# 002005176591
Unscheduled inspection
Start date: 2020-10-16, end date: —, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 002005154319
Unscheduled inspection
Start date: 2020-10-19, end date: —, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 002004451005
Unscheduled inspection
Start date: 2020-07-23, end date: —, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 002004367639
Unscheduled inspection
Start date: 2020-04-20, end date: —, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 002004314379
Unscheduled inspection
Start date: 2020-03-16, end date: 2020-03-23, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is conducted in order to implement the audit program approved by AA Kulakov, Deputy Head of the Rostechnadzor Technical University, on July 30, 2019. The objectives of this audit are to monitor the measures taken to ensure that a legal entity complies with the mandatory requirements of legislation on urban development during the construction and reconstruction of a capital construction facility, to prevent the detection and suppression of violations of mandatory requirements established by Federal laws and other regulatory acts of the Russian Federation, and to take measures to to eliminate violations of mandatory requirements if they are identified and to bring to justice persons who have violated the requirements of Federal laws and other regulatory legal acts.7 The subject of this audit is the compliance of the work performed and the building materials used during the construction of the reconstruction of the capital construction facility, as well as the results of such work, with the requirements approved in accordance with parts 15 15_2 and 15_3 of Article 48 of the Urban Planning Code of the Russian Federation project documentation, taking into account the changes made to the project documentation in accordance with Parts 3_8 and 3_9 of Article 49 of the Urban Planning Code of the Russian Federation, including the requirements for energy efficiency, with the exception of capital construction facilities for which energy efficiency requirements do not apply, and the requirements for equipping the capital construction facility with metering devices for energy resources used, the need for construction permits to comply with the requirements set out in Parts 2 Articles 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 001903051025
Unscheduled inspection
Start date: 2019-09-09, end date: —, duration: —
Authority: —
Purpose of inspection:
# 001800171993
Unscheduled inspection
Start date: 2018-02-26, end date: 2018-02-28, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the purpose of monitoring the execution of the order The objectives of this audit are to monitor the measures taken by a legal entity to comply with the order and comply with mandatory industrial safety requirements, to take measures to eliminate violations of mandatory requirements if they are identified and to bring to justice persons who have violated the requirements of Federal laws and other regulatory legal acts. The subject of this audit is to comply with the instructions of the state control and supervision authorities
# 772100230142
Unscheduled inspection
Start date: 2021-06-02, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772100176510
Unscheduled inspection
Start date: 2021-05-17, end date: 2021-02-20, duration: 3
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This check is carried out in order to monitor the implementation of Regulation No. 49-G dated February 15, 2020./3.3-20/ G-32.
The objectives of this audit are:
to monitor the measures taken
by the legal entity to comply with the regulations and comply with the mandatory requirements of legislation on urban development activities during the construction and reconstruction of a capital construction facility.;
taking measures to eliminate violations of mandatory requirements
(if they are identified) and to bring to justice persons who have committed violations of the requirements of Federal laws and other regulatory legal acts.
The subject of the audit is the fulfillment of the instructions of the state control (supervision) body
# 772100151663
Unscheduled inspection
Start date: 2021-04-14, end date: 2021-04-29, duration: 12
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the audit program; The tasks of the audit: prevention, identification and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements design documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of design documentation identified during construction control and state construction supervision
# 002005176591
Unscheduled inspection
Start date: 2020-10-16, end date: 2020-10-29, duration: 10
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is conducted in order to implement the audit program approved by the acting Deputy head of the Rostechnadzor MTU on August 12, 2020. The objectives of this audit are to monitor the measures taken by the legal entity to comply with the mandatory requirements of legislation on urban development during the construction and reconstruction of a capital construction facility, to prevent the detection and suppression of violations of mandatory requirements established by Federal laws and other regulatory acts of the Russian Federation, and to take measures to eliminate violations of mandatory requirements, if they are identified, and to bring to justice persons who have committed violations of the requirements of Federal laws and other regulatory legal acts7 The subject of this audit is the compliance of the work performed and the building materials used during the construction of the reconstruction of the capital construction facility, as well as the results of such work, with the requirements approved in accordance with parts 15 15_2 and 15_3 of Article 48 of the Urban Planning Code. the Code of the Russian Federation of project documentation, taking into account the changes made to the project documentation in accordance with Parts 3_8 and 3_9 of Article 49 of the Urban Planning Code of the Russian Federation, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply, and the requirements for equipping a capital construction facility with metering devices for energy resources used, the need for construction permits to meet the requirements established by parts 2 3 and 31 Articles 52 of the Urban Planning Code of the Russian Federation
# 002005154319
Unscheduled inspection
Start date: 2020-10-19, end date: 2020-10-26, duration: 6
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is conducted in order to implement the audit program approved by the Deputy Head of Rostechnadzor AA Kulakov on October 3, 2019. The objectives of this audit are to monitor the measures taken to ensure that a legal entity complies with the mandatory requirements of legislation on urban development during the construction and reconstruction of a capital construction facility, to prevent the detection and suppression of violations of mandatory requirements established by Federal laws and other regulatory acts of the Russian Federation, and to take measures to eliminate violations of mandatory requirements, if they are identified and if persons who have committed violations of the requirements of Federal laws and other regulatory legal acts7 are held accountable, the subject of this audit is the compliance of the work performed and the building materials used during the construction and reconstruction of a capital construction facility, as well as the results of such work, with the requirements of Article 48 of the Urban Planning Code of the Russian Federation approved in accordance with Parts 15 15_2 and 15_3 of the Russian Federation project documentation, taking into account the changes made to the project documentation in accordance with Parts 3_8 and 3_9 of Article 49 of the Urban Planning Code of the Russian Federation, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply, and the requirements for equipping a capital construction facility with metering devices for energy resources used, the need for construction permits to comply with the requirements set out in Parts 2 to 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 002004451005
Unscheduled inspection
Start date: 2020-07-23, end date: 2020-07-30, duration: 6
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The objectives of this audit are to monitor the measures taken by a legal entity to comply with the mandatory requirements of legislation on urban development during the construction and reconstruction of a capital construction facility, to prevent, identify and suppress violations of mandatory requirements established by Federal laws and other regulatory acts of the Russian Federation, and to take measures to eliminate violations of mandatory requirements if they are identified and to bring to justice those who have violated the requirements of Federal Laws and other regulatory legal acts7 The subject of this audit is the compliance of the work performed and the building materials used during the construction of the reconstruction of the capital construction facility, as well as the results of such work, with the requirements of the project documentation approved in accordance with Parts 15 15_2 and 15_3 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with Parts 3_8 and 3_9 of the Article 49 of the Urban Development Code of the Russian Federation, including energy efficiency requirements, with the exception of capital construction facilities to which energy efficiency requirements do not apply, and the requirements for equipping a capital construction facility with metering devices for energy resources used, including construction permits to comply with the requirements established by Parts 2 3 and 31 of Article 52 of the Urban Development Code of the Russian Federation
# 002004454106
Unscheduled inspection
Start date: 2020-07-13, end date: 2020-07-29, duration: 13
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: 6 To establish that this audit is being conducted in order to implement the audit program approved by Deputy Head of the Rostechnadzor Technical University AA Kulakov on July 30, 2019. The objectives of this audit are to monitor the measures taken to ensure that a legal entity complies with the mandatory requirements of legislation on urban development during the construction and reconstruction of a capital construction facility, to prevent the detection and suppression of violations of mandatory requirements established by Federal laws and other regulatory acts of the Russian Federation, and to take measures to ensure that the legal entity complies with the mandatory requirements of legislation on urban development during the construction and reconstruction of a capital construction facility. measures to eliminate violations of mandatory requirements if they are identified and to bring to justice persons who have committed violations of the requirements of Federal laws and other regulatory legal acts.7 The subject of this audit is the compliance of the work performed and the construction materials used during the construction of the reconstruction of the capital construction facility, as well as the results of such work, with the requirements approved in accordance with parts 15 15_2 and 15_3 of Article 48 Urban Development Code of the Russian Federation project documentation, taking into account the changes made to the project documentation in accordance with Parts 3_8 and 3_9 of Article 49 of the Urban Development Code of the Russian Federation, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply, and the requirements for equipping a capital construction facility with metering devices for energy resources used, the need for construction permits to meet the requirements established by the Legislation of the Russian Federation. parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 002004367639
Unscheduled inspection
Start date: 2020-04-20, end date: 2020-04-27, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: 6 To establish that this audit is being conducted in order to implement the audit program approved by Deputy Head of Rostechnadzor AA Kulakov on October 3, 2019. The objectives of this audit are to monitor the measures taken to ensure that a legal entity complies with the mandatory requirements of legislation on urban development during the construction and reconstruction of a capital construction facility, to prevent the detection and suppression of violations of mandatory requirements established by Federal laws and other regulatory acts of the Russian Federation, and to take measures to ensure that the legal entity complies with the mandatory requirements of legislation on urban development during the construction and reconstruction of a capital construction facility. measures to eliminate violations of mandatory requirements if they are identified and to bring to justice persons who have committed violations of the requirements of Federal laws and other regulatory legal acts.7 The subject of this audit is the compliance of the work performed and the construction materials used during the construction of the reconstruction of the capital construction facility, as well as the results of such work, with the requirements approved in accordance with parts 15 15_2 and 15_3 of Article 48 Urban Development Code of the Russian Federation project documentation, taking into account the changes made to the project documentation in accordance with Parts 3_8 and 3_9 of Article 49 of the Urban Development Code of the Russian Federation, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply, and the requirements for equipping a capital construction facility with metering devices for energy resources used, the need for construction permits to meet the requirements established by the Legislation of the Russian Federation. parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 002004314379
Unscheduled inspection
Start date: 2020-03-16, end date: 2020-03-23, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is conducted in order to implement the audit program approved by AA Kulakov, Deputy Head of the Rostechnadzor Technical University, on July 30, 2019. The objectives of this audit are to monitor the measures taken to ensure that a legal entity complies with the mandatory requirements of legislation on urban development during the construction and reconstruction of a capital construction facility, to prevent the detection and suppression of violations of mandatory requirements established by Federal laws and other regulatory acts of the Russian Federation, and to take measures to to eliminate violations of mandatory requirements if they are identified and to bring to justice persons who have violated the requirements of Federal laws and other regulatory legal acts.7 The subject of this audit is the compliance of the work performed and the building materials used during the construction of the reconstruction of the capital construction facility, as well as the results of such work, with the requirements approved in accordance with parts 15 15_2 and 15_3 of Article 48 of the Urban Planning Code of the Russian Federation project documentation, taking into account the changes made to the project documentation in accordance with Parts 3_8 and 3_9 of Article 49 of the Urban Planning Code of the Russian Federation, including the requirements for energy efficiency, with the exception of capital construction facilities for which energy efficiency requirements do not apply, and the requirements for equipping the capital construction facility with metering devices for energy resources used, the need for construction permits to comply with the requirements set out in Parts 2 Articles 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 002004229980
Unscheduled inspection
Start date: 2020-02-04, end date: 2020-02-11, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is conducted in order to implement the audit program approved by AA Kulakov, Deputy Head of the Rostechnadzor Technical University, on October 3, 2019. The objectives of this audit are to monitor the measures taken to ensure that a legal entity complies with the mandatory requirements of legislation on urban development during the construction and reconstruction of a capital construction facility, to prevent the detection and suppression of violations of mandatory requirements established by Federal laws and other regulatory acts of the Russian Federation, and to take measures to to eliminate violations of mandatory requirements if they are identified and to bring to justice persons who have committed violations of the requirements of Federal laws and other regulatory legal acts.7 The subject of this audit is the compliance of the work performed and the building materials used during the construction of the reconstruction of the capital construction facility, as well as the results of such work, with the requirements approved in accordance with Parts 15 15_2 and 15_3 of Article 48 of the Urban Planning Code of the Russian Federation project documentation, taking into account the changes made to the project documentation in accordance with Parts 3_8 and 3_9 of Article 49 of the Urban Planning Code of the Russian Federation, including the requirements for energy efficiency, with the exception of capital construction facilities for which energy efficiency requirements do not apply, and the requirements for equipping the capital construction facility with metering devices for energy resources used, the need for construction permits to comply with the requirements set out in Parts 2 Articles 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 771904142813
Unscheduled inspection
Start date: 2019-12-20, end date: 2019-12-27, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po g Moskve
Purpose of inspection: execution of the decree of the Government of the Russian Federation dated November 5, 2019 YUBP49546 in accordance with Article 10 of Part 2 of Paragraph 3 of Federal Law No. 294 FZ dated December 26, 2008 "On the Protection of the Rights of Legal Entities and Individual Entrepreneurs in the implementation of State Control, Supervision and Municipal Control" compliance with mandatory requirements and or requirements established by municipal legal acts
# 001904013675
Unscheduled inspection
Start date: 2019-12-09, end date: 2019-12-16, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: 6 To establish that this audit is being conducted in order to implement the audit program approved by Deputy Head of the Rostechnadzor Technical University AA Kulakov on July 30, 2019. The objectives of this audit are to monitor the measures taken to ensure that a legal entity complies with the mandatory requirements of legislation on urban development during the construction and reconstruction of a capital construction facility, to prevent the detection and suppression of violations of mandatory requirements established by Federal laws and other regulatory acts of the Russian Federation, and to take measures to ensure that the legal entity complies with the mandatory requirements of legislation on urban development during the construction and reconstruction of a capital construction facility. measures to eliminate violations of mandatory requirements if they are identified and to bring to justice persons who have committed violations of the requirements of Federal laws and other regulatory legal acts.7 The subject of this audit is the compliance of the work performed and the construction materials used during the construction of the reconstruction of the capital construction facility, as well as the results of such work, with the requirements approved in accordance with parts 15 15_2 and 15_3 of Article 48 Urban Development Code of the Russian Federation project documentation, taking into account the changes made to the project documentation in accordance with Parts 3_8 and 3_9 of Article 49 of the Urban Development Code of the Russian Federation, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply, and the requirements for equipping a capital construction facility with metering devices for energy resources used, the need for construction permits to meet the requirements established by the Legislation of the Russian Federation. parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 001904013607
Unscheduled inspection
Start date: 2019-12-09, end date: 2019-12-16, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: 6 To establish that this audit is being conducted in order to implement the audit program approved by Deputy Head of Rostechnadzor AA Kulakov on October 3, 2019. The objectives of this audit are to monitor the measures taken to ensure that a legal entity complies with the mandatory requirements of legislation on urban development during the construction and reconstruction of a capital construction facility, to prevent the detection and suppression of violations of mandatory requirements established by Federal laws and other regulatory acts of the Russian Federation, and to take measures to ensure that the legal entity complies with the mandatory requirements of legislation on urban development during the construction and reconstruction of a capital construction facility. measures to eliminate violations of mandatory requirements if they are identified and to bring to justice persons who have committed violations of the requirements of Federal laws and other regulatory legal acts.7 The subject of this audit is the compliance of the work performed and the construction materials used during the construction of the reconstruction of the capital construction facility, as well as the results of such work, with the requirements approved in accordance with parts 15 15_2 and 15_3 of Article 48 Urban Development Code of the Russian Federation project documentation, taking into account the changes made to the project documentation in accordance with Parts 3_8 and 3_9 of Article 49 of the Urban Development Code of the Russian Federation, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply, and the requirements for equipping a capital construction facility with metering devices for energy resources used, the need for construction permits to meet the requirements established by the Legislation of the Russian Federation. parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 001903051025
Unscheduled inspection
Start date: 2019-09-09, end date: 2019-09-23, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: 6 To establish that this audit is being conducted in order to implement the audit program approved by Deputy Head of the Rostechnadzor Technical University AA Kulakov on July 30, 2019. The objectives of this audit are to monitor the measures taken to ensure that a legal entity complies with the mandatory requirements of legislation on urban development during the construction and reconstruction of a capital construction facility, to prevent the detection and suppression of violations of mandatory requirements established by Federal laws and other regulatory acts of the Russian Federation, and to take measures to ensure that the legal entity complies with the mandatory requirements of legislation on urban development during the construction and reconstruction of a capital construction facility. measures to eliminate violations of mandatory requirements if they are identified and to bring to justice persons who have committed violations of the requirements of Federal laws and other regulatory legal acts.7 The subject of this audit is the compliance of the work performed and the building materials used during the construction of the reconstruction of the capital construction facility, as well as the results of such work with the requirements of the design documentation, including energy efficiency requirements, with the exception of facilities capital construction projects that are not subject to energy efficiency requirements and the requirements for equipping a capital construction facility with metering devices for used energy resources require a construction permit to comply with the requirements established by Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation.
# 771902852113
Unscheduled inspection
Start date: 2019-07-03, end date: 2019-07-08, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po g Moskve
Purpose of inspection: The tasks of this audit are to carry out, in accordance with the procedure established by the legislation of the Russian Federation, verification of compliance with fire safety requirements at protection facilities established by federal laws and regulatory legal acts of the Russian Federation adopted in accordance with them and taking measures based on the results of the audit, compliance with the instructions of state control bodies, supervision of municipal control bodies, carrying out measures
# 77190803457443
Unscheduled inspection
Start date: 2019-07-04, end date: 2019-07-31, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the parameters of the capital construction facility with the maximum parameters of permitted construction reconstruction of capital construction facilities established by the rules of land use and development documentation on the layout of the territory and mandatory requirements for the parameters of capital construction facilities established by the Urban Planning Code and other federal laws
# 77190803327784
Unscheduled inspection
Start date: 2019-02-06, end date: 2019-02-08, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 771802371064
Unscheduled inspection
Start date: 2018-12-13, end date: 2019-01-17, duration: —
Authority: Gosudarstvennaya inspekciya truda v gorode Moskve
Purpose of inspection: The audit is conducted in order to protect the rights and interests of an employee from 131118 74013118 Upon registration and termination of an employment contract. The objectives of the audit are supervision and control over compliance with legislation and other regulatory legal acts containing labor law norms. The subject of this audit is compliance with mandatory requirements and or requirements established by municipal legal acts. compliance with information contained in the notification of the commencement of certain types of business compliance of information contained in the application and documents of a legal entity or individual entrepreneur on granting legal status of a special permit license issuance of a permit approval with mandatory requirements as well as data on these legal entities and individual entrepreneurs contained in the unified state register of individual entrepreneurs and other federal information resources compliance with the instructions of state control bodies supervision of municipal control bodies holding events to prevent harm to the life and health of citizens, harm to animals, plants, the environment, cultural heritage sites, historical and cultural monuments of the peoples of the Russian Federation, museum objects and museum collections included in the Museum Fund of the Russian Federation, documents of special historical significance, scientific and cultural significance, which are part of the national library fund for the prevention of natural and man-made emergencies, and to ensure safety States to eliminate the consequences of causing such harm
# 771801908776
Unscheduled inspection
Start date: 2018-10-15, end date: —, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po gorodu Moskve
Purpose of inspection:
# 77180803210346
Unscheduled inspection
Start date: 2018-08-20, end date: 2018-09-14, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the requirements established by the legislation on urban planning activities within the framework of the subject of state construction supervision
# 77180803163892
Unscheduled inspection
Start date: 2018-06-20, end date: 2018-07-17, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 771800480735
Unscheduled inspection
Start date: 2018-06-21, end date: 2018-07-18, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po g Moskve
Purpose of inspection: implementation of the instruction of the Government of the Russian Federation dated May 31, 2018 YUBP43019 the objectives of this audit are to verify, in accordance with the procedure established by the legislation of the Russian Federation, compliance with fire safety requirements at protection facilities established by federal laws and regulatory legal acts of the Russian Federation adopted in accordance with them and to take measures based on the results of the audit, compliance with mandatory requirements and or requirements established by municipal legal acts
# 77180803147636
Unscheduled inspection
Start date: 2018-05-25, end date: 2018-05-29, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 001800171993
Unscheduled inspection
Start date: 2018-02-26, end date: 2018-02-28, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the purpose of monitoring the execution of the order The objectives of this audit are to monitor the measures taken by a legal entity to comply with the order and comply with mandatory industrial safety requirements, to take measures to eliminate violations of mandatory requirements if they are identified and to bring to justice persons who have violated the requirements of Federal laws and other regulatory legal acts. The subject of this audit is to comply with the instructions of the state control and supervision authorities
# 77170701349824
Unscheduled inspection
Start date: 2017-01-27, end date: 2017-02-27, duration: —
Authority: Gosudarstvennaya inspekciya truda v gorode Moskve
Purpose of inspection: Compliance with labor legislation in order to monitor the implementation of the previously issued instruction from 20122016 8PP201631519081673 federal state supervision control over compliance with the requirements of labor legislation and other regulatory legal acts containing labor law norms compliance with the instructions of state control bodies supervision of municipal control bodies