Found 4 inspections:

# 362100015579
Unscheduled inspection
Start date: 2021-03-02, end date: 2021-03-04, duration: 3
Authority: Verhne-Donskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the fulfillment by the Federal State Budgetary Scientific Institution "Federal Scientific Center named after I.V. Michurin" of the regulations of the Verkhne-Don Department of Rostechnadzor dated 01/24/2020 No. T3/127-135, the objectives of this audit are: verification of the fulfillment by the Federal State Budgetary Scientific Institution "Federal Scientific Center named after I.V. Michurin" of violations of electrical safety requirements in the electric power industry, violations of safety requirements electrical installations identified by the Verkhne-Don department of Rostechnadzor as part of an unscheduled on-site inspection on 24.01.2020.


# 002004212181
Unscheduled inspection
Start date: 2020-01-22, end date: 2020-01-24, duration:
Authority: VerhneDonskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the fulfillment of violations of electrical safety requirements in the electric power industry violations of the safety requirements of electrical installations identified by the Verkhnedonsky Department of Rostechnadzor as part of an unscheduled on-site inspection dated 14032019 from 14082019


# 001902936742
Unscheduled inspection
Start date: 2019-08-12, end date: 2019-08-14, duration:
Authority: VerhneDonskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the fulfillment of violations of electrical safety requirements in the electric power industry violations of the safety requirements of electrical installations identified by the Verkhnedonsky Department of Rostechnadzor as part of an unscheduled on-site inspection of 14032019


# 001902555832
Unscheduled inspection
Start date: 2019-03-11, end date: 2019-03-14, duration:
Authority: VerhneDonskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The objectives of this audit are to verify compliance with safety requirements in the electric power industry, to verify compliance with safety requirements of electrical installations and networks


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.