Found 7 inspections:

# 612004979252
Unscheduled inspection
Start date: 2020-09-30, end date: —, duration:
Authority: Regionalnaya sluzhba gosudarstvennogo stroitelnogo nadzora Rostovskoi oblasti
Purpose of inspection:


# 612004394826
Unscheduled inspection
Start date: 2020-04-13, end date: 2020-04-17, duration: 5
Authority: Regionalnaya sluzhba gosudarstvennogo stroitelnogo nadzora Rostovskoi oblasti
Purpose of inspection: The inspection is carried out in order to fulfill the p6 inspection program Device reinforcement concreting of monolithic reinforced concrete structures according to otm + 19500 Device of metal structures covering trusses beams racks girders on otm + 16480 in axes 26 710 The objectives of this inspection are to prevent identify and suppress violations of the law committed by the developer customer as well as the person carrying out construction on the basis of an agreement with the developer or customer hereinafter contractor on urban planning activities, including technical regulations and project documentation, the subject of this audit is to verify compliance with mandatory requirements and or requirements established by municipal legal acts


# 611903698843
Unscheduled inspection
Start date: 2019-09-19, end date: —, duration:
Authority:
Purpose of inspection:


# 611902618195
Unscheduled inspection
Start date: 2019-03-18, end date: 2019-03-29, duration:
Authority: Regionalnaya sluzhba gosudarstvennogo stroitelnogo nadzora Rostovskoi oblasti
Purpose of inspection: the inspection is carried out in order to fulfill the p5 inspection program Device reinforcement concreting of monolithic reinforced concrete structures according to otm + 19500 Device of metal structures covering trusses beams racks girders on otm + 16480 in axes 26 710 the objectives of this inspection are to prevent identify and suppress violations of the law committed by the developer customer as well as the person carrying out construction on the basis of an agreement with the developer or customer hereinafter contractor on urban planning activities, including technical regulations and project documentation, the subject of this audit is to verify compliance with mandatory requirements and or requirements established by municipal legal acts


# 611902564174
Unscheduled inspection
Start date: 2019-03-18, end date: 2019-03-29, duration:
Authority: Regionalnaya sluzhba gosudarstvennogo stroitelnogo nadzora Rostovskoi oblasti
Purpose of inspection: the inspection is carried out in order to fulfill the p5 inspection program Device reinforcement concreting of monolithic reinforced concrete structures according to otm + 19500 Device of metal structures covering trusses beams racks girders on otm + 16480 in axes 26 710 the objectives of this inspection are to prevent identify and suppress violations of the law committed by the developer customer as well as the person carrying out construction on the basis of an agreement with the developer or customer hereinafter contractor on urban planning activities, including technical regulations and project documentation, the subject of this audit is to verify compliance with mandatory requirements and or requirements established by municipal legal acts


# 61160701091556
Unscheduled inspection
Start date: 2016-10-24, end date: 2016-11-03, duration:
Authority: Regionalnaya sluzhba gosudarstvennogo stroitelnogo nadzora Rostovskoi oblasti
Purpose of inspection: the purpose of the implementation of p 3 of the Program of inspections in the case 0102995 task prevention detection and suppression of violations of the legislation on urban development, including technical regulations and design documentationsubject verification of compliance with the execution of works and applied building materials during the construction reconstruction of a capital construction facility, committed by the developer, the technical customer and the person carrying out construction on the basis of an agreement with the developer or the technical customer. also, the results of such work meet the requirements of the technical regulations of the project documentation


# 61160601775372
Unscheduled inspection
Start date: 2016-07-14, end date: 2016-07-22, duration:
Authority: Regionalnaya sluzhba gosudarstvennogo stroitelnogo nadzora Rostovskoi oblasti
Purpose of inspection: The purpose of fulfilling p 2 of the Program of inspections in the case 0102995 task is to prevent the identification and suppression of violations of the legislation on urban development, including technical regulations and project documentation, by the developer, the technical customer, as well as the person carrying out construction on the basis of an agreement with the developer or technical customer, including technical regulations and project documentation, the conformity of work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work requirements of the technical regulations of the project documentation


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.