# 002105334728
Unscheduled inspection
Start date: 2021-02-02, end date: 2021-02-05, duration: 4
Authority: Verhne-Donskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: In order to: comply with paragraph 2 of the approved inspection program, the objectives of this inspection are:
prevention, detection and suppression of violations of urban planning legislation, including technical regulations, and project documentation committed by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer (hereinafter referred to as the contractor). The purpose of the audit is to comply with the mandatory requirements and/or requirements established by municipal legal acts at the capital construction facility: Plant Protection Products Plant
# 002005214639
Unscheduled inspection
Start date: 2020-11-09, end date: 2020-11-11, duration: 3
Authority: VerhneDonskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: In order to comply with paragraph 1 of the approved inspection program dated 28092020, the objectives of this inspection are to prevent, identify and suppress violations of urban planning legislation by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, hereinafter referred to as the contractor, including technical regulations and design documentationthe subject of this inspection is compliance with mandatory requirements during the construction of the ACS "Plant for the Production of plant protection products"
# 362100298576
Unscheduled inspection
Start date: 2021-06-23, end date: —, duration: 2
Authority: Verhne-Donskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: In order to: comply with paragraph 4 of the approved inspection program dated 09/28/2020, the objectives of this inspection are:
prevention, detection and suppression of violations of legislation on urban development, including technical regulations, and project documentation committed by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer (hereinafter referred to as the contractor). The subject of this audit is compliance with mandatory requirements during the construction of a capital construction facility: Plant Protection Products Manufacturing Plant
# 362100112354
Unscheduled inspection
Start date: 2021-04-08, end date: 2021-04-14, duration: 5
Authority: Verhne-Donskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: In order to comply with paragraph 3 of the approved inspection program, the objectives of this inspection are: prevention, detection and suppression of violations of urban planning legislation, including technical regulations, and project documentation committed by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer (hereinafter referred to as the contractor). The purpose of the audit is to ensure compliance with the mandatory requirements for the construction of a capital construction facility: Plant Protection Products Plant
# 002105334728
Unscheduled inspection
Start date: 2021-02-02, end date: 2021-02-05, duration: 4
Authority: Verhne-Donskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: In order to: comply with paragraph 2 of the approved inspection program, the objectives of this inspection are:
prevention, detection and suppression of violations of urban planning legislation, including technical regulations, and project documentation committed by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer (hereinafter referred to as the contractor). The purpose of the audit is to comply with the mandatory requirements and/or requirements established by municipal legal acts at the capital construction facility: Plant Protection Products Plant
# 002005214639
Unscheduled inspection
Start date: 2020-11-09, end date: 2020-11-11, duration: 3
Authority: VerhneDonskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: In order to comply with paragraph 1 of the approved inspection program dated 28092020, the objectives of this inspection are to prevent, identify and suppress violations of urban planning legislation by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, hereinafter referred to as the contractor, including technical regulations and design documentationthe subject of this inspection is compliance with mandatory requirements during the construction of the ACS "Plant for the Production of plant protection products"