Found 18 inspections:

# 001902865915
Unscheduled inspection
Start date: 2019-07-15, end date: 2019-07-16, duration:
Authority: Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This check is carried out in order to verify the fulfillment of the items previously issued in the order from 22022019 H183r, the deadline for which has expired, The objectives of this check are to implement measures to monitor the elimination of violations specified in the paragraphs of the order from 22022019 H183r


# 742100187843
Unscheduled inspection
Start date: 2021-05-13, end date: 2021-05-19, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1. Verification of the execution of the order dated 02/09/2021, due on 03/30/2021. 2. Availability of a building permit. 3. Meeting the requirements of Parts 2.3 and 3.1 of art. 52 of the Urban Planning Code of the Russian Federation.


# 742100207223
Unscheduled inspection
Start date: 2021-05-20, end date: 2021-06-17, duration: 20
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1. Inspection of the completed construction site. 2. Availability of a building permit. 3. Compliance with the requirements of Parts 2.3 and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation.


# 742100055392
Unscheduled inspection
Start date: 2021-03-17, end date: 2021-03-23, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1. Compliance with the performance of works on interior decoration, landscaping, compliance with sanitary and epidemiological requirements and measures to ensure access for low-mobility groups of the population. and the construction materials used during the construction, reconstruction of the capital construction facility, as well as the results of such work, to the requirements of the project documentation approved in accordance with Parts 15, 15.2 and 15.3 of Article 48 of this Code (subject to changes made to the project documentation in accordance with parts 3.8 and 3.9 of Article 49 of this Code) and (or) information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of this Code), including energy efficiency requirements (with the exception of capital construction facilities to which energy efficiency requirements do not apply) and requirements for equipping the capital construction facility with metering devices for energy resources used; 2. Availability of a building permit. 3. Compliance with the requirements of Parts 2.3 and 3.1 of art.52 of the Urban Planning Code of the Russian Federation.


# 742005239178
Unscheduled inspection
Start date: 2020-11-26, end date: —, duration:
Authority:
Purpose of inspection:


# 741903902754
Unscheduled inspection
Start date: 2019-10-30, end date: 2019-11-06, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the roof installation work completion bricklaying of partitions finishing of facade surfaces laying of internal engineering systems the beginning and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of this Code, taking into account the changes made to the project documentation in accordance with in accordance with parts 38 and 39 of Article 49 of this Code and or the information model, if the formation and maintenance of an information model are mandatory in accordance with the requirements of this Code, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply and the requirements for equipping the capital construction facility with metering devices for energy resources used2 The availability of permits for construction 3 Meeting the requirements of HH 23 and 31 st52 of the Urban Planning Code of the Russian Federation


# 001902865915
Unscheduled inspection
Start date: 2019-07-15, end date: 2019-07-16, duration:
Authority: Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This check is carried out in order to verify the fulfillment of the items previously issued in the order from 22022019 H183r, the deadline for which has expired, The objectives of this check are to implement measures to monitor the elimination of violations specified in the paragraphs of the order from 22022019 H183r


# 741902512295
Unscheduled inspection
Start date: 2019-02-21, end date: 2019-02-27, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the work performed during the installation of the building frame, the walls and parapets of the 4th floor with the brickwork of the walls and partitions and the construction materials used during the construction of the capital construction facility, as well as the results of the design documentation 2 Availability of a construction permit 3 Compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation


# 741802026386
Unscheduled inspection
Start date: 2018-11-07, end date: 2018-11-13, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the work performed during the installation of the 2nd floor building frame and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of the technical regulations of the project documentation 2 Availability of a construction permit 3 Compliance with the requirements of hh 23 and 31 st52 Urban Planning Code of the Russian Federation


# 741800965046
Unscheduled inspection
Start date: 2018-09-12, end date: 2018-09-18, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the work performed during the installation of the 2nd floor building frame and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of the technical regulations of the project documentation 2 Availability of a construction permit 3 Compliance with the requirements of hh 23 and 31 st52 Urban Planning Code of the Russian Federation


# 741800525721
Unscheduled inspection
Start date: 2018-07-17, end date: —, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection:


# 74170701629947
Unscheduled inspection
Start date: 2017-05-24, end date: 2017-05-30, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the work on the installation of internal engineering systems and the construction materials used during the construction of a capital construction facility, as well as the results of such work, with the requirements of the technical regulations of the project documentation2 Availability of a construction permit 3 Compliance with the requirements of hr 23 st52 of the Urban Planning Code of the Russian Federation


# 74160701251343
Unscheduled inspection
Start date: 2016-12-26, end date: 2016-12-30, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 The compliance of the work on the foundations of the walls of the floors of the underground part of the end of the walls of the 1st floor and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of the technical regulations of the project documentation2 The availability of a construction permit3 Compliance with the requirements of hh 23 st52 of the Urban Planning Code of the Russian Federation


# 74160701251253
Unscheduled inspection
Start date: 2016-12-26, end date: 2016-12-30, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 The compliance of the work on the installation of external engineering networks, the completion and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of the technical regulations of the project documentation2 The availability of a construction permit3 Compliance with the requirements of hh 23 st52 of the Urban Planning Code of the Russian Federation


# 74160701131978
Unscheduled inspection
Start date: 2016-11-28, end date: 2016-12-02, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1The compliance of the work on the installation of external and internal engineering networks heating lighting landscaping to asphalt and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of the technical regulations of the project documentation2the receipt of a construction permit3the fulfillment of the requirements of hh 23 st52 of the Urban Planning Code of the Russian Federation


# 74160701132014
Unscheduled inspection
Start date: 2016-11-28, end date: 2016-12-02, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 The compliance of the work on the foundations of the walls of the underground part of axis 12 and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of the technical regulations of the project documentation2 The availability of a construction permit3 Compliance with the requirements of hh 23 st52 of the Urban Planning Code of the Russian Federation


# 74160700321368
Unscheduled inspection
Start date: 2016-09-12, end date: —, duration:
Authority:
Purpose of inspection:


# 74160601781624
Unscheduled inspection
Start date: 2016-08-22, end date: 2016-08-26, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the work on the roof, floors, warehouse landscaping, Walls, columns and floors of the underground part of the ABK and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of the technical regulations of the project documentation2 Availability of a construction permit3 Compliance with the requirements of hh 23 st52 of the Urban Planning Code of the Russian Federation


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.