Found 22 inspections:

# 002004376233
Unscheduled inspection
Start date: 2020-04-28, end date: 2020-04-30, duration: 3
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is carried out in order to verify the implementation of the measures provided for in paragraphs 112 of the previously issued regulation 15097 ET dated 06092019, the deadline for which expires on 270-42020the purpose of this audit is to verify the actual fulfillment of the mandatory requirements specified in the regulation within the prescribed time frame. The purpose of this audit is to comply with the instructions of the state control supervision body


# 002004376460
Unscheduled inspection
Start date: 2020-04-30, end date: 2020-05-12, duration: 5
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is carried out in order to verify the implementation of the measures provided for in paragraphs 122 of the previously issued regulation 15001 ET dated 17012020, the deadline for which expires on 29042020the purpose of this audit is to verify the actual fulfillment of the mandatory requirements specified in the regulation within the prescribed time frame. The purpose of this audit is to comply with the instructions of the state control supervision authority


# 001902331560
Unscheduled inspection
Start date: 2019-01-14, end date: 2019-01-18, duration: 5
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the audit is carried out in order to verify the implementation of the measures provided for in paragraphs 1 2 5 8 of the previously issued regulation 15205T dated 22102018, the deadline for which expires on 11/12/2019. The purpose of this audit is to verify the actual fulfillment of the mandatory requirements specified in the regulation within the established time frame. The subject of this audit is the fulfillment of the regulation of the state control supervision body


# 001800608434
Unscheduled inspection
Start date: 2018-08-13, end date: 2018-08-17, duration:
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this inspection is carried out in order to verify the progress of the preparation of heat supply facilities for operation in the autumn winter period 20182019 in accordance with the order of the Federal Service for Environmental Technological and Nuclear Supervision dated 16072018 308 and the instructions of the Deputy Chairman of the Government of the Russian Federation VL Mutko dated June 26, 2018 VMP93773 "On monitoring the progress of preparation and assessment of the readiness of heat supply facilities for operation in the autumn winter period 20182019" The objectives of this audit are to verify the progress of the preparation of heat supply facilities for operation in the autumn-winter period 20182019. The subject of this audit is compliance with the requirements of Federal laws and other normative legal acts of the Russian Federation in preparation for the autumn-winter period 20182019


# 00150601022385
Unscheduled inspection
Start date: 2015-10-05, end date: 2015-10-08, duration:
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the implementation of measures provided for by the previously issued regulation No. 150190 dated 17102014


# 242101543848
Unscheduled inspection
Start date: 2021-08-17, end date: —, duration:
Authority:
Purpose of inspection:


# 242100411945
Unscheduled inspection
Start date: 2021-08-17, end date: —, duration: 20
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: Purpose: to verify the fulfillment of the previously issued to the person being checked Regulation No.145-pr dated 06/11/2021 on the elimination of identified violations at the housing facility(s), the deadline for which expires on 08/16/2021. The objectives of this audit are: to establish the fact of elimination previously identified violations, verification of the work actually performed in accordance with the prescribed measures within the prescribed period. The subject of this audit is the fulfillment of the legal requirement of the regulation(s) of the body carrying out state regional housing supervision.


# 242100236191
Unscheduled inspection
Start date: 2021-05-17, end date: —, duration: 20
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: Purpose: to verify the fulfillment of the previously issued to the person being checked Regulation No. 75-GZHN dated 03/22/2021 on the elimination of identified violations at the housing facility(s), the deadline for which expires on 05/14/2021; Task: to establish the fact of the elimination of previously identified violations, to verify the actual work performed in accordance with the prescribed measures within the prescribed period.; Subject: compliance with the legal requirement of the regulation(s) of the body carrying out state regional housing supervision.


# 242101528156
Unscheduled inspection
Start date: 2021-03-17, end date: 2021-04-05, duration: 14
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: verification of the execution of the order No. 50-z dated 02.02.2021, previously issued to the person being checked, on the elimination of identified violations at the housing facility(s), the deadline for which expires on 05.03.2021.establishment of the fact of elimination of previously identified violations, verification of the work actually performed in accordance with the prescribed measures within the prescribed period.Compliance with the regulations of state control (supervision) bodies and municipal control bodies


# 242101528054
Unscheduled inspection
Start date: 2021-03-17, end date: —, duration: 14
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: purpose: to verify the fulfillment of the previously issued to the person being checked regulation No. 50-z dated 02.02.2021 on the elimination of identified violations at the housing facility(s), the deadline for which expires 05.03.2021. The objectives of this audit are: to establish the fact of the elimination of previously identified violations, to verify the actual work performed in accordance with the prescribed measures within the prescribed period. 7. The subject of this audit is the fulfillment of the legal requirement of the regulation(s) of the body carrying out state regional housing supervision.


# 242100078337
Unscheduled inspection
Start date: 2021-03-04, end date: 2021-04-01, duration: 20
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: in order to assess the compliance of the actions (inaction) of a legal entity with mandatory requirements, based on the memo of the head of the territorial division for the western group of districts O.I. Slobodyan dated 02.26.2021 No. 42/21-ZTP on violations of the timing and frequency of information posting in the state housing and communal services GIS housing and communal services. The objectives of this audit are: prevention, detection and suppression of violations of the requirements established by housing legislation.


# 242105321513
Unscheduled inspection
Start date: 2021-01-25, end date: —, duration:
Authority:
Purpose of inspection:


# 002004376233
Unscheduled inspection
Start date: 2020-04-28, end date: 2020-04-30, duration: 3
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is carried out in order to verify the implementation of the measures provided for in paragraphs 112 of the previously issued regulation 15097 ET dated 06092019, the deadline for which expires on 270-42020the purpose of this audit is to verify the actual fulfillment of the mandatory requirements specified in the regulation within the prescribed time frame. The purpose of this audit is to comply with the instructions of the state control supervision body


# 002004376460
Unscheduled inspection
Start date: 2020-04-30, end date: 2020-05-12, duration: 5
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is carried out in order to verify the implementation of the measures provided for in paragraphs 122 of the previously issued regulation 15001 ET dated 17012020, the deadline for which expires on 29042020the purpose of this audit is to verify the actual fulfillment of the mandatory requirements specified in the regulation within the prescribed time frame. The purpose of this audit is to comply with the instructions of the state control supervision authority


# 002004127495
Unscheduled inspection
Start date: 2020-01-13, end date: 2020-01-17, duration: 5
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is carried out in order to verify the implementation of the measures provided for in paragraphs 199 of the previously issued regulation 150971 ET dated 06092019, the deadline for which expires on 30122019the purpose of this audit is to verify the actual fulfillment of the mandatory requirements specified in the regulation within the prescribed time frame. The purpose of this audit is to comply with the instructions of the state control supervision authority


# 001902886468
Unscheduled inspection
Start date: 2019-08-26, end date: 2019-09-06, duration: 10
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The inspection is carried out in order to comply with the order of the Federal Service for Environmental, Technological and Nuclear Supervision dated 0102201944 "On conducting inspections of compliance by electric power industry entities, heat supply organizations, heating grid organizations and Consumers of electric Energy in 2019" issued on the basis of the instruction of the Deputy Chairman of the Government of the Russian Federation dated January 18, 2019 DKP9274


# 001902331560
Unscheduled inspection
Start date: 2019-01-14, end date: 2019-01-18, duration: 5
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the audit is carried out in order to verify the implementation of the measures provided for in paragraphs 1 2 5 8 of the previously issued regulation 15205T dated 22102018, the deadline for which expires on 11/12/2019. The purpose of this audit is to verify the actual fulfillment of the mandatory requirements specified in the regulation within the established time frame. The subject of this audit is the fulfillment of the regulation of the state control supervision body


# 001801785620
Unscheduled inspection
Start date: 2018-10-16, end date: 2018-10-22, duration:
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is carried out in order to verify the implementation of measures provided for by the previously issued regulation 15 149 T dated 17082018, the deadline for which expires on 08102018. The purpose of this audit is to verify the actual fulfillment of the mandatory requirements specified in the regulation within the established time frame. The subject of this audit is the fulfillment of the order of the state control supervision body


# 001800608434
Unscheduled inspection
Start date: 2018-08-13, end date: 2018-08-17, duration:
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this inspection is carried out in order to verify the progress of the preparation of heat supply facilities for operation in the autumn winter period 20182019 in accordance with the order of the Federal Service for Environmental Technological and Nuclear Supervision dated 16072018 308 and the instructions of the Deputy Chairman of the Government of the Russian Federation VL Mutko dated June 26, 2018 VMP93773 "On monitoring the progress of preparation and assessment of the readiness of heat supply facilities for operation in the autumn winter period 20182019" The objectives of this audit are to verify the progress of the preparation of heat supply facilities for operation in the autumn-winter period 20182019. The subject of this audit is compliance with the requirements of Federal laws and other normative legal acts of the Russian Federation in preparation for the autumn-winter period 20182019


# 24160601555553
Unscheduled inspection
Start date: 2016-03-14, end date: 2016-04-08, duration:
Authority: Mezhregionalnoe upravlenie gosavtodornadzora po Krasnoyarskomu krayu Respublike Tyva i Respublike Hakasiya
Purpose of inspection: verification of the execution of regulation 18 of 29.0116


# 00150601022385
Unscheduled inspection
Start date: 2015-10-05, end date: 2015-10-08, duration:
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the implementation of measures provided for by the previously issued regulation No. 150190 dated 17102014


# 24150600016028
Unscheduled inspection
Start date: 2015-08-03, end date: 2015-08-28, duration:
Authority: Glavnoe upravlenie MCHS Rossii po Krasnoyarskomu krayu
Purpose of inspection: control over the execution of the order issued earlier by the OND for Birilyussky and Bolsheuluysky districts of the Main Directorate of the Ministry of Emergency Situations of Russia for the Krasnoyarsk Territory on the elimination of violations of fire safety requirements on the implementation of measures to ensure fire safety at protection facilities and to prevent the threat of fire dated 08082014 107118


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.