# 162101393379
Unscheduled inspection
Start date: 2021-11-29, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162101393903
Unscheduled inspection
Start date: 2021-11-29, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162101393838
Unscheduled inspection
Start date: 2021-11-29, end date: —, duration: 10
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2, 3 and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 03/22/2021 case No. 17-04-2020/0071. The objectives of this audit are: prevention, as well as identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this review is (select the appropriate one): compliance with mandatory requirements and (or) requirements established by municipal legal acts.
# 162101393975
Unscheduled inspection
Start date: 2021-11-29, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162101393456
Unscheduled inspection
Start date: 2021-11-29, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 162101216841
Unscheduled inspection
Start date: 2021-10-15, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 162100631076
Unscheduled inspection
Start date: 2021-09-07, end date: 2021-01-29, duration: 4
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2, 3 and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 06/11/2021 case No. 12-04-2021/0052.
The objectives of this audit are:
prevention, as well as identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation.
The subject of this audit is (select the appropriate one):
compliance with mandatory requirements and (or) requirements established by municipal legal acts;
# 162100512679
Unscheduled inspection
Start date: 2021-08-23, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 162100512106
Unscheduled inspection
Start date: 2021-08-23, end date: —, duration: 9
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed, the construction materials used during the construction of the capital construction facility, and the results of such work with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of parts 2, 3, and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 03/22/2021 case No. 17-04-2020/0071.
The objectives of this audit are:
prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility.
The subject of this audit is (to choose the appropriate one):
compliance with mandatory requirements and (or) requirements established by municipal legal acts.
# 162100512272
Unscheduled inspection
Start date: 2021-08-23, end date: —, duration: 9
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2, 3 and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 03/22/2021 case No. 17-04-2020/0072.
The objectives of this audit are:
prevention, as well as identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation.
The subject of this audit is (select the appropriate one):
compliance with mandatory requirements and (or) requirements established by municipal legal acts.
# 162100505993
Unscheduled inspection
Start date: 2021-08-23, end date: —, duration: 9
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed, the construction materials used during the construction of the capital construction facility, and the results of such work with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of parts 2, 3, and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 03/22/2021 case No. 17-04-2020/0070.
The objectives of this audit are:
prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility.
The subject of this review is (select the appropriate one): compliance with mandatory requirements and/or requirements established by municipal legal acts.
# 162100505736
Unscheduled inspection
Start date: 2021-08-23, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162100336199
Unscheduled inspection
Start date: 2021-07-06, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 162100336265
Unscheduled inspection
Start date: 2021-07-06, end date: —, duration: 4
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2, 3 and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 03/22/2021 case No. 17-04-2020/0073.
The objectives of this audit are:
prevention, as well as identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation.
The subject of this audit is (select the appropriate one):
compliance with mandatory requirements and (or) requirements established by municipal legal acts.
# 162100336154
Unscheduled inspection
Start date: 2021-07-06, end date: —, duration: 4
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed, the construction materials used during the construction of the capital construction facility, and the results of such work with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of parts 2, 3, and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 03/22/2021 case No. 17-04-2020/0071.
The objectives of this audit are:
prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility.
The subject of this audit is (to choose the appropriate one):
compliance with mandatory requirements and (or) requirements established by municipal legal acts.
# 162100336053
Unscheduled inspection
Start date: 2021-07-06, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 162100335951
Unscheduled inspection
Start date: 2021-07-06, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 162100207216
Unscheduled inspection
Start date: 2021-05-11, end date: —, duration: —
Authority: Gosudarstvennaya inspekciya truda v Respublike Tatarstan
Purpose of inspection:
The purpose of the audit is to protect the rights and interests of employees on the basis of Part 7 of Article 360 of the Labor Code of the Russian Federation.
Verification tasks:
- ensuring the observance and protection of labor rights and freedoms of citizens;
- ensuring the employer's compliance with labor legislation and other regulatory legal acts containing labor law norms;
Subject of verification: compliance with mandatory requirements or requirements established by municipal legal acts