Found 9 inspections:

# 34170802792295
Unscheduled inspection
Start date: 2017-10-27, end date: 2017-10-31, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: in order to assess the compliance of activities carried out at the Facility with the requirements of urban planning legislation of the Russian Federation legislation of the Russian Federation in the field of environmental protection fire safety requirements and sanitary and epidemiological welfare of the population as well as energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, including technical regulations and project documentation, the purpose of this audit is to prevent identify and suppress violations of the legislation of the Russian Federation, including technical regulations and project documentation, the subject of this audit is compliance with mandatory requirements in relation to compliance of construction works, their results and applied building materials with the requirements of technical regulations of project documentation, availability of a construction permit, and compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 34170802711242
Unscheduled inspection
Start date: 2017-10-11, end date: 2017-10-19, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: in order to assess the compliance of activities carried out at the facility with the requirements of the urban planning legislation of the Russian Federation, including technical regulations and design documentationthe task of this audit is to prevent identify and suppress violations of the legislation of the Russian Federation, including technical regulations and design documentationthe subject of this audit is compliance with mandatory requirements in relation to the compliance of construction works, their results and applied building materials with technical requirements regulations of the project documentation, the availability of a construction permit, and the fulfillment of the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 34170701657980
Unscheduled inspection
Start date: 2017-06-02, end date: 2017-06-09, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: In order to assess the compliance of activities carried out at the Facility with the requirements of the urban planning legislation of the Russian Federation, the legislation of the Russian Federation in the field of environmental protection, fire safety requirements and sanitary and epidemiological welfare of the population, as well as energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, including technical regulations and design documentationthe purpose of this audit is to prevent identify and prevent violations of the legislation of the Russian Federation, including technical regulations and design documentationthe subject of this audit is compliance with mandatory requirements regarding the conformity of construction works, their results and the construction materials used, with the requirements of technical regulations, project documentation, and the availability of a construction permit and compliance with established requirements for admission to construction work


# 34160701193122
Unscheduled inspection
Start date: 2016-12-09, end date: 2016-12-12, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: s celyu ocenki sootvetstviya deyatelnosti osuschestvlyaemoi na Obekte trebovaniyam gradostroitelnogo zakonodatelstva Rossiiskoi Federacii v tom chisle tehnicheskih reglamentov i proektnoi dokumentaciizadachei nastoyaschei proverki yavlyaetsya preduprezhdenie vyyavlenie i presechenie dopuschennyh narushenii zakonodatelstva Rossiiskoi Federacii v tom chisle tehnicheskih reglamentov i proektnoi dokumentacii


# 34160701053837
Unscheduled inspection
Start date: 2016-10-31, end date: 2016-11-09, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: In order to assess the compliance of activities carried out at the Facility with the requirements of the urban planning legislation of the Russian Federation, the legislation of the Russian Federation in the field of environmental protection, fire safety requirements and sanitary and epidemiological welfare of the population, as well as energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, including technical regulations and design documentationthe purpose of this audit is to prevent identify and prevent violations of the legislation of the Russian Federation, including technical regulations and design documentationthe subject of this audit is compliance with mandatory requirements regarding the conformity of construction works, their results and the construction materials used, with the requirements of technical regulations, project documentation, and the availability of a construction permit and compliance with established requirements for admission to construction work


# 34160700854951
Unscheduled inspection
Start date: 2016-09-28, end date: —, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection:


# 34160700055438
Unscheduled inspection
Start date: 2016-08-23, end date: 2016-08-29, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: in order to assess the compliance of activities carried out at the Facility with the requirements of urban planning legislation of the Russian Federation as well as energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used with the requirements of urban planning legislation, including technical regulations and project documentation, the purpose of this audit is to prevent identify and suppress violations of the legislation of the Russian Federation, including technical regulations and project documentation The purpose of this check is to comply with the mandatory requirements in relation to the compliance of construction works with their results and the construction materials used with the requirements of technical regulations, project documentation, availability of a construction permit, and compliance with the established requirements for admission to construction work


# 34160601785703
Unscheduled inspection
Start date: 2016-08-11, end date: —, duration:
Authority:
Purpose of inspection:


# 34160601690843
Unscheduled inspection
Start date: 2016-07-01, end date: 2016-07-11, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: assessment of compliance of the activities carried out at the facility with the requirements of the urban planning legislation of the Russian Federation


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.