# 742101395238
Unscheduled inspection
Start date: 2021-12-03, end date: —, duration: —
Authority: —
Purpose of inspection:
# 742101338507
Unscheduled inspection
Start date: 2021-11-24, end date: —, duration: —
Authority: —
Purpose of inspection:
# 742101223982
Unscheduled inspection
Start date: 2021-10-29, end date: 2021-11-08, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1. Sootvetstvie vypolneniya rabot po ustanovke dverei, otdelochnym rabotam, blagoustroistvu, ustanovke MAF i primenyaemyh stroitelnyh materialov v processe stroitelstva, rekonstrukcii obekta kapitalnogo stroitelstva, a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15, 15.2 i 15.3 stati 48 nastoyaschego Kodeksa proektnoi dokumentacii (s uchetom izmenenii, vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 3.8 i 3.9 stati 49 nastoyaschego Kodeksa) i (ili) informacionnoi modeli (v sluchae, esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami nastoyaschego Kodeksa), v tom chisle trebovaniyam energeticheskoi effektivnosti (za isklyucheniem obektov kapitalnogo stroitelstva, na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya) i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov. 2. Nalichie razresheniya na stroitelstvo. 3. Vypolnenie trebovanii ch.ch. 2,3 i 3.1 st.52 Gradostroitelnogo kodeksa RF.
# 742100771339
Unscheduled inspection
Start date: 2021-09-28, end date: —, duration: —
Authority: —
Purpose of inspection:
# 742100492353
Unscheduled inspection
Start date: 2021-08-24, end date: —, duration: —
Authority: —
Purpose of inspection:
# 742100278288
Unscheduled inspection
Start date: 2021-06-15, end date: 2021-06-21, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1. Proverka ispolneniya predpisaniya ot 31.03.2021g., srok ispolneniya 31.05.2021. 2. Nalichie razresheniya na stroitelstvo. 3. Vypolnenie trebovanii ch.ch. 2,3 i 3.1 st.52 Gradostroitelnogo kodeksa RF.
# 742100217806
Unscheduled inspection
Start date: 2021-05-26, end date: —, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection:
# 742100059096
Unscheduled inspection
Start date: 2021-03-25, end date: 2021-03-31, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1. Sootvetstvie vypolneniya rabot po ustroistvu krovli, ustanovke okonnyh i dvernyh konstrukcii, vnutrennih inzhenernyh sistem 2 i 3 etazha (v processe vypolneniya rabot) i primenyaemyh stroitelnyh materialov v processe stroitelstva, rekonstrukcii obekta kapitalnogo stroitelstva, a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15, 15.2 i 15.3 stati 48 nastoyaschego Kodeksa proektnoi dokumentacii (s uchetom izmenenii, vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 3.8 i 3.9 stati 49 nastoyaschego Kodeksa) i (ili) informacionnoi modeli (v sluchae, esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami nastoyaschego Kodeksa), v tom chisle trebovaniyam energeticheskoi effektivnosti (za isklyucheniem obektov kapitalnogo stroitelstva, na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya) i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov. 2. Nalichie razresheniya na stroitelstvo. 3. Vypolnenie trebovanii ch.ch. 2,3 i 3.1 st.52 Gradostroitelnogo kodeksa RF.
# 742005229236
Unscheduled inspection
Start date: 2020-11-24, end date: —, duration: —
Authority: —
Purpose of inspection:
# 742004444132
Unscheduled inspection
Start date: 2020-07-03, end date: 2020-07-09, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Sootvetstvie vypolneniya rabot po ustroistvu monolitnogo karkasa 5 etazha naruzhnyh inzhenernyh setei v processe vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15 152 i 153 stati 48 nastoyaschego Kodeksa proektnoi dokumentacii s uchetom izmenenii vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 38 i 39 stati 49 nastoyaschego Kodeksa i ili informacionnoi modeli v sluchae esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami nastoyaschego Kodeksa v tom chisle trebovaniyam energeticheskoi effektivnosti za isklyucheniem obektov kapitalnogo stroitelstva na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov2 Nalichie razresheniya na stroitelstvo3 Vypolnenie trebovanii chch 23 i 31 st52 Gradostroitelnogo kodeksa RF
# 742004354806
Unscheduled inspection
Start date: 2020-03-27, end date: —, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection:
# 742004216919
Unscheduled inspection
Start date: 2020-01-23, end date: 2020-01-29, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Proverka ispolneniya predpisaniya ob ustranenii narushenii pri stroitelstve rekonstrukcii obekta kapitalnogo stroitelstva ot 22112019 g2 Nalichie razresheniya na stroitelstvo3 Vypolnenie trebovanii ch ch 2 3 i 31 st52 Gradostroitelnogo kodeksa RF
# 741903972755
Unscheduled inspection
Start date: 2019-11-18, end date: —, duration: —
Authority: —
Purpose of inspection:
# 741903000491
Unscheduled inspection
Start date: 2019-08-21, end date: 2019-09-17, duration: —
Authority: Gosudarstvennaya inspekciya truda v CHelyabinskoi oblasti
Purpose of inspection: Osuschestvlenie federalnogo gosudarstvennogo nadzora za soblyudeniem yuridicheskim licom ili individualnym predprinimatelem obyazatelnyh trebovanii trudovogo zakonodatelstva i inyh normativnyh pravovyh aktov soderzhaschih normy trudovogo prava Pismo iz organa pravoohranitelnoi sistemy 74482219PV ot 19082019 smertelnom nsluchae na obekte SMR
# 741902540581
Unscheduled inspection
Start date: 2019-03-01, end date: 2019-03-07, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Proverka ispolneniya predpisaniya ob ustranenii narushenii pri stroitelstve rekonstrukcii obekta kapitalnogo stroitelstva ot 31102018 g 2 Nalichie razresheniya na stroitelstvo 3 Vypolnenie trebovanii chch 23 i 31 st52 Gradostroitelnogo kodeksa RF
# 741802129561
Unscheduled inspection
Start date: 2018-11-26, end date: 2018-11-30, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Sootvetstvie vypolneniya rabot po ustroistvu monolitnogo karkasa zdaniya 12 etazhi v processe vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii 2 Nalichie razresheniya na stroitelstvo 3 Vypolnenie trebovanii chch 23 i 31 st52 Gradostroitelnogo kodeksa RF
# 741801997917
Unscheduled inspection
Start date: 2018-10-25, end date: —, duration: —
Authority: —
Purpose of inspection:
# 741801549359
Unscheduled inspection
Start date: 2018-09-27, end date: 2018-10-03, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Sootvetstvie vypolneniya rabot po ustroistvu monolitnyh fundamentov posle vypolneniya rabot rabot po ustroistvu monolitnogo karkasa zdaniya 12 etazhi v processe vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii 2 Nalichie razresheniya na stroitelstvo 3 Vypolnenie trebovanii chch 23 i 31 st52 Gradostroitelnogo kodeksa RF
# 741800637161
Unscheduled inspection
Start date: 2018-08-23, end date: —, duration: —
Authority: —
Purpose of inspection:
# 741800552852
Unscheduled inspection
Start date: 2018-07-19, end date: 2018-07-25, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Sootvetstvie vypolneniya rabot po organizacii stroitelnoi ploschadki zemlyanyh rabot rabot po vdavlivaniyu svai v processe vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii 2 Proverka vypolneniya predpisaniya ob ustranenii narushenii pri stroitelstve rekonstrukcii obekta kapitalnogo stroitelstva ot 30 maya 2018 goda 3 Nalichie razresheniya na stroitelstvo 4 Vypolnenie trebovanii chch 23 i 31 st52 Gradostroitelnogo kodeksa RF
# 741800364279
Unscheduled inspection
Start date: 2018-05-17, end date: 2018-05-30, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: Proverka svedenii izlozhennyh v zayavlenii YUsupovoi LS gr Klenina SM perenanapravlennom v URGSN prokuraturoi Leninskogo raiona g Magnitogorska vh 07318 ot 26042018 g Vyyavlenie i presechenie narushenii gradostroitelnogo zakonodatelstva Soblyudenie obyazatelnyh trebovanii ili trebovanii ustanovlennyh municipalnymi pravovymi aktami Predotvraschenie prichineniya vreda zhizni zdorovyu grazhdan vreda zhivotnym rasteniyam okruzhayuschei srede
# 741800214630
Unscheduled inspection
Start date: 2018-03-16, end date: —, duration: —
Authority: —
Purpose of inspection:
# 74170802875077
Unscheduled inspection
Start date: 2017-11-28, end date: 2017-12-04, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1The compliance of the work performed during the installation of the metal structures of the tribune of sector A and the building materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations of the project documentation2the presence of a construction permit 3The fulfillment of the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation
# 74170802708126
Unscheduled inspection
Start date: 2017-10-18, end date: 2017-10-24, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1The compliance of the work performed during the installation of the metal structures of the tribune of sector B and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations of the project documentation2the presence of a construction permit 3The fulfillment of the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation
# 74170802519846
Unscheduled inspection
Start date: 2017-09-25, end date: 2017-09-29, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1The compliance of the work performed during the installation of the metal structures of the tribune of sector A and the building materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations of the project documentation2the presence of a construction permit 3The fulfillment of the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation
# 74160701061223
Unscheduled inspection
Start date: 2016-11-10, end date: —, duration: —
Authority: —
Purpose of inspection:
# 74160701020227
Unscheduled inspection
Start date: 2016-10-20, end date: 2016-10-26, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1The compliance of earthworks with the complex of works on the installation of foundations before the completion of work and the construction materials used during the construction of a capital construction facility, as well as the results of such work, with the requirements of technical regulations of project documentation2the presence of a construction permit 3The fulfillment of the requirements of hh 23 st52 of the Urban Planning Code of the Russian Federation