# 741801785518
Unscheduled inspection
Start date: 2018-10-03, end date: —, duration: —
Authority: —
Purpose of inspection:
# 741800422892
Unscheduled inspection
Start date: 2018-06-08, end date: 2018-06-15, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the work on the construction of the ABC roof with the device of the roofing pie of the production building and the construction materials used during the construction of the capital construction facility as well as the results of such work with the requirements of technical regulations of the project documentation 2 Availability of a construction permit 3 Compliance with the requirements of h 23 and 31 st 52 of the Urban Planning Code of the Russian Federation
# 741800340067
Unscheduled inspection
Start date: 2018-05-08, end date: 2018-05-22, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the work on the installation of external and internal walls of the ABC with the device of the roofing pie of the production building and the construction materials used during the construction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation 2 Availability of a construction permit 3 Compliance with the requirements of h 23 and 31 st 52 of the Urban Planning Code of the Russian Federation
# 741800285053
Unscheduled inspection
Start date: 2018-04-17, end date: 2018-04-23, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the installation of external and internal walls of the production building and the construction materials used during the construction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation 2 Availability of a construction permit 3 Compliance with the requirements of h 23 and 31 st 52 of the Urban Planning Code of the Russian Federation
# 741800179569
Unscheduled inspection
Start date: 2018-03-14, end date: —, duration: —
Authority: —
Purpose of inspection:
# 74170802872791
Unscheduled inspection
Start date: 2017-11-22, end date: 2017-11-28, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1The compliance of the work on the installation of the foundations of the production building with the observance of fire-fighting and sanitary-epidemiological measures and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations of the project documentation2 The presence of a construction permit 3 Compliance with the requirements of h 23 and 31 st 52 of the Urban Planning Code of the Russian Federation
# 74170701623457
Unscheduled inspection
Start date: 2017-05-26, end date: —, duration: —
Authority: —
Purpose of inspection: