3 and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation.


# 742100055437
Unscheduled inspection
Start date: 2021-03-15, end date: 2021-03-19, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1. Compliance of the work performed to verify the regulations of 01/22/2021 and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of the project documentation approved in accordance with Parts 15, 15.2 and 15.3 of Article 48 of this Code (taking into account the changes made to the project documentation in accordance with Parts 3.8 and 3.9 of Article 49 of this Code) and (or) an information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of this Code), including energy efficiency requirements (with the exception of capital construction facilities, to which energy efficiency requirements do not apply) and equipment requirements of the capital construction facility metering devices for energy resources used; 2. Availability of a building permit. 3. Compliance with the requirements of Parts 2.3 and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation.


# 742005215804
Unscheduled inspection
Start date: 2020-11-17, end date: —, duration:
Authority:
Purpose of inspection:


# 741800348068
Unscheduled inspection
Start date: 2018-05-04, end date: 2018-06-03, duration:
Authority: Gosudarstvennaya inspekciya truda v CHelyabinskoi oblasti
Purpose of inspection: implementation of federal state supervision over compliance with labor legislation and other regulatory legal acts containing labor law norms in connection with the received appeal of employees of LLC "RiProekt" vh 747119518OB dated 25042018 as well as a reasoned representation of an official dated 26042018


# 001800268284
Unscheduled inspection
Start date: 2018-04-09, end date: 2018-04-09, duration:
Authority: Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: issuance of a permit for the commissioning of electrical installations for the production of tests measurements of electrical testing laboratories