# 772101382102
Unscheduled inspection
Start date: 2021-11-25, end date: —, duration:
Authority:
Purpose of inspection:


# 772100667119
Unscheduled inspection
Start date: 2021-09-09, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803477013
Unscheduled inspection
Start date: 2019-08-13, end date: 2019-08-20, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77190803458550
Unscheduled inspection
Start date: 2019-07-16, end date: 2019-07-24, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77190803431450
Unscheduled inspection
Start date: 2019-06-04, end date: 2019-06-05, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77190803402681
Unscheduled inspection
Start date: 2019-04-22, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803310615
Unscheduled inspection
Start date: 2018-12-28, end date: 2019-01-28, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803195098
Unscheduled inspection
Start date: 2018-08-07, end date: 2018-08-15, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803109108
Unscheduled inspection
Start date: 2018-03-29, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803072708
Unscheduled inspection
Start date: 2018-01-30, end date: 2018-01-31, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803081869
Unscheduled inspection
Start date: 2018-01-11, end date: 2018-01-12, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance by a legal entity and an individual entrepreneur with mandatory requirements in the process of carrying out activities in the field of industrial safety as well as compliance with mandatory requirements of buildings, premises, structures, technical devices, equipment, materials and ongoing technological processes


# 77180803066552
Unscheduled inspection
Start date: 2018-01-11, end date: —, duration:
Authority:
Purpose of inspection:


# 77170803005819
Unscheduled inspection
Start date: 2017-12-18, end date: —, duration:
Authority:
Purpose of inspection:


# 77170802856495
Unscheduled inspection
Start date: 2017-11-09, end date: —, duration:
Authority:
Purpose of inspection:


# 77170802790805
Unscheduled inspection
Start date: 2017-10-30, end date: 2017-10-31, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77170802015925
Unscheduled inspection
Start date: 2017-09-27, end date: —, duration:
Authority:
Purpose of inspection:


# 77170701768848
Unscheduled inspection
Start date: 2017-06-30, end date: —, duration:
Authority:
Purpose of inspection: