# 001903385581
Unscheduled inspection
Start date: 2019-09-16, end date: 2019-10-11, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Nastoyaschaya proverka provoditsya s celyu kontrolya vypolneniya ranee vydannogo predpisaniya ot 01 avgusta 2019g 352POZP140 p 12345 srok ispolneniya kotorogo istekzadachami nastoyaschei proverki yavlyayutsya kontrol za ispolneniem ranee vydannogo predpisaniya ot 01 avgusta 2019g 352POZP140 p 12345 srok ispolneniya kotoryh istekPredmetom nastoyaschei proverki yavlyaetsyakontrol vypolneniya predpisaniya dolzhnostnogo lica Sibirskogo upravleniya Rostehnadzora ot 01 avgusta 2019g 352POZP140 p 12345 srok ispolneniya kotorogo istek
# 001902436009
Unscheduled inspection
Start date: 2019-01-16, end date: 2019-02-12, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Nastoyaschaya proverka provoditsya s celyu proverki vypolneniya ranee vydannogo predpisaniya ot 29082018 3627POZP86 punkty 14 vydannogo dolzhnostnymi licami Sibirskogo upravleniya Rostehnadzora srok ispolneniya kotorogo istek Zadachami nastoyaschei proverki yavlyaetsya kontrol za ispolneniem ranee vydannogo predpisaniya ot 29082018 3627POZP86 punkty 14 vydannogo dolzhnostnymi licami Sibirskogo upravleniya Rostehnadzora srok ispolneniya kotorogo istek Predmetom nastoyaschei proverki yavlyaetsya vypolnenie predpisaniya dolzhnostnyh lic Sibirskogo upravleniya Rostehnadzora ot 29082018 3627POZP86 punkty 14
# 001800633398
Unscheduled inspection
Start date: 2018-08-13, end date: 2018-08-31, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this inspection is carried out in order to comply with the order of the Federal Service for Environmental Technological and Nuclear Supervision "On monitoring the preparation of heat supply facilities for operation in the autumn winter period 2018-2019" dated 16072018 308 issued pursuant to the instruction of Deputy Prime Minister of the Russian Federation Vladimir Mutko dated 26062018 VMP93773 the purpose of this inspection is to verify the readiness of the heat supply heating network organization to work in the autumn winter The period 2018-2019 is the verification of the safe operation and technical condition of power plants of the main and auxiliary equipment of boiler houses and heating networks
# 00170701875276
Unscheduled inspection
Start date: 2017-08-28, end date: 2017-09-22, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Checking the readiness of the heat supply organization to work in the autumn-winter period of 2017-2018
# 001903385581
Unscheduled inspection
Start date: 2019-09-16, end date: 2019-10-11, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Nastoyaschaya proverka provoditsya s celyu kontrolya vypolneniya ranee vydannogo predpisaniya ot 01 avgusta 2019g 352POZP140 p 12345 srok ispolneniya kotorogo istekzadachami nastoyaschei proverki yavlyayutsya kontrol za ispolneniem ranee vydannogo predpisaniya ot 01 avgusta 2019g 352POZP140 p 12345 srok ispolneniya kotoryh istekPredmetom nastoyaschei proverki yavlyaetsyakontrol vypolneniya predpisaniya dolzhnostnogo lica Sibirskogo upravleniya Rostehnadzora ot 01 avgusta 2019g 352POZP140 p 12345 srok ispolneniya kotorogo istek
# 001902868271
Unscheduled inspection
Start date: 2019-07-15, end date: 2019-08-09, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to comply with the order of the Federal Service for Environmental Technological and Nuclear Supervision "On monitoring the progress of preparation of heat supply facilities for operation in the autumn winter period of 20192020" dated 04072019 261 issued pursuant to the instruction of the Government of the Russian Federation dated 19062019 VMP95084THE purpose of this inspection is to verify the progress of preparation of heat supply facilities for operation in the autumn winter period of 20192020 checking the provision of safe operation and technical condition of power plants of the main and auxiliary equipment of boiler houses and heating networks The subject of this inspection is the observance of mandatory safety requirements in the field of electric power industry and the observance of mandatory safety requirements in the field of heat supply
# 001902436009
Unscheduled inspection
Start date: 2019-01-16, end date: 2019-02-12, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Nastoyaschaya proverka provoditsya s celyu proverki vypolneniya ranee vydannogo predpisaniya ot 29082018 3627POZP86 punkty 14 vydannogo dolzhnostnymi licami Sibirskogo upravleniya Rostehnadzora srok ispolneniya kotorogo istek Zadachami nastoyaschei proverki yavlyaetsya kontrol za ispolneniem ranee vydannogo predpisaniya ot 29082018 3627POZP86 punkty 14 vydannogo dolzhnostnymi licami Sibirskogo upravleniya Rostehnadzora srok ispolneniya kotorogo istek Predmetom nastoyaschei proverki yavlyaetsya vypolnenie predpisaniya dolzhnostnyh lic Sibirskogo upravleniya Rostehnadzora ot 29082018 3627POZP86 punkty 14
# 001800633398
Unscheduled inspection
Start date: 2018-08-13, end date: 2018-08-31, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this inspection is carried out in order to comply with the order of the Federal Service for Environmental Technological and Nuclear Supervision "On monitoring the preparation of heat supply facilities for operation in the autumn winter period 2018-2019" dated 16072018 308 issued pursuant to the instruction of Deputy Prime Minister of the Russian Federation Vladimir Mutko dated 26062018 VMP93773 the purpose of this inspection is to verify the readiness of the heat supply heating network organization to work in the autumn winter The period 2018-2019 is the verification of the safe operation and technical condition of power plants of the main and auxiliary equipment of boiler houses and heating networks
# 00170701875276
Unscheduled inspection
Start date: 2017-08-28, end date: 2017-09-22, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Checking the readiness of the heat supply organization to work in the autumn-winter period of 2017-2018