Found 26 inspections:

# 162101469779
Unscheduled inspection
Start date: 2021-12-14, end date: —, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:


# 162101469348
Unscheduled inspection
Start date: 2021-12-14, end date: —, duration:
Authority:
Purpose of inspection:


# 162101389524
Unscheduled inspection
Start date: 2021-11-24, end date: —, duration:
Authority:
Purpose of inspection:


# 162101389029
Unscheduled inspection
Start date: 2021-11-24, end date: —, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:


# 162100098570
Unscheduled inspection
Start date: 2021-03-30, end date: 2021-04-06, duration: 6
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed, the construction materials used during the construction of the capital construction facility, and the results of such work with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of parts 2, 3, and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 03/25/2021 case No. 12-11-2015/0165. The objectives of this audit are: prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The subject of this audit is (select the appropriate one): compliance with mandatory requirements and (or) requirements established by municipal legal acts;


# 162005234089
Unscheduled inspection
Start date: 2020-11-23, end date: 2020-11-27, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: Determination of the compliance of the completed works applied in the process of construction of the capital construction facility of building materials and the results of such works with the requirements of the design documentation prevention as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, compliance with mandatory requirements or requirements established by municipal legal acts


# 162005202786
Unscheduled inspection
Start date: 2020-10-23, end date: —, duration:
Authority: Gosudarstvennaya inspekciya truda v Respublike Tatarstan
Purpose of inspection:


# 162005145859
Unscheduled inspection
Start date: 2020-10-01, end date: 2020-10-02, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program from 06032020 case 121120150165 The objectives of this inspection are to prevent as well as identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts


# 162005195923
Unscheduled inspection
Start date: 2020-10-26, end date: 2020-10-30, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the reconstruction of the capital construction facility comply with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 23092020 case 140420200015 The objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, the person carrying out reconstruction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts


# 162004480964
Unscheduled inspection
Start date: 2020-08-12, end date: 2020-08-13, duration: 2
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the reconstruction of the capital construction facility comply with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program from 25062020 case 140420200015 The objectives of this inspection are to prevent as well as identify and suppress violations committed by the developer, the customer, the person carrying out the reconstruction on the basis of a contract with the developer or the customer of compliance with the requirements of technical regulations and other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts


# 162004450728
Unscheduled inspection
Start date: 2020-07-15, end date: 2020-07-17, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the reconstruction of the capital construction facility comply with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program from 25062020 case 140420200015 The objectives of this inspection are to prevent as well as identify and suppress violations committed by the developer, the customer, the person carrying out the reconstruction on the basis of a contract with the developer or the customer of compliance with the requirements of technical regulations and other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts


# 162004296212
Unscheduled inspection
Start date: 2020-02-20, end date: 2020-02-28, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 07/122018 case 121120150165 The objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations and other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts


# 161903992118
Unscheduled inspection
Start date: 2019-11-22, end date: 2019-11-27, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 07/122018 case 121120150165the objectives of this inspection are to prevent, identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The purpose of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts


# 161903510116
Unscheduled inspection
Start date: 2019-09-13, end date: 2019-09-16, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the eliminated violations with the requirements of technical regulations, project documentation, other regulations, norms and rules, as well as to draw up an act on the elimination of violations based on the notice received by the Inspectorate dated 29082019 8009 on the elimination of violations during the construction of the reconstruction of the capital construction facility, which was ordered to be eliminated within the time limit set by the regulation from 19082019 1212085001 to 09092019tasks The purpose of this audit is to prevent as well as identify and suppress violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentationthe purpose of this audit is to select the necessary compliance with the instructions of state control bodies, supervision bodies, municipal control bodies.


# 161902962520
Unscheduled inspection
Start date: 2019-08-16, end date: —, duration:
Authority:
Purpose of inspection:


# 161902831656
Unscheduled inspection
Start date: 2019-07-02, end date: 2019-07-04, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 07/122018 case 121120150165the objectives of this inspection are to prevent, identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The purpose of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts


# 161902527007
Unscheduled inspection
Start date: 2019-02-22, end date: 2019-02-26, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 07/122018 case 121120150165 The objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by municipal legal acts


# 161902458705
Unscheduled inspection
Start date: 2019-01-29, end date: —, duration:
Authority:
Purpose of inspection:


# 161802317460
Unscheduled inspection
Start date: 2018-12-17, end date: 2018-12-19, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program dated 07/122018 case 121120150165 The objectives of this inspection are to prevent as well as identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The subject of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by municipal legal acts


# 161801960355
Unscheduled inspection
Start date: 2018-10-19, end date: —, duration:
Authority:
Purpose of inspection:


# 161800413704
Unscheduled inspection
Start date: 2018-06-06, end date: 2018-06-08, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: To establish that this inspection is carried out in order to determine the fact of fulfillment of the order dated 07032018 1719002501, the deadline for which expired on 21052018, and to draw up an act based on the results of the inspection. The objectives of this inspection are to prevent, identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, violations of compliance with the requirements of the works performed during the construction of the capital construction facility. The subject of this audit is to select the necessary compliance with the mandatory requirements and or requirements established by municipal legal acts.


# 161800425518
Unscheduled inspection
Start date: 2018-06-01, end date: 2018-06-29, duration:
Authority: Glavnoe upravlenie MCHS Rossii po Respublike Tatarstan
Purpose of inspection: provision of state services for licensing activities related to the installation, maintenance and repair of fire safety equipment for buildings and structures based on the application of IC Ak Bars LLC dated 25042018 7589


# 16170802897160
Unscheduled inspection
Start date: 2017-12-04, end date: 2017-12-11, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: To establish that this inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation In accordance with the inspection program dated 09102017 case 171120170011, the objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, or the person carrying out construction on the basis of a contract with the developer or the customer. The purpose of this inspection is to select the necessary compliance with mandatory requirements and or the requirements established by municipal legal acts


# 16170802666892
Unscheduled inspection
Start date: 2017-10-05, end date: —, duration:
Authority:
Purpose of inspection:


# 16170701708255
Unscheduled inspection
Start date: 2017-06-14, end date: 2017-06-16, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: To establish that this inspection is carried out in order to determine whether the construction materials used in the construction and reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with energy metering devices, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code In accordance with the inspection program from 17032017 case 171120170011the objectives of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The purpose of this inspection is to select the necessary compliance with mandatory requirements


# 16170701580855
Unscheduled inspection
Start date: 2017-05-15, end date: —, duration:
Authority:
Purpose of inspection:


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.