# 772100138397
Unscheduled inspection
Start date: 2021-04-26, end date: 2021-05-11, duration: 10
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Control of compliance of the performed works with the mandatory requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for energy resources used and other regulatory legal acts during the construction of the capital construction facility; the task of this check is to prevent, identify and suppress violations committed by the developer, the technical customer, as well as the person carrying out the reconstruction on on the basis of an agreement with a developer or a technical customer, violations of legislation on urban planning, including design documentation, requirements for energy conservation and energy efficiency improvement;
The subject of this review is:compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of the design documentation approved in accordance with Parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation (taking into account the changes made to the design documentation in accordance with Parts 3.8 and 3.9 of Article 49 of the Urban Planning Code Of the Russian Federation) and (or) an information model, including energy efficiency requirements (with the exception of capital construction projects, to which energy efficiency requirements do not apply) and the requirements for equipping the capital construction facility with metering devices for used energy resources;
availability of a building permit;
compliance with the requirements established by Parts 2, 3 and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation.
# 002105306180
Unscheduled inspection
Start date: 2021-01-20, end date: 2021-01-26, duration: 5
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Monitoring the compliance of the work performed with the mandatory requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used and other regulatory legal acts during the construction of the capital construction facility; the purpose of this audit is to prevent, identify and suppress violations committed by the developer, the technical customer, as well as the person carrying out the reconstruction based on a contract with a developer or technical customer, violations of legislation on urban planning, including project documentation, requirements for energy conservation and energy efficiency improvement;
The subject of this review is:compliance of the work performed and the building materials used during the construction, reconstruction of the capital construction facility, as well as the results of such work with the requirements of the project documentation approved in accordance with Parts 15, 15.2 and 15.3 of art. 48 of the Urban Planning Code of the Russian Federation (subject to changes made to the project documentation in accordance with Parts 3.8 and 3.9 of art. 49 of the Urban Planning Code Of the Russian Federation) and (or) an information model, including energy efficiency requirements (with the exception of capital construction facilities that are not subject to energy efficiency requirements) and the requirements for equipping the capital construction facility with metering devices for used energy resources;
availability of a building permit;
compliance with the requirements established by Parts 2, 3 and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation.