Found 10 inspections:

# 001902500528
Unscheduled inspection
Start date: 2019-01-24, end date: —, duration:
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:


# 142101370132
Unscheduled inspection
Start date: 2021-11-24, end date: —, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha (YAkutiya)
Purpose of inspection:


# 142100411237
Unscheduled inspection
Start date: 2021-08-05, end date: —, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha (YAkutiya)
Purpose of inspection:


# 622005314207
Unscheduled inspection
Start date: 2020-12-24, end date: 2021-01-28, duration: 20
Authority: Gosudarstvennaya inspekciya truda v Ryazanskoi oblasti
Purpose of inspection: The audit is carried out in order to carry out federal state supervision over compliance with the requirements of the labor legislation of the Russian Federation on labor and labor protection in connection with the presence of an organization's request for an unscheduled on-site inspection by the state control body for supervision of municipal control in order to establish the fact of early execution by the organization of the order of the state control body for supervision of municipal control The tasks of the audit are to ensure compliance and protection of labor rights and freedoms citizens, including the right to safe working conditions, ensuring compliance by the employer with labor legislation and other regulatory legal acts containing labor law norms, the subject of verification is compliance with the instructions of state control bodies, supervision bodies of municipal control


# 77190803472049
Unscheduled inspection
Start date: 2019-08-12, end date: 2019-09-06, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, fulfillment by the person carrying out the construction requirements of part 3 of Article 52 of the Urban Planning Code


# 77190803376103
Unscheduled inspection
Start date: 2019-03-21, end date: 2019-03-29, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 001902500528
Unscheduled inspection
Start date: 2019-01-24, end date: 2019-02-05, duration:
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: proverka provoditsya s celyu kontrolya ispolneniya OOO «IC Energostroi» ranee vydannogo predpisaniya ot 17102018 5039RVPA182 ob ustranenii narushenii pri rekonstrukcii obekta kapitalnogo stroitelstva «Rekonstrukciya VL 330kV Nalchik Vladikavkaz2 s obrazovaniem VL 330kV Zaramagskaya GES1 Vladikavkaz2 i VL 330 kV Zaramagskaya GES1 Nalchik dlya vydachi moschnosti Zaramagskoi GES1» raspolozhennogo po adresu Rossiiskaya Federaciya Respublika Severnaya OsetiyaAlaniya Alagirskii raion Zadachami nastoyaschei proverki yavlyayutsya 1 osuschestvlenie kontrolya za prinyatymi OOO «IC Energostroi» merami po ispolneniyu ranee vydannogo predpisaniya ot 17102018 5039RVPA182 v oblasti stroitelstva pri rekonstrukcii obekta kapitalnogo stroitelstva «Rekonstrukciya VL 330kV Nalchik Vladikavkaz2 s obrazovaniem VL 330kV Zaramagskaya GES1 Vladikavkaz2 i VL 330 kV Zaramagskaya GES1 Nalchik dlya vydachi moschnosti Zaramagskoi GES1» 2 prinyatie mer po privlecheniyu k otvetstvennosti lic dopustivshih narusheniya trebovanii federalnyh zakonov i inyh normativnyh pravovyh aktov


# 77190803320284
Unscheduled inspection
Start date: 2019-01-28, end date: —, duration:
Authority:
Purpose of inspection:


# 151801917154
Unscheduled inspection
Start date: 2018-10-05, end date: 2018-11-01, duration:
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po Respublike Severnaya OsetiyaAlaniya
Purpose of inspection: proverka provoditsya s celyu vypolneniya Trebovaniya prokuratury RSOAlaniya ot 02102018 g 72611462018 o provedenii vneplanovoi proverki v otnoshenii OOO «Inzhiniringovyi centr Energostroi» zadachami nastoyaschei proverki yavlyayutsya nadzor za soblyudeniem obyazatelnyh trebovanii v oblasti ohrany okruzhayuschei sredy ohrany atmosfernogo vozduha ispolzovaniya i ohrany vodnyh obektov ispolzovaniya i ohrany zemel obrascheniya s othodami proizvodstva i potrebleniya geologicheskogo izucheniya racionalnogo ispolzovaniya i ohrany nedr ohrany vosproizvodstva i ispolzovaniya obektov zhivotnogo mira i sredy ih obitaniya ohrany i ispolzovaniya osobo ohranyaemyh prirodnyh territorii i dr Predmetom nastoyaschei proverki yavlyaetsya soblyudenie obyazatelnyh trebovanii


# 77180803075307
Unscheduled inspection
Start date: 2018-02-02, end date: 2018-02-09, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used