Found 26 inspections:

# 472005316039
Unscheduled inspection
Start date: 2020-12-15, end date: 2021-01-19, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of completion of work on the implementation of construction reconstruction of the capital construction facility specified in the notice of the developer technical customer on completion of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for energy resources used to meet the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out construction


# 472005315868
Unscheduled inspection
Start date: 2020-12-15, end date: —, duration:
Authority:
Purpose of inspection:


# 472005201404
Unscheduled inspection
Start date: 2020-10-28, end date: 2020-11-24, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of completion of work on the implementation of construction reconstruction of the capital construction facility specified in the notice of the developer technical customer on completion of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for energy resources used to meet the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out construction


# 472005201473
Unscheduled inspection
Start date: 2020-10-30, end date: 2020-11-26, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of completion of work on the implementation of construction reconstruction of the capital construction facility specified in the notice of the developer technical customer on completion of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for energy resources used to meet the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out construction


# 471904069244
Unscheduled inspection
Start date: 2019-12-02, end date: 2019-12-27, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of elimination of violations of the mandatory requirements specified in the notice of the person carrying out the construction on elimination of the identified violations The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the facility capital construction metering devices for energy resources used to comply with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out the construction


# 471904098735
Unscheduled inspection
Start date: 2019-12-06, end date: 2020-01-10, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of elimination of violations of the mandatory requirements specified in the notice of the person carrying out the construction on elimination of the identified violations The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the facility capital construction metering devices for energy resources used to comply with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out the construction


# 471903997547
Unscheduled inspection
Start date: 2019-11-20, end date: 2019-12-17, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of elimination of violations of the mandatory requirements specified in the notice of the person carrying out the construction on elimination of the identified violations The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the facility capital construction metering devices for energy resources used to meet the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out the construction, the purpose of checking the execution of the issued instruction on the elimination of violations identified by the subject of this audit is the fulfillment of the instructions of the Committee of State Construction Supervision and State Expertise of the Leningrad Region the objectives of this audit are to prevent identify and suppress violations of legislation on urban development activities committed by the developer, the technical customer, the person carrying out construction, including technical regulations and design objectives of this audit are to prevent identify and suppress violations of legislation on urban development activities committed by the developer, the technical customer, the person carrying out construction in including technical regulations and project documentation


# 471903894202
Unscheduled inspection
Start date: 2019-10-23, end date: 2019-11-20, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of completion of work on the implementation of construction reconstruction of the capital construction facility specified in the notice of the developer technical customer on completion of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for used energy resources compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out construction


# 471903856614
Unscheduled inspection
Start date: 2019-10-14, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection:


# 471902876376
Unscheduled inspection
Start date: 2019-07-17, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection:


# 471902876371
Unscheduled inspection
Start date: 2019-07-17, end date: 2019-08-13, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of elimination of violations of the mandatory requirements specified in the notice of the person carrying out the construction on elimination of the identified violations The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the facility capital construction metering devices for energy resources used to meet the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out the construction, the purpose of checking the execution of the issued instruction on the elimination of violations identified by the subject of this audit is the fulfillment of the instructions of the Committee of State Construction Supervision and State Expertise of the Leningrad Region the objectives of this audit are to prevent identify and suppress violations of legislation on urban development activities committed by the developer, the technical customer, the person carrying out construction, including technical regulations and design objectives of this audit are to prevent identify and suppress violations of legislation on urban development activities committed by the developer, the technical customer, the person carrying out construction in including technical regulations and project documentation


# 471902746661
Unscheduled inspection
Start date: 2019-05-30, end date: 2019-06-27, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose of checking the execution of the issued instruction on the elimination of identified violations The subject of this audit is the fulfillment of the instructions of the Committee of State Construction Supervision and State expertise of the Leningrad Region the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations, and the design objectives of this audit are to prevent identify and suppress by the developer, the technical customer, the person carrying out the construction of violations of the legislation on urban planning activities, including technical regulations and project documentation


# 471902663457
Unscheduled inspection
Start date: 2019-04-17, end date: 2019-05-21, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose is to verify the completion of work on the construction and reconstruction of a capital construction facility specified in the developer's notice to the technical customer on completion of construction. The subject of this audit is compliance with mandatory requirements, including compliance with the performance of work and the construction materials used during the construction and reconstruction of a capital construction facility, as well as the results of such work with the requirements of technical regulations and design documentation, including energy efficiency requirements compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation and the requirements for equipping the capital construction facility with metering devices for used energy resources the objectives of this audit are to prevent identify and suppress violations of legislation on urban development by the developer technical customer person carrying out construction, including technical regulations and project documentation


# 471902567060
Unscheduled inspection
Start date: 2019-03-11, end date: 2019-04-05, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of elimination of violations of the mandatory requirements specified in the notice of the person carrying out the construction on elimination of the identified violations The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the facility capital construction metering devices for energy resources used to comply with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out the construction


# 471902604903
Unscheduled inspection
Start date: 2019-03-28, end date: 2019-04-24, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of works at the beginning of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban planning activities committed by the developer, the technical customer, the person carrying out the construction, including technical regulations and project documentation


# 471902604812
Unscheduled inspection
Start date: 2019-03-28, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection:


# 471902442793
Unscheduled inspection
Start date: 2019-01-21, end date: 2019-02-15, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of elimination of violations of the mandatory requirements specified in the notice of the person carrying out the construction on elimination of the identified violations The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the facility capital construction with metering devices for used energy resources compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 471802097925
Unscheduled inspection
Start date: 2018-11-15, end date: 2018-12-12, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of completion of work on the implementation of construction reconstruction of the capital construction facility specified in the notice of the developer technical customer on completion of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for used energy resources compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 471801770461
Unscheduled inspection
Start date: 2018-09-27, end date: 2018-10-24, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of completion of work on the implementation of construction reconstruction of the capital construction facility specified in the notice of the developer technical customer on completion of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for used energy resources compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 471801770442
Unscheduled inspection
Start date: 2018-09-27, end date: —, duration:
Authority:
Purpose of inspection:


# 471800355327
Unscheduled inspection
Start date: 2018-05-07, end date: 2018-06-04, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: verification of the completion of work on the construction reconstruction of the capital construction facility specified in the notice of the developer technical customer on completion of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations design documentation, including energy efficiency requirements and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban development activities committed by the developer, the technical customer, the person carrying out the construction, including technical regulations and project documentation


# 471800239496
Unscheduled inspection
Start date: 2018-03-28, end date: 2018-04-24, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: verification of work at the beginning of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used compliance with the requirements of parts 2 Articles 3 and 31 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out the construction


# 47170701311118
Unscheduled inspection
Start date: 2017-01-18, end date: —, duration:
Authority:
Purpose of inspection:


# 47170701307172
Unscheduled inspection
Start date: 2017-01-16, end date: 2017-02-10, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose of checking the elimination of violations of the mandatory requirements specified in the notice of the person carrying out the construction on the elimination of the identified violations. The subject of this check is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the capital construction facility with appliances accounting for used energy resourcescompliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation


# 47160701248436
Unscheduled inspection
Start date: 2016-12-19, end date: —, duration:
Authority:
Purpose of inspection:


# 47160701202246
Unscheduled inspection
Start date: 2016-12-05, end date: 2016-12-30, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose of checking the elimination of violations of the mandatory requirements specified in the notice of the person carrying out the construction on the elimination of identified violations The subject of this check is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the capital construction facility construction of metering devices for used energy resources compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.