# 001904426576
Unscheduled inspection
Start date: 2019-08-20, end date: 2019-08-22, duration: 20
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the progress of preparation of heat supply facilities for operation in the autumn winter period of 2019-2020 pursuant to the order of the Federal Service for Environmental Technological and Nuclear Supervision dated 04072019 261 and the instruction of the Government of the Russian Federation dated June 19, 2019 VMP95084 "On monitoring the progress of preparation and assessment of the readiness of heat supply facilities for operation in the autumn winter period of 2019-2020"The objectives of this audit are to verify the progress of the preparation of heat supply facilities for operation in the autumn winter period of 2019-2020. The purpose of this audit is to ensure that Municipal Unitary Enterprise Housing and Communal Services "Zheleznodorozhnik" complies with the requirements of Federal laws and other regulatory legal acts of the Russian Federation when preparing for the autumn winter period of 2019-2020
# 001801900473
Unscheduled inspection
Start date: 2018-10-08, end date: 2018-10-12, duration: —
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the implementation of the measures provided for in paragraphs 1 2 3 4 5 6 7 8 9 of the previously issued prescription within the established time frame
# 001800604568
Unscheduled inspection
Start date: 2018-08-06, end date: 2018-08-31, duration: —
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to check the progress of the preparation of heat supply facilities for operation in the autumn winter period 2018-2019 in accordance with the order of the Federal Service for Environmental Technological and Nuclear Supervision dated 16072018 308 and the instruction of Deputy Prime Minister of the Russian Federation Vladimir Mutko dated June 26, 2018 VMP93773 "On monitoring the preparation and assessment of the readiness of heat supply facilities for operation in the autumn winter period 2018-2019". The purpose of this audit is to check the progress of the preparation of heat supply facilities for operation in the autumn winter period of 2018-2019. The subject of this audit is compliance with the requirements of Federal laws and other regulatory legal acts of the Russian Federation in preparation for the autumn winter period of 2018-2019
# 00170802886003
Unscheduled inspection
Start date: 2017-11-23, end date: 2017-11-24, duration: —
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of the implementation of measures provided for in p1 of the previously issued regulation 18220ET
# 00150601269081
Unscheduled inspection
Start date: 2015-10-12, end date: 2015-10-16, duration: —
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the implementation of the measures provided for by the previously issued prescription
# 001904426576
Unscheduled inspection
Start date: 2019-08-20, end date: 2019-08-22, duration: 20
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the progress of preparation of heat supply facilities for operation in the autumn winter period of 2019-2020 pursuant to the order of the Federal Service for Environmental Technological and Nuclear Supervision dated 04072019 261 and the instruction of the Government of the Russian Federation dated June 19, 2019 VMP95084 "On monitoring the progress of preparation and assessment of the readiness of heat supply facilities for operation in the autumn winter period of 2019-2020"The objectives of this audit are to verify the progress of the preparation of heat supply facilities for operation in the autumn winter period of 2019-2020. The purpose of this audit is to ensure that Municipal Unitary Enterprise Housing and Communal Services "Zheleznodorozhnik" complies with the requirements of Federal laws and other regulatory legal acts of the Russian Federation when preparing for the autumn winter period of 2019-2020
# 191902810395
Unscheduled inspection
Start date: 2019-06-18, end date: 2019-07-15, duration: —
Authority: Gosudarstvennaya inspekciya truda v Respublike Hakasiya
Purpose of inspection: Control over the execution by a legal entity or individual entrepreneur of a previously issued order to eliminate an identified violation of mandatory labor requirements for which the Order 1912155619 has expired
# 191902762580
Unscheduled inspection
Start date: 2019-06-05, end date: —, duration: —
Authority: —
Purpose of inspection:
# 191902590136
Unscheduled inspection
Start date: 2019-03-27, end date: 2019-04-23, duration: —
Authority: Gosudarstvennaya inspekciya truda v Respublike Hakasiya
Purpose of inspection: Implementation of federal state supervision over compliance by a legal entity or an individual entrepreneur with the mandatory requirements of labor legislation and other regulatory legal acts containing labor law norms
# 191802210611
Unscheduled inspection
Start date: 2018-12-07, end date: 2019-01-11, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po Respublike Hakasiya
Purpose of inspection: verification of the fulfillment of the previously issued regulation 317SZ dated 18052018
# 001801900473
Unscheduled inspection
Start date: 2018-10-08, end date: 2018-10-12, duration: —
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the implementation of the measures provided for in paragraphs 1 2 3 4 5 6 7 8 9 of the previously issued prescription within the established time frame
# 001800604568
Unscheduled inspection
Start date: 2018-08-06, end date: 2018-08-31, duration: —
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to check the progress of the preparation of heat supply facilities for operation in the autumn winter period 2018-2019 in accordance with the order of the Federal Service for Environmental Technological and Nuclear Supervision dated 16072018 308 and the instruction of Deputy Prime Minister of the Russian Federation Vladimir Mutko dated June 26, 2018 VMP93773 "On monitoring the preparation and assessment of the readiness of heat supply facilities for operation in the autumn winter period 2018-2019". The purpose of this audit is to check the progress of the preparation of heat supply facilities for operation in the autumn winter period of 2018-2019. The subject of this audit is compliance with the requirements of Federal laws and other regulatory legal acts of the Russian Federation in preparation for the autumn winter period of 2018-2019
# 191800343739
Unscheduled inspection
Start date: 2018-05-04, end date: 2018-06-01, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po Respublike Hakasiya
Purpose of inspection: verification of the execution of previously issued regulations 210OSN dated 28042017, the deadline for which expired 28042018 regulations 622SZ dated 21082017, the deadline for which expired 06032018
# 00170802886003
Unscheduled inspection
Start date: 2017-11-23, end date: 2017-11-24, duration: —
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of the implementation of measures provided for in p1 of the previously issued regulation 18220ET
# 19170701882728
Unscheduled inspection
Start date: 2017-08-10, end date: 2017-09-06, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po Respublike Hakasiya
Purpose of inspection: verification of the execution of p2 of the previously issued regulation 1189SZ dated 20012017, the deadline for which expired 03072017
# 19160701261240
Unscheduled inspection
Start date: 2016-12-23, end date: —, duration: —
Authority: —
Purpose of inspection:
# 00160601746192
Unscheduled inspection
Start date: 2016-09-08, end date: 2016-09-09, duration: —
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: checking the progress of preparation of electric power and heat supply facilities for operation in the autumn-winter period of 2016-2017
# 00150601269081
Unscheduled inspection
Start date: 2015-10-12, end date: 2015-10-16, duration: —
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the implementation of the measures provided for by the previously issued prescription
# 19150600735533
Unscheduled inspection
Start date: 2015-08-26, end date: —, duration: —
Authority: —
Purpose of inspection: