Found 61 inspection:

# 772101461115
Unscheduled inspection
Start date: 2021-12-13, end date: —, duration:
Authority:
Purpose of inspection:


# 772101295827
Unscheduled inspection
Start date: 2021-11-08, end date: —, duration:
Authority:
Purpose of inspection:


# 772101170942
Unscheduled inspection
Start date: 2021-10-14, end date: 2021-10-14, duration: 1
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The purpose of the audit: carrying out control measures in connection with the verification of compliance with the instruction; The tasks of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: verification of the elimination of violations specified in the instruction issued by Mosgosstroynadzor


# 772101204585
Unscheduled inspection
Start date: 2021-10-18, end date: —, duration:
Authority:
Purpose of inspection:


# 772100802099
Unscheduled inspection
Start date: 2021-09-20, end date: 2021-09-22, duration: 3
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The purpose of the audit: carrying out control measures in connection with the receipt of a notification from the developer (customer); The objectives of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: checking the elimination of violations specified in the order issued by Mosgosstroynadzor


# 772100411431
Unscheduled inspection
Start date: 2021-08-05, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


# 772100508707
Unscheduled inspection
Start date: 2021-08-23, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


# 772100349407
Unscheduled inspection
Start date: 2021-07-15, end date: —, duration:
Authority:
Purpose of inspection:


# 772100006032
Unscheduled inspection
Start date: 2021-02-11, end date: —, duration:
Authority:
Purpose of inspection:


# 772105293608
Unscheduled inspection
Start date: 2021-01-11, end date: —, duration:
Authority:
Purpose of inspection:


# 772005259266
Unscheduled inspection
Start date: 2020-12-03, end date: —, duration:
Authority:
Purpose of inspection:


# 772004456967
Unscheduled inspection
Start date: 2020-07-20, end date: —, duration:
Authority:
Purpose of inspection:


# 772004459850
Unscheduled inspection
Start date: 2020-07-15, end date: —, duration:
Authority:
Purpose of inspection:


# 772004317321
Unscheduled inspection
Start date: 2020-03-02, end date: 2020-03-23, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the implementation of the verification program verification tasks prevention identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, subject to verification of compliance of the work and construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including energy efficiency requirements and equipment requirements of the capital construction facility metering devices for energy resources used


# 772004317347
Unscheduled inspection
Start date: 2020-03-02, end date: —, duration:
Authority:
Purpose of inspection:


# 772004382889
Unscheduled inspection
Start date: 2020-03-25, end date: 2020-03-27, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the verification of compliance with the requirements of the task of the audit, to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to verify the elimination of violations specified in the order issued by Mosgosstroynadzor


# 772004287847
Unscheduled inspection
Start date: 2020-02-14, end date: 2020-02-14, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the verification of compliance with the requirements of the task of the audit, to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to verify the elimination of violations specified in the order issued by Mosgosstroynadzor


# 772004167953
Unscheduled inspection
Start date: 2020-01-13, end date: —, duration:
Authority:
Purpose of inspection:


# 771904098352
Unscheduled inspection
Start date: 2019-12-13, end date: 2019-12-16, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the verification of compliance with the requirements of the task of the audit, to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to verify the elimination of violations specified in the order issued by Mosgosstroynadzor


# 771904098319
Unscheduled inspection
Start date: 2019-12-13, end date: 2019-12-16, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the verification of compliance with the requirements of the task of the audit, to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to verify the elimination of violations specified in the order issued by Mosgosstroynadzor


# 771904098381
Unscheduled inspection
Start date: 2019-12-13, end date: 2019-12-16, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the verification of compliance with the requirements of the task of the audit, to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to verify the elimination of violations specified in the order issued by Mosgosstroynadzor


# 771904085750
Unscheduled inspection
Start date: 2019-12-16, end date: 2019-12-16, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the verification of compliance with the requirements of the task of the audit, to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to verify the elimination of violations specified in the order issued by Mosgosstroynadzor


# 771903937834
Unscheduled inspection
Start date: 2019-11-18, end date: 2019-11-18, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the verification of compliance with the requirements of the task of the audit, to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to verify the elimination of violations specified in the order issued by Mosgosstroynadzor


# 771903800509
Unscheduled inspection
Start date: 2019-10-08, end date: —, duration:
Authority:
Purpose of inspection:


# 771903848491
Unscheduled inspection
Start date: 2019-10-10, end date: —, duration:
Authority:
Purpose of inspection:


# 771903574482
Unscheduled inspection
Start date: 2019-09-12, end date: —, duration:
Authority:
Purpose of inspection:


# 771903574384
Unscheduled inspection
Start date: 2019-09-12, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803478229
Unscheduled inspection
Start date: 2019-08-19, end date: 2019-08-20, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77190803481536
Unscheduled inspection
Start date: 2019-08-22, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


# 77190803486718
Unscheduled inspection
Start date: 2019-08-26, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803427939
Unscheduled inspection
Start date: 2019-06-10, end date: 2019-07-08, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77190803328774
Unscheduled inspection
Start date: 2019-02-18, end date: 2019-02-21, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77190803342155
Unscheduled inspection
Start date: 2019-02-25, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803272570
Unscheduled inspection
Start date: 2018-11-26, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803272569
Unscheduled inspection
Start date: 2018-11-26, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


# 77180803244697
Unscheduled inspection
Start date: 2018-10-15, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803244696
Unscheduled inspection
Start date: 2018-10-15, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803198826
Unscheduled inspection
Start date: 2018-08-14, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803205705
Unscheduled inspection
Start date: 2018-08-20, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803178258
Unscheduled inspection
Start date: 2018-07-11, end date: 2018-07-13, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803178253
Unscheduled inspection
Start date: 2018-07-11, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


# 77180803136174
Unscheduled inspection
Start date: 2018-05-07, end date: 2018-05-09, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803146985
Unscheduled inspection
Start date: 2018-05-22, end date: 2018-05-23, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803148594
Unscheduled inspection
Start date: 2018-05-25, end date: 2018-05-28, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803102812
Unscheduled inspection
Start date: 2018-03-15, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


# 77180803094560
Unscheduled inspection
Start date: 2018-03-01, end date: 2018-03-02, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803094475
Unscheduled inspection
Start date: 2018-03-01, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803113317
Unscheduled inspection
Start date: 2018-03-29, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803058690
Unscheduled inspection
Start date: 2018-01-16, end date: 2018-01-18, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803069035
Unscheduled inspection
Start date: 2018-01-23, end date: —, duration:
Authority:
Purpose of inspection:


# 77170803034877
Unscheduled inspection
Start date: 2017-12-27, end date: 2017-12-28, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170802995247
Unscheduled inspection
Start date: 2017-12-12, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


# 77170802924293
Unscheduled inspection
Start date: 2017-11-29, end date: 2017-12-01, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77170802198023
Unscheduled inspection
Start date: 2017-09-07, end date: 2017-09-11, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77170701857069
Unscheduled inspection
Start date: 2017-08-02, end date: 2017-08-04, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77170701891669
Unscheduled inspection
Start date: 2017-08-23, end date: —, duration:
Authority:
Purpose of inspection:


# 77170701832164
Unscheduled inspection
Start date: 2017-07-25, end date: —, duration:
Authority:
Purpose of inspection:


# 77170701754224
Unscheduled inspection
Start date: 2017-06-28, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


# 77170701637156
Unscheduled inspection
Start date: 2017-05-16, end date: —, duration:
Authority:
Purpose of inspection:


# 77170701463082
Unscheduled inspection
Start date: 2017-03-15, end date: —, duration:
Authority:
Purpose of inspection:


# 77170701373189
Unscheduled inspection
Start date: 2017-02-08, end date: —, duration:
Authority:
Purpose of inspection:


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.