# 782101317255
Unscheduled inspection
Start date: 2021-10-11, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: b) proverki rabot, ukazannyh v izveschenii lica, osuschestvlyayuschego stroitelstvo, o srokah zaversheniya rabot, kotorye podlezhat proverke
vh. 03-6306/2018-18 ot 16.07.2021 );
v) proverki ustraneniya narushenii obyazatelnyh trebovanii, ukazannyh v izveschenii lica, osuschestvlyayuschego stroitelstvo, ob ustranenii vyyavlennyh narushenii
ot 30.09.2021, vh. 03-6306/2018-17;
z) proverki ispolneniya vydannogo predpisaniya ob ustranenii vyyavlennogo narusheniya № P586-RK-21 ot "30" avgusta 2021 goda, srok ispolneniya kotorogo istek "30" sentyabrya 2021 goda;
a) soblyudenie obyazatelnyh trebovanii, v tom chisle:
sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva, rekonstrukcii obekta kapitalnogo stroitelstva, a takzhe rezultatov takih rabot trebovaniyam proektnoi dokumentacii, v tom chisle trebovaniyam energeticheskoi effektivnosti (za isklyucheniem obektov kapitalnogo stroitelstva, na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya) i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov;
nalichiya razresheniya na stroitelstvo;
vypolneniya trebovanii, ustanovlennyh chastyami 2, 3 i 3.1 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii;
b) vypolnenie predpisanii komiteta gosudarstvennogo stroitelnogo nadzora i
gosudarstvennoi ekspertizy Leningradskoi oblasti;
# 472004446756
Unscheduled inspection
Start date: 2020-07-02, end date: 2020-07-29, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of the works specified in the inspection program The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used parts 2 3 and 31 of Article 52 of the Urban Development Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban development activities committed by the developer, the technical customer, the person carrying out the construction, including technical regulations and project documentation
# 782004237117
Unscheduled inspection
Start date: 2020-01-28, end date: —, duration: —
Authority: —
Purpose of inspection:
# 471902852412
Unscheduled inspection
Start date: 2019-07-04, end date: 2019-07-31, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of the works specified in the notice of the person carrying out the construction on the completion dates of the works that are subject to verification The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the facility capital construction metering devices for energy resources used to comply with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out the construction
# 781800594299
Unscheduled inspection
Start date: 2018-07-30, end date: 2018-08-24, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po g SanktPeterburgu
Purpose of inspection: this inspection is carried out in order to prevent damage to the rights legitimate interests of life or health of citizens, the environment, cultural heritage sites, historical and cultural monuments of the peoples of the Russian Federation, the defense and security of the state, the possibility of which is associated with the implementation by legal entities of activities for the installation, maintenance and repair of fire safety facilities of buildings and structures The objectives of this inspection are to prevent identify and suppress violations by a legal entity, its head and other officials, its authorized representatives of the requirements established by Federal Law No. 04052011 99FZ "On Licensing of certain types of activities" and Decree of the Government of the Russian Federation dated 30122011 1225 "On licensing activities for installation, maintenance and repair of fire safety equipment for buildings and structures" the subject of this audit is compliance with the license applicant the licensee of the licensing requirements for the implementation of activities for the installation maintenance and repair of fire safety equipment for buildings and structures