Found 6 inspections:

# 771800685266
Unscheduled inspection
Start date: 2018-08-30, end date: 2017-09-26, duration:
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po gorodu Moskve
Purpose of inspection: ocenki sootvetstviya yuridicheskogo lica licenzionnym trebovaniyam i sootvetstvie svedenii o soiskatele soderzhaschimsya v edinom gosudarstvennom reestre yuridicheskih lic i drugih federalnyh informacionnyh resursah po obrascheniyu yuridicheskogo lica po zayavleniyu 01246092 ot 26072018 g o predostavlenii licenzii


# 77170801965730
Unscheduled inspection
Start date: 2017-08-31, end date: 2017-09-08, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170801965627
Unscheduled inspection
Start date: 2017-08-31, end date: —, duration:
Authority:
Purpose of inspection:


# 77170701861054
Unscheduled inspection
Start date: 2017-08-03, end date: —, duration:
Authority:
Purpose of inspection:


# 77170701785462
Unscheduled inspection
Start date: 2017-07-06, end date: 2017-07-21, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77160701269937
Unscheduled inspection
Start date: 2016-12-26, end date: 2017-01-13, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.