# 472004423918
Unscheduled inspection
Start date: 2020-06-04, end date: 2020-07-02, duration: 2
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of the works specified in the inspection program The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used parts 2 3 and 31 of Article 52 of the Urban Development Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban development activities committed by the developer, the technical customer, the person carrying out the construction, including technical regulations and project documentation
# 471902681668
Unscheduled inspection
Start date: 2019-04-25, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection:
# 471902573331
Unscheduled inspection
Start date: 2019-03-13, end date: 2019-04-09, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of elimination of violations of the mandatory requirements specified in the notice of the person carrying out the construction on elimination of the identified violations The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the facility capital construction metering devices for energy resources used to comply with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out the construction
# 471902455968
Unscheduled inspection
Start date: 2019-01-23, end date: 2019-02-19, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of the works specified in the notice of the person carrying out the construction on the completion dates of the works that are subject to verification The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the facility capital construction metering devices for energy resources used to comply with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out the construction
# 471802093480
Unscheduled inspection
Start date: 2018-10-24, end date: 2018-11-21, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of elimination of violations of the mandatory requirements specified in the notice of the person carrying out the construction on elimination of the identified violations The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the facility capital construction with metering devices for used energy resources compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 471800365949
Unscheduled inspection
Start date: 2018-05-10, end date: 2018-06-06, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: verification of the elimination of violations of the mandatory requirements specified in the notice of the person carrying out the construction on the elimination of the identified violations The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the capital construction facility implementation of the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of the legislation on urban planning activities committed by the developer, the technical customer, the person carrying out the construction, including technical regulations and project documentation
# 471800206784
Unscheduled inspection
Start date: 2018-03-14, end date: 2018-04-10, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: verification of the works specified in the notice of the person carrying out the construction on the completion dates of the works that are subject to verification The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the capital construction facility implementation of the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of the legislation on urban planning activities committed by the developer, the technical customer, the person carrying out the construction, including technical regulations and project documentation
# 47160701255627
Unscheduled inspection
Start date: 2016-12-21, end date: 2017-01-24, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Cel proverka rabot ukazannyh v izveschenii lica osuschestvlyayuschego stroitelstvo o srokah zaversheniya rabot kotorye podlezhat proverkePredmet proverki sootvetstvie vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstvapriborami ucheta ispolzuemyh energeticheskih resursovvypolnenie trebovanii chastei 2 i 3 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii