# 742005235819
Unscheduled inspection
Start date: 2020-11-23, end date: 2020-11-27, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance with the work carried out on Insulation of the attic Insulation of the floors of the technical floor Installation of elevators Painting of the facade Installation of Windows Installation of interior doors Installation of entrance doors Installation of internal plumbing networks for heating Installation of ETC. Internal electrical installation of communication networks intercom fire alarm networks Interior finishing works Installation of external plumbing External sewerage External heating networks Landscaping Landscaping Installation of IAF during the execution of the work and the construction materials used during the construction reconstruction of the capital construction facility, as well as the results of such work, the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of this Code, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of this Code and or the information model in the case of if the formation and maintenance of an information model are mandatory in accordance with the requirements of this Code, including energy efficiency requirements, with the exception of capital construction facilities to which energy efficiency requirements do not apply, and the requirements for equipping the capital construction facility with metering devices for used energy resources 2 Availability of a construction permit 3 Compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation
# 742005189500
Unscheduled inspection
Start date: 2020-10-27, end date: 2020-11-02, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the work on the installation of the attic after completion of work Installation of deflectors Insulation of the attic Insulation of the floors of the technical floor Installation of panel seams Installation of elevators Facade painting Installation of windows Installation of interior doors Installation of entrance doors Installation of internal networks of water supply sewerage heating Installation ETC Internal electrical work Installation of communication networks intercom networks fire alarm Internal finishing work Outdoor plumbing Device Outdoor sewerage device external heat supply networks Landscaping Landscaping works Installation of IAF during the execution of works and construction materials used during the construction reconstruction of a capital construction facility as well as the results of such work to the requirements of the project documentation approved in accordance with Parts 15 152 and 153 of Article 48 of this Code, taking into account the changes made to the project documentation in accordance with parts 38 and 39 Article 49 of this Code and or an information model if the formation and maintenance of an information model are mandatory in accordance with the requirements of this Code, including energy efficiency requirements, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for energy resources used 2 Availability of a construction permit 3 Performance requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation