# 612100825897
Unscheduled inspection
Start date: 2021-10-13, end date: —, duration: 16
Authority: Regionalnaya sluzhba gosudarstvennogo stroitelnogo nadzora Rostovskoi oblasti
Purpose of inspection: To establish that this inspection is carried out in order to: fulfill paragraph 2 of the inspection program: Reinforcement, concreting of foundations (Halls 1,2,3). Installation of metal structures of frames. The objectives of this audit are: prevention, detection and suppression of violations of the legislation on urban development, including project documentation, committed by the developer, the customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the customer (hereinafter referred to as the contractor) The subject of this audit is to verify: compliance with mandatory requirements and (or) requirements established by municipal legal acts


# 612100541270
Unscheduled inspection
Start date: 2021-08-23, end date: —, duration: 5
Authority: Regionalnaya sluzhba gosudarstvennogo stroitelnogo nadzora Rostovskoi oblasti
Purpose of inspection: To establish that this inspection is carried out in order to: verify the execution of: Regulation No. 01.002.3306-1 dated 06/18/2021 to 08/18/2021, issued by ARIAL LLC (TIN 6166065317) the objectives of this inspection are: prevention, identification and suppression of violations committed by the developer, the customer, as well as the person carrying out construction on the basis of the contract with the developer or the customer (hereinafter referred to as the contractor), violations of the legislation on urban development, including project documentation The subject of this audit is the verification of: compliance with the instructions of state control (supervision) bodies, municipal control bodies


# 612100241634
Unscheduled inspection
Start date: 2021-05-25, end date: —, duration: 18
Authority: Regionalnaya sluzhba gosudarstvennogo stroitelnogo nadzora Rostovskoi oblasti
Purpose of inspection: To establish that this inspection is carried out for the purpose of: fulfilling paragraph 1 of the inspection program: The work of the preparatory period. The installation of a pile foundation (Halls 1,2,3). the objectives of this inspection are: prevention, detection and suppression of violations of legislation on urban development, including technical regulations, and project documentation committed by the developer, the customer, as well as the person carrying out construction on the basis of an agreement with the developer or the customer (hereinafter referred to as the contractor) 7. The subject of this audit is to verify: compliance with mandatory requirements and (or) requirements established by municipal legal acts


# 612100041236
Unscheduled inspection
Start date: 2021-02-04, end date: 2021-02-05, duration: 2
Authority: Regionalnaya sluzhba gosudarstvennogo stroitelnogo nadzora Rostovskoi oblasti
Purpose of inspection: The objectives of this audit are: prevention, detection and suppression of violations of legislation on urban development, including technical regulations, and project documentation committed by the developer, the customer, as well as the person carrying out construction on the basis of an agreement with the developer or the customer (hereinafter referred to as the contractor) The subject of this audit is to verify: compliance with mandatory requirements and (or) requirements established by municipal legal acts


# 612105338687
Unscheduled inspection
Start date: 2021-01-28, end date: 2021-02-05, duration: 7
Authority: Regionalnaya sluzhba gosudarstvennogo stroitelnogo nadzora Rostovskoi oblasti
Purpose of inspection: the inspection is carried out for the purpose of: fulfilling clause 6 of the inspection program: Checking the completed construction of a capital construction facility the objectives of this inspection are: prevention, detection and suppression of violations of the legislation on urban development activities committed by the developer, the customer, as well as the person carrying out construction on the basis of an agreement with the developer or the customer (hereinafter referred to as the contractor), including technical regulations and project documentation The subject of this audit is to verify: compliance with mandatory requirements and (or) requirements established by municipal legal acts


# 612004427965
Unscheduled inspection
Start date: 2020-06-05, end date: 2020-06-16, duration: 7
Authority: Regionalnaya sluzhba gosudarstvennogo stroitelnogo nadzora Rostovskoi oblasti
Purpose of inspection: The inspection is carried out in order to fulfill the p5 inspection program Finishing works in PM common areas staircases bathrooms on all floors Landscaping and landscaping The objectives of this inspection are to prevent identify and suppress violations of legislation on urban development, including technical regulations, committed by the developer, the customer, as well as the person carrying out construction on the basis of an agreement with the developer or the customer, hereinafter the contractor. The subject of this audit is to verify compliance with mandatory requirements and or requirements established by municipal legal acts


# 612004321407
Unscheduled inspection
Start date: 2020-03-02, end date: 2020-03-06, duration: 5
Authority: Regionalnaya sluzhba gosudarstvennogo stroitelnogo nadzora Rostovskoi oblasti
Purpose of inspection: The inspection is carried out in order to fulfill the p4 program of inspections The device of external engineering networks The device of internal engineering networks of power supply ventilation and smoke removal fire alarm water supply drainage power supply gas supply installation of technological and elevator equipment The objectives of this inspection are to prevent identify and suppress violations of the legislation on urban planning committed by the developer the customer as well as the person carrying out construction on the basis of an agreement with the developer or the customer hereinafter the contractor activities, including technical regulations and project documentation, the subject of this audit is to verify compliance with mandatory requirements and or requirements established by municipal legal acts


# 611903988860
Unscheduled inspection
Start date: 2019-11-11, end date: 2019-11-15, duration:
Authority: Regionalnaya sluzhba gosudarstvennogo stroitelnogo nadzora Rostovskoi oblasti
Purpose of inspection: the inspection is carried out with the aim of fulfilling the p3 inspection program The construction of the aboveground part of buildings and structures, including the completion of work on the devices of monolithic structures of the frame column diaphragm ceiling walls stairwells elevator shafts, work on the device of enclosing structures, the device of internal partitions, the tasks of this inspection are the prevention identification and suppression of admitted by the developer, the customer, as well as the person carrying out construction on the basis of an agreement with the developer or the customer hereinafter referred to as the contractor for violations of the legislation on urban planning activities, including technical regulations and project documentation, the subject of this audit is to verify compliance with mandatory requirements and or requirements established by municipal legal acts


# 611903844308
Unscheduled inspection
Start date: 2019-08-05, end date: 2019-08-09, duration:
Authority: Regionalnaya sluzhba gosudarstvennogo stroitelnogo nadzora Rostovskoi oblasti
Purpose of inspection: in order to fulfill the p1 program of inspections, Verification of the organizational and legal order of construction Preparatory work preparation of the construction site cleaning of the territory from vegetation and debris installation of a fence installation of an object passport installation of a wheel washing station placement and arrangement of a construction site on-duty lighting washbasins toilets fire shields, etc. Earthworks ground layout development of a pit for a reservoir the tasks of this inspection are prevention identification and suppression of violations committed by the developer the customer as well as the person carrying out construction on the basis of an agreement with the developer or the customer hereinafter referred to as the contractor of violations of legislation on urban development activities, including technical regulations and project documentation, the subject of this audit is to verify compliance with mandatory requirements and or requirements established by municipal legal acts


# 611902764659
Unscheduled inspection
Start date: 2019-05-07, end date: 2019-05-15, duration:
Authority: Regionalnaya sluzhba gosudarstvennogo stroitelnogo nadzora Rostovskoi oblasti
Purpose of inspection: in order to fulfill the p1 program of inspections of the work of the preparatory period, the organization of construction works installation of a fence fence arrangement of a construction site arrangement of storage sites for building materials Earthworks, including the layout of the territory, the development of a foundation pit, the installation of a pile field


# 611800564604
Unscheduled inspection
Start date: 2018-07-19, end date: 2018-07-31, duration:
Authority: Regionalnaya sluzhba gosudarstvennogo stroitelnogo nadzora Rostovskoi oblasti
Purpose of inspection: 1 fulfillment of the p3 inspection program General construction works on the section Outdoor water supply and sewerage networks 2 prevention identification and suppression of violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, the customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the customer hereinafter the contractor, 3 compliance with mandatory requirements and or requirements established by municipal legal acts


# 611800218438
Unscheduled inspection
Start date: 2018-03-19, end date: 2018-03-30, duration:
Authority: Regionalnaya sluzhba gosudarstvennogo stroitelnogo nadzora Rostovskoi oblasti
Purpose of inspection: This audit is carried out in order to fulfill the p2 program of inspections. The objectives of this audit are to prevent, identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, as well as the person carrying out construction on the basis of an agreement with the developer or the technical customer. The subject of this audit is compliance with mandatory requirements or requirements established by municipal legal acts. acts