# 74170701380581
Unscheduled inspection
Start date: 2017-02-15, end date: 2017-03-17, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Verification of a capital construction facility completed 2The receipt of a construction permit 3The fulfillment of the requirements of hh 23 st52 of the Urban Planning Code of the Russian Federation
# 74160701232507
Unscheduled inspection
Start date: 2016-12-21, end date: 2017-01-24, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Verification of the completed capital construction facility 2 Availability of a construction permit 3 Compliance with the requirements of hr 23 st52 of the Urban Planning Code of the Russian Federation
# 74160701034984
Unscheduled inspection
Start date: 2016-10-24, end date: 2016-10-28, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1conformity of work on the installation of the facade of translucent enclosing structures and the building materials used during the construction of a capital construction facility, as well as the results of such work, to the requirements of the technical regulations of the project documentation2 Receipt of a construction permit3 Compliance with the requirements of hh 23 st52 of the Urban Planning Code of the Russian Federation
# 74160700795941
Unscheduled inspection
Start date: 2016-09-28, end date: 2016-10-04, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1The compliance of the work on the construction of the frame structures of the 2324 floors of the building and the building materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of the technical regulations of the project documentation2the need for a construction permit3the requirements of hh 23 st52 of the Urban Planning Code of the Russian Federation
# 74160601752090
Unscheduled inspection
Start date: 2016-08-03, end date: 2016-08-09, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1The compliance of the work on the construction of the building frame on the 22nd floor, the installation of internal partitions on the 16th floor, the masonry of the exterior walls on the 20th floor and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of the technical regulations of the project documentation2the need for a construction permit3the requirements of hh 23 st52 of the Urban Planning Code of the Russian Federation