# 63170802927961
Unscheduled inspection
Start date: 2017-12-04, end date: —, duration: —
Authority: —
Purpose of inspection:
# 63170802873460
Unscheduled inspection
Start date: 2017-11-22, end date: 2017-11-24, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Programma provedeniya proverok ot 13112017 izveschenie ot 14112017 5013 Proverka sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov inyh normativnyh pravovyh aktov i proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov
# 63170802623788
Unscheduled inspection
Start date: 2017-10-05, end date: —, duration: —
Authority: —
Purpose of inspection:
# 63170802729585
Unscheduled inspection
Start date: 2017-10-16, end date: 2017-11-03, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Predpisanie ot 22092017 02234551 izveschenie ot 09102017 4277 Vypolnenie ranee vydannogo predpisaniya
# 63170802729792
Unscheduled inspection
Start date: 2017-10-17, end date: 2017-10-20, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Programma provedeniya proverok ot 14072015 izveschenie ot 09102017 4268 Proverka sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov inyh normativnyh pravovyh aktov i proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov
# 63170802429477
Unscheduled inspection
Start date: 2017-09-15, end date: —, duration: —
Authority: —
Purpose of inspection:
# 63170802419391
Unscheduled inspection
Start date: 2017-09-15, end date: 2017-09-22, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Programma provedeniya proverok ot 14072015 izveschenie ot 07092017 3742 Proverka sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov inyh normativnyh pravovyh aktov i proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov
# 63170701681595
Unscheduled inspection
Start date: 2017-07-03, end date: —, duration: —
Authority: —
Purpose of inspection:
# 63170701686407
Unscheduled inspection
Start date: 2017-06-13, end date: 2017-06-23, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Programma provedeniya proverok ot 28092016 izveschenie ot 31052017 2026Proverka sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov inyh normativnyh pravovyh aktov i proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov
# 63170701672898
Unscheduled inspection
Start date: 2017-06-06, end date: 2017-06-06, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Programma provedeniya proverok ot 30072014 izveschenie ot 30052017 2016 Proverka sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov inyh normativnyh pravovyh aktov i proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov
# 63170701591915
Unscheduled inspection
Start date: 2017-05-15, end date: 2017-05-19, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Predpisanie ot 31032017 02231181Vypolnenie ranee vydannogo predpisaniya
# 63170701468056
Unscheduled inspection
Start date: 2017-03-22, end date: —, duration: —
Authority: —
Purpose of inspection:
# 63170701456662
Unscheduled inspection
Start date: 2017-03-21, end date: 2017-03-31, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Programma provedeniya proverok ot 28092016 izveschenie ot 09032017 792 Proverka sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov inyh normativnyh pravovyh aktov i proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov
# 63170701365830
Unscheduled inspection
Start date: 2017-02-13, end date: —, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection:
# 63170701284218
Unscheduled inspection
Start date: 2017-01-10, end date: 2017-01-25, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Programma provedeniya proverok ot 18052015 izveschenie ot 26122016 7278 Proverka sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov inyh normativnyh pravovyh aktov i proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov
# 63170701318151
Unscheduled inspection
Start date: 2017-01-25, end date: 2017-01-31, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Programma provedeniya proverok ot 28092016 izveschenie ot 12012017 116 Proverka sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov inyh normativnyh pravovyh aktov i proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov
# 63160701208152
Unscheduled inspection
Start date: 2016-12-08, end date: 2016-12-12, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 63160701200894
Unscheduled inspection
Start date: 2016-12-08, end date: —, duration: —
Authority: —
Purpose of inspection:
# 63160701265210
Unscheduled inspection
Start date: 2016-12-27, end date: —, duration: —
Authority: —
Purpose of inspection:
# 63160701208206
Unscheduled inspection
Start date: 2016-12-07, end date: 2016-12-15, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 63160701199668
Unscheduled inspection
Start date: 2016-12-07, end date: 2016-12-23, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 63160701162936
Unscheduled inspection
Start date: 2016-12-01, end date: 2016-12-09, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: fulfillment of a previously issued prescription
# 63160701162781
Unscheduled inspection
Start date: 2016-12-01, end date: —, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection:
# 63160701090021
Unscheduled inspection
Start date: 2016-11-15, end date: 2016-11-25, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 63160700984407
Unscheduled inspection
Start date: 2016-10-17, end date: 2016-10-31, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 63160700984146
Unscheduled inspection
Start date: 2016-10-17, end date: —, duration: —
Authority: —
Purpose of inspection:
# 63160700951338
Unscheduled inspection
Start date: 2016-10-17, end date: 2016-10-21, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 63160700951124
Unscheduled inspection
Start date: 2016-10-17, end date: 2016-10-19, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 63160700951226
Unscheduled inspection
Start date: 2016-10-17, end date: 2016-10-19, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 63160701018181
Unscheduled inspection
Start date: 2016-10-18, end date: —, duration: —
Authority: —
Purpose of inspection:
# 63160700823288
Unscheduled inspection
Start date: 2016-09-23, end date: 2016-09-26, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 63160700837589
Unscheduled inspection
Start date: 2016-09-26, end date: —, duration: —
Authority: —
Purpose of inspection:
# 63160601717214
Unscheduled inspection
Start date: 2016-07-25, end date: 2016-08-05, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 63160601717105
Unscheduled inspection
Start date: 2016-07-25, end date: 2016-08-05, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 63160601723760
Unscheduled inspection
Start date: 2016-07-20, end date: 2016-07-29, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 63160601704006
Unscheduled inspection
Start date: 2016-07-18, end date: 2016-07-29, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used