# 77190803471068
Unscheduled inspection
Start date: 2019-08-01, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77190803431479
Unscheduled inspection
Start date: 2019-06-06, end date: 2019-06-21, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77190803397490
Unscheduled inspection
Start date: 2019-04-15, end date: 2019-04-26, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 771902681913
Unscheduled inspection
Start date: 2019-04-29, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170803061988
Unscheduled inspection
Start date: 2017-12-28, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 77170802795022
Unscheduled inspection
Start date: 2017-10-27, end date: 2017-11-15, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170802489287
Unscheduled inspection
Start date: 2017-09-11, end date: 2017-09-22, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 50170701738311
Unscheduled inspection
Start date: 2017-06-13, end date: 2017-06-15, duration: —
Authority: Glavnoe upravlenie gosudarstvennogo stroitelnogo nadzora Moskovskoi oblasti
Purpose of inspection: proverki ustraneniya narushenii izveschenie ob ustranenii narushenii ot 31052017 R00157490650356622132 v ramkah predpisaniya ot 24052017 07120786000503 srok vypolneniya do 26062017 ocenka sootvetstviya vypolnyaemyh rabot trebovaniyam tehnicheskih reglamentov i proektnoi dokumentacii na obekte kapitalnogo stroitelstva «Nazemnaya avtostoyanka otkrytogo tipa na 486 mashinomest so vstroennymi ne zhilymi pomescheniyami » po adresu Moskovskaya oblast g Domodedovo mkr YUzhnyi proverka ispolneniya predpisaniya ot 24052017 07120786000503 srok vypolneniya do 26062017
# 50170701388304
Unscheduled inspection
Start date: 2017-02-08, end date: 2017-02-14, duration: —
Authority: Glavnoe upravlenie gosudarstvennogo stroitelnogo nadzora Moskovskoi oblasti
Purpose of inspection: proverki ispolneniya predpisaniya ot 06122016 0712078600502 srok vypolneniya do 30012017 ocenka sootvetstviya vypolnyaemyh rabot trebovaniyam tehnicheskih reglamentov i proektnoi dokumentacii na obekte kapitalnogo stroitelstva «Nadzemnaya avtostoyanka otkrytogo tipa na 486 mashinomest so vstroennymi nezhilymi pomescheniyami» po adresu Moskovskaya oblast g Domodedovo mkr YUzhnyi proverka ispolneniya predpisaniya ot 06122016 0712078600502 srok vypolneniya do 30012017