# 772100680177
Unscheduled inspection
Start date: 2021-09-10, end date: 2021-09-16, duration: 5
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The purpose of the audit: carrying out control measures in connection with the verification of compliance with the instruction; The tasks of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: verification of the elimination of violations specified in the instruction issued by Mosgosstroynadzor
# 772100271196
Unscheduled inspection
Start date: 2021-06-07, end date: 2021-07-02, duration: 19
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the audit program; The tasks of the audit: prevention, identification and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements design documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of design documentation identified during construction control and state construction supervision
# 772004257564
Unscheduled inspection
Start date: 2020-02-11, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77190803456795
Unscheduled inspection
Start date: 2019-07-08, end date: 2019-07-19, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77190803456793
Unscheduled inspection
Start date: 2019-07-08, end date: 2019-07-26, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77190803440892
Unscheduled inspection
Start date: 2019-06-17, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77190803428385
Unscheduled inspection
Start date: 2019-06-03, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77190803412554
Unscheduled inspection
Start date: 2019-05-13, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77190803422104
Unscheduled inspection
Start date: 2019-05-21, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77190803384121
Unscheduled inspection
Start date: 2019-04-15, end date: 2019-05-17, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77190803403517
Unscheduled inspection
Start date: 2019-04-22, end date: 2019-05-08, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77190803370163
Unscheduled inspection
Start date: 2019-03-11, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77190803370685
Unscheduled inspection
Start date: 2019-03-18, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77190803378030
Unscheduled inspection
Start date: 2019-03-21, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77190803381952
Unscheduled inspection
Start date: 2019-03-26, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77190803359131
Unscheduled inspection
Start date: 2019-03-04, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77190803328193
Unscheduled inspection
Start date: 2019-02-06, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77190803327708
Unscheduled inspection
Start date: 2019-02-05, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77190803320007
Unscheduled inspection
Start date: 2019-01-21, end date: 2019-01-23, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77190803317736
Unscheduled inspection
Start date: 2019-01-21, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77190803319302
Unscheduled inspection
Start date: 2019-01-23, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803296647
Unscheduled inspection
Start date: 2018-12-10, end date: 2018-12-11, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803296667
Unscheduled inspection
Start date: 2018-12-12, end date: 2019-01-17, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77180803283966
Unscheduled inspection
Start date: 2018-11-26, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803272127
Unscheduled inspection
Start date: 2018-11-12, end date: 2018-11-23, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803278686
Unscheduled inspection
Start date: 2018-11-15, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803244200
Unscheduled inspection
Start date: 2018-10-02, end date: 2018-10-03, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803217485
Unscheduled inspection
Start date: 2018-09-03, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803222475
Unscheduled inspection
Start date: 2018-09-06, end date: 2018-09-07, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803208862
Unscheduled inspection
Start date: 2018-08-27, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 77180803197443
Unscheduled inspection
Start date: 2018-08-06, end date: 2018-08-10, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803206719
Unscheduled inspection
Start date: 2018-08-20, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803180296
Unscheduled inspection
Start date: 2018-07-10, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803185541
Unscheduled inspection
Start date: 2018-07-23, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803165239
Unscheduled inspection
Start date: 2018-06-25, end date: 2018-06-25, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803165238
Unscheduled inspection
Start date: 2018-06-26, end date: 2018-07-23, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77180803125141
Unscheduled inspection
Start date: 2018-04-16, end date: 2018-04-27, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803117192
Unscheduled inspection
Start date: 2018-04-24, end date: 2018-05-24, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77180803102408
Unscheduled inspection
Start date: 2018-03-19, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803095812
Unscheduled inspection
Start date: 2018-03-12, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 77180803097516
Unscheduled inspection
Start date: 2018-03-07, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803086894
Unscheduled inspection
Start date: 2018-02-01, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803081759
Unscheduled inspection
Start date: 2018-02-05, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803070844
Unscheduled inspection
Start date: 2018-02-05, end date: 2018-03-09, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77170802860959
Unscheduled inspection
Start date: 2017-12-04, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170803011722
Unscheduled inspection
Start date: 2017-12-18, end date: 2017-12-22, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170802851669
Unscheduled inspection
Start date: 2017-11-14, end date: 2017-11-17, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77170802796337
Unscheduled inspection
Start date: 2017-10-24, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170802747368
Unscheduled inspection
Start date: 2017-10-17, end date: 2017-10-24, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170802747367
Unscheduled inspection
Start date: 2017-10-17, end date: 2017-10-24, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170802511851
Unscheduled inspection
Start date: 2017-09-19, end date: 2017-09-29, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170802511850
Unscheduled inspection
Start date: 2017-09-19, end date: 2017-09-29, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170802041414
Unscheduled inspection
Start date: 2017-09-06, end date: 2017-09-08, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170801989342
Unscheduled inspection
Start date: 2017-09-04, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170801989338
Unscheduled inspection
Start date: 2017-09-04, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170701840101
Unscheduled inspection
Start date: 2017-07-28, end date: 2017-08-01, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77170701743282
Unscheduled inspection
Start date: 2017-06-26, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170701657257
Unscheduled inspection
Start date: 2017-05-29, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170701505202
Unscheduled inspection
Start date: 2017-04-10, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170701525130
Unscheduled inspection
Start date: 2017-04-26, end date: 2017-04-28, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77170701545365
Unscheduled inspection
Start date: 2017-04-24, end date: 2017-04-25, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170701475270
Unscheduled inspection
Start date: 2017-03-23, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170701413683
Unscheduled inspection
Start date: 2017-02-27, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170701303113
Unscheduled inspection
Start date: 2017-01-13, end date: 2017-01-16, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77160701144751
Unscheduled inspection
Start date: 2016-11-23, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77160701041649
Unscheduled inspection
Start date: 2016-10-27, end date: 2016-10-28, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: elimination of violations specified in the instruction issued by Mosgosstroynadzor prevention detection and suppression of violations of technical regulations and project documentation committed by the audited person verification of elimination of violations specified in the instruction issued by Mosgosstroynadzor
# 77160700729682
Unscheduled inspection
Start date: 2016-09-16, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77160601770444
Unscheduled inspection
Start date: 2016-08-05, end date: 2016-08-08, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: ustranenie narushenii ukazannyh v predpisanii vydannom Mosgosstroinadzorom preduprezhdenie vyyavlenie i presechenie dopuschennyh proveryaemym licom narushenii tehnicheskih reglamentov i proektnoi dokumentacii proverka ustraneniya narushenii ukazannyh v predpisanii vydannom Mosgosstroinadzorom 335316 ot 12042016