Found 5 inspections:

# 181902959669
Unscheduled inspection
Start date: 2019-08-23, end date: 2019-08-30, duration:
Authority: Gosudarstvennaya inspekciya truda v Udmurtskoi Respublike
Purpose of inspection: verification of information received from the Federal Service for Labor and Employment dated 20022019 TK107033


# 161800635197
Unscheduled inspection
Start date: 2018-08-29, end date: 2018-08-31, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: Determination of the compliance of the completed works applied in the process of construction reconstruction of the capital construction facility of building materials and the results of such works with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of capital construction facilities with metering devices for energy resources used checking the availability of a construction permit compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation prevention as well as identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation compliance with mandatory requirements or requirements established by municipal legal acts


# 16170802570209
Unscheduled inspection
Start date: 2017-09-28, end date: 2017-09-29, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: Opredelenie sootvetstviya vypolnennyh rabot primenennyh v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva stroitelnyh materialov rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obektov kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov proverka nalichiya razresheniya na stroitelstvo vypolneniya trebovanii chastei 2 i 3 stati 52 Gradostroitelnogo Kodeksa RF v sootvetstvii s programmoi proverok ot 13072015 delo 151120150071 preduprezhdenie a takzhe vyyavlenie i presechenie dopuschennyh zastroischikom zakazchikom licom osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom narushenii sootvetstviya vypolnyaemyh v processe stroitelstva obekta kapitalnogo stroitelstva rabot trebovaniyam tehnicheskih reglamentov inyh normativnyh pravovyh aktov i proektnoi dokumentacii soblyudenie obyazatelnyh trebovanii ili trebovanii ustanovlennyh municipalnymi pravovymi aktami


# 16160700936183
Unscheduled inspection
Start date: 2016-10-03, end date: 2016-10-03, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: determination of compliance of the completed works during the construction of a capital construction facility with the technical regulations of the project documentation


# 16160700124830
Unscheduled inspection
Start date: 2016-09-05, end date: 2016-09-08, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: determination of compliance of the completed works during the construction of a capital construction facility with the technical regulations of the project documentation


Information about inspections