Found 98 inspections:

# 772101429392
Unscheduled inspection
Start date: 2021-12-09, end date: 2021-12-15, duration: 5
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The purpose of the audit: carrying out control measures in connection with the verification of compliance with the instruction; The tasks of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: verification of the elimination of violations specified in the instruction issued by Mosgosstroynadzor


# 772101340416
Unscheduled inspection
Start date: 2021-11-15, end date: 2021-11-26, duration: 10
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the inspection program; The tasks of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: checking the elimination of violations specified in the instruction issued by Mosgosstroynadzor compliance of the work and the construction materials used in the construction, reconstruction process the capital construction facility, as well as the results of such work, meet the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of design documentation identified during construction control and state construction supervision


# 772101162406
Unscheduled inspection
Start date: 2021-10-04, end date: 2021-10-29, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the audit program; The tasks of the audit: prevention, identification and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements design documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of design documentation identified during construction control and state construction supervision


# 772101170628
Unscheduled inspection
Start date: 2021-10-04, end date: —, duration:
Authority:
Purpose of inspection:


# 772100936759
Unscheduled inspection
Start date: 2021-10-04, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


# 772101303383
Unscheduled inspection
Start date: 2021-10-01, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


# 772100727906
Unscheduled inspection
Start date: 2021-09-14, end date: —, duration:
Authority:
Purpose of inspection:


# 772100609847
Unscheduled inspection
Start date: 2021-09-01, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


# 772100441577
Unscheduled inspection
Start date: 2021-08-11, end date: 2021-08-18, duration: 6
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The purpose of the audit: carrying out control measures in connection with the verification of compliance with the instruction; The tasks of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: verification of the elimination of violations specified in the instruction issued by Mosgosstroynadzor


# 772100431294
Unscheduled inspection
Start date: 2021-08-09, end date: 2021-08-20, duration: 10
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The purpose of the audit: carrying out control measures in connection with the verification of compliance with the instruction; The tasks of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: verification of the elimination of violations specified in the instruction issued by Mosgosstroynadzor


# 772100473323
Unscheduled inspection
Start date: 2021-08-23, end date: —, duration:
Authority:
Purpose of inspection:


# 772100350254
Unscheduled inspection
Start date: 2021-07-14, end date: 2021-07-23, duration: 8
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The purpose of the audit: carrying out control measures in connection with the verification of compliance with the instruction; The tasks of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: verification of the elimination of violations specified in the instruction issued by Mosgosstroynadzor


# 772100328377
Unscheduled inspection
Start date: 2021-07-05, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


# 772100278428
Unscheduled inspection
Start date: 2021-07-05, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


# 772100367118
Unscheduled inspection
Start date: 2021-07-20, end date: 2021-07-28, duration: 7
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The purpose of the audit: carrying out control measures in connection with the verification of compliance with the instruction; The tasks of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: verification of the elimination of violations specified in the instruction issued by Mosgosstroynadzor


# 772100250438
Unscheduled inspection
Start date: 2021-06-17, end date: 2021-07-07, duration: 15
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the inspection program; The tasks of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: checking the elimination of violations specified in the instruction issued by Mosgosstroynadzor compliance of the work and the construction materials used in the construction, reconstruction process the capital construction facility, as well as the results of such work, meet the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of design documentation identified during construction control and state construction supervision


# 772100250436
Unscheduled inspection
Start date: 2021-06-15, end date: 2021-06-28, duration: 10
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the inspection program; The tasks of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: checking the elimination of violations specified in the instruction issued by Mosgosstroynadzor compliance of the work and the construction materials used in the construction, reconstruction process the capital construction facility, as well as the results of such work, meet the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of design documentation identified during construction control and state construction supervision


# 772100324293
Unscheduled inspection
Start date: 2021-06-30, end date: 2021-07-08, duration: 7
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The purpose of the audit: carrying out control measures in connection with the verification of compliance with the instruction; The tasks of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: verification of the elimination of violations specified in the instruction issued by Mosgosstroynadzor


# 772100244590
Unscheduled inspection
Start date: 2021-06-01, end date: 2021-06-28, duration: 19
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the audit program; The tasks of the audit: prevention, identification and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements design documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of design documentation identified during construction control and state construction supervision


# 772100188286
Unscheduled inspection
Start date: 2021-05-12, end date: 2021-06-08, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the inspection program; The tasks of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: checking the elimination of violations specified in the instruction issued by Mosgosstroynadzor compliance of the work and the construction materials used in the construction, reconstruction process the capital construction facility, as well as the results of such work, meet the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of design documentation identified during construction control and state construction supervision


# 772100251206
Unscheduled inspection
Start date: 2021-05-31, end date: —, duration:
Authority:
Purpose of inspection:


# 772100146802
Unscheduled inspection
Start date: 2021-05-06, end date: —, duration:
Authority:
Purpose of inspection:


# 772100135648
Unscheduled inspection
Start date: 2021-04-09, end date: 2021-04-30, duration: 16
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the audit program; The tasks of the audit: prevention, identification and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements design documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of design documentation identified during construction control and state construction supervision


# 772100080108
Unscheduled inspection
Start date: 2021-04-08, end date: 2021-04-29, duration: 16
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the audit program; The tasks of the audit: prevention, identification and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements design documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of design documentation identified during construction control and state construction supervision


# 772100105906
Unscheduled inspection
Start date: 2021-04-06, end date: 2021-04-14, duration: 7
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the inspection program; The tasks of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: checking the elimination of violations specified in the instruction issued by Mosgosstroynadzor compliance of the work and the construction materials used in the construction, reconstruction process the capital construction facility, as well as the results of such work, meet the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of design documentation identified during construction control and state construction supervision


# 772100035499
Unscheduled inspection
Start date: 2021-03-15, end date: 2021-04-02, duration: 15
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the audit program; The tasks of the audit: prevention, identification and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements design documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of design documentation identified during construction control and state construction supervision


# 772100035498
Unscheduled inspection
Start date: 2021-03-15, end date: 2021-04-02, duration: 15
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the audit program; The tasks of the audit: prevention, identification and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements design documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of design documentation identified during construction control and state construction supervision


# 772100091915
Unscheduled inspection
Start date: 2021-03-29, end date: 2021-04-09, duration: 10
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The purpose of the audit: carrying out control measures in connection with the verification of compliance with the instruction; The tasks of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: verification of the elimination of violations specified in the instruction issued by Mosgosstroynadzor


# 772100082586
Unscheduled inspection
Start date: 2021-03-22, end date: 2021-03-31, duration: 8
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the audit program; The tasks of the audit: prevention, identification and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements design documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of design documentation identified during construction control and state construction supervision


# 772100081842
Unscheduled inspection
Start date: 2021-03-22, end date: 2021-03-30, duration: 7
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the audit program; The tasks of the audit: prevention, identification and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements design documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of design documentation identified during construction control and state construction supervision


# 772105354674
Unscheduled inspection
Start date: 2021-02-16, end date: 2021-03-10, duration: 15
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the audit program; The tasks of the audit: prevention, identification and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements design documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of design documentation identified during construction control and state construction supervision


# 772100036482
Unscheduled inspection
Start date: 2021-02-26, end date: —, duration:
Authority:
Purpose of inspection:


# 772105296481
Unscheduled inspection
Start date: 2021-01-11, end date: —, duration:
Authority:
Purpose of inspection:


# 772005192122
Unscheduled inspection
Start date: 2020-11-02, end date: —, duration:
Authority:
Purpose of inspection:


# 772005219135
Unscheduled inspection
Start date: 2020-11-26, end date: —, duration:
Authority:
Purpose of inspection:


# 772004461324
Unscheduled inspection
Start date: 2020-08-10, end date: —, duration:
Authority:
Purpose of inspection:


# 772004469043
Unscheduled inspection
Start date: 2020-07-27, end date: —, duration:
Authority:
Purpose of inspection:


# 772004432880
Unscheduled inspection
Start date: 2020-07-02, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


# 772004470348
Unscheduled inspection
Start date: 2020-07-31, end date: —, duration:
Authority:
Purpose of inspection:


# 772004427535
Unscheduled inspection
Start date: 2020-06-04, end date: 2020-06-15, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the implementation of the verification program verification tasks prevention identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, subject to verification of compliance of the work and construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including energy efficiency requirements and equipment requirements of the capital construction facility metering devices for energy resources used by specialists in the organization of construction of the main engineers of the project


# 772004425158
Unscheduled inspection
Start date: 2020-06-15, end date: —, duration:
Authority:
Purpose of inspection:


# 772004415400
Unscheduled inspection
Start date: 2020-05-25, end date: 2020-06-10, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the implementation of the verification program verification tasks prevention identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, subject to verification of compliance of the work and construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including energy efficiency requirements and equipment requirements of the capital construction facility metering devices for energy resources used


# 772004413917
Unscheduled inspection
Start date: 2020-05-22, end date: —, duration:
Authority:
Purpose of inspection:


# 772004329626
Unscheduled inspection
Start date: 2020-03-04, end date: 2020-03-05, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the verification of compliance with the requirements of the task of the audit, to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to verify the elimination of violations specified in the order issued by Mosgosstroynadzor


# 772004329083
Unscheduled inspection
Start date: 2020-03-04, end date: —, duration:
Authority:
Purpose of inspection:


# 772004360033
Unscheduled inspection
Start date: 2020-03-13, end date: 2020-03-26, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the verification of compliance with the requirements of the task of the audit, to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to verify the elimination of violations specified in the order issued by Mosgosstroynadzor


# 772004222698
Unscheduled inspection
Start date: 2020-02-04, end date: —, duration:
Authority:
Purpose of inspection:


# 772004284289
Unscheduled inspection
Start date: 2020-02-11, end date: —, duration:
Authority:
Purpose of inspection:


# 772004287174
Unscheduled inspection
Start date: 2020-02-13, end date: —, duration:
Authority:
Purpose of inspection:


# 772004239809
Unscheduled inspection
Start date: 2020-01-28, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


# 772004223890
Unscheduled inspection
Start date: 2020-01-23, end date: —, duration:
Authority:
Purpose of inspection:


# 771904058403
Unscheduled inspection
Start date: 2019-12-03, end date: 2019-12-16, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the implementation of the verification program verification tasks prevention identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, subject to verification of compliance of the work and construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including energy efficiency requirements and equipment requirements of the capital construction facility metering devices for energy resources used


# 771904068352
Unscheduled inspection
Start date: 2019-12-11, end date: 2019-12-19, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with checking the fulfillment of the requirements of the task of the audit, to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to check the compliance of the work and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of the design documentation, including energy efficiency requirements and equipment requirements of the facility capital construction with metering devices for energy resources used


# 771904085972
Unscheduled inspection
Start date: 2019-12-18, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


# 771903950477
Unscheduled inspection
Start date: 2019-11-11, end date: 2019-11-29, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the verification of compliance with the requirements of the task of the audit, to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to verify the elimination of violations specified in the order issued by Mosgosstroynadzor


# 771903864570
Unscheduled inspection
Start date: 2019-10-16, end date: 2019-10-18, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the receipt of a notification from the developer of the customer's task of verification, to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to check and verify the elimination of violations specified in the order issued by Mosgosstroynadzor


# 771903820957
Unscheduled inspection
Start date: 2019-10-16, end date: —, duration:
Authority:
Purpose of inspection:


# 771903610079
Unscheduled inspection
Start date: 2019-09-17, end date: —, duration:
Authority:
Purpose of inspection:


# 771903620941
Unscheduled inspection
Start date: 2019-09-23, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803490285
Unscheduled inspection
Start date: 2019-09-02, end date: 2019-09-04, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 771903619069
Unscheduled inspection
Start date: 2019-09-09, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803471011
Unscheduled inspection
Start date: 2019-08-01, end date: 2019-08-07, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77190803471028
Unscheduled inspection
Start date: 2019-08-01, end date: 2019-08-02, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77190803471027
Unscheduled inspection
Start date: 2019-08-01, end date: 2019-08-07, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77190803471025
Unscheduled inspection
Start date: 2019-08-01, end date: 2019-08-02, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77190803475438
Unscheduled inspection
Start date: 2019-08-09, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803474830
Unscheduled inspection
Start date: 2019-08-09, end date: 2019-08-13, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: carrying out control measures in connection with the verification of compliance with the prescriptionrevention detection and suppression of violations of the requirements of the design documentation of the legislation on urban development activity by the person being checked, verification of the elimination of violations specified in the prescription issued by Mosgosstroynadzor


# 77190803469978
Unscheduled inspection
Start date: 2019-07-31, end date: 2019-08-09, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77190803457307
Unscheduled inspection
Start date: 2019-07-12, end date: 2019-07-22, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77190803460248
Unscheduled inspection
Start date: 2019-07-17, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803457605
Unscheduled inspection
Start date: 2019-07-15, end date: 2019-07-23, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77190803450639
Unscheduled inspection
Start date: 2019-07-04, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803454091
Unscheduled inspection
Start date: 2019-07-09, end date: 2019-07-12, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77190803452976
Unscheduled inspection
Start date: 2019-07-08, end date: 2019-07-10, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77190803452486
Unscheduled inspection
Start date: 2019-07-08, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803436598
Unscheduled inspection
Start date: 2019-06-14, end date: 2019-06-27, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 501902898095
Unscheduled inspection
Start date: 2019-06-11, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803445535
Unscheduled inspection
Start date: 2019-06-25, end date: 2019-06-26, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: carrying out control measures in connection with the verification of compliance with the prescriptionrevention detection and suppression of violations of the requirements of the design documentation of the legislation on urban development activity by the person being checked, verification of the elimination of violations specified in the prescription issued by Mosgosstroynadzor


# 77190803415070
Unscheduled inspection
Start date: 2019-06-03, end date: 2019-06-14, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77190803417735
Unscheduled inspection
Start date: 2019-05-16, end date: 2019-06-03, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77190803417660
Unscheduled inspection
Start date: 2019-05-16, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803418013
Unscheduled inspection
Start date: 2019-05-21, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803418004
Unscheduled inspection
Start date: 2019-05-21, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803422940
Unscheduled inspection
Start date: 2019-05-24, end date: 2019-05-29, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: this audit is carried out in order to carry out control measures in connection with the verification of the fulfillment of the instruction on the basis of the expiration of the deadline for the execution by a legal entity, an individual entrepreneur, issued by the state construction supervision authority, of an order to eliminate an identified violation of mandatory requirements from 06032019 121419 The objectives of this audit are to prevent identify and suppress violations of the requirements of the design documentation of the legislation on urban planning activity by the subject of this audit It is a verification of the elimination of violations specified in the order issued by Mosgosstroynadzor 121419 of 06032019


# 77190803422495
Unscheduled inspection
Start date: 2019-05-24, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803423350
Unscheduled inspection
Start date: 2019-05-29, end date: 2019-05-31, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77190803423349
Unscheduled inspection
Start date: 2019-05-29, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803406839
Unscheduled inspection
Start date: 2019-04-30, end date: 2019-05-31, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77190803400475
Unscheduled inspection
Start date: 2019-04-22, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803407570
Unscheduled inspection
Start date: 2019-04-26, end date: 2019-04-30, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: carrying out control measures in connection with the verification of compliance with the prescriptionrevention detection and suppression of violations of the requirements of the design documentation of the legislation on urban development activity by the person being checked, verification of the elimination of violations specified in the prescription issued by Mosgosstroynadzor


# 77190803392954
Unscheduled inspection
Start date: 2019-04-09, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803347056
Unscheduled inspection
Start date: 2019-03-11, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803382690
Unscheduled inspection
Start date: 2019-03-29, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803382691
Unscheduled inspection
Start date: 2019-03-29, end date: 2019-04-18, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77190803331497
Unscheduled inspection
Start date: 2019-02-14, end date: 2019-02-27, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: this audit is carried out in order to ensure that the capital construction facility meets the requirements of technical regulations and design documentation on the basis of the approved inspection program dated 16072018 1 The objectives of this audit are to prevent identify and suppress violations of technical regulations and design documentation committed by the audited person. The subject of this audit is the compliance of the work and construction materials used during the construction reconstruction of the capital construction facility as well as the results of such inspections works according to the requirements of the technical regulations of the project documentation, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for used energy resources


# 77190803317353
Unscheduled inspection
Start date: 2019-01-25, end date: 2019-02-14, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 501802193354
Unscheduled inspection
Start date: 2018-10-17, end date: 2018-11-02, duration:
Authority: Glavnoe upravlenie gosudarstvennogo stroitelnogo nadzora Moskovskoi oblasti
Purpose of inspection: verification of the elimination of violations within the framework of regulation 0980018500502 dated 17092018 with a deadline of 17102018


# 501802193272
Unscheduled inspection
Start date: 2018-10-17, end date: 2018-11-02, duration:
Authority: Glavnoe upravlenie gosudarstvennogo stroitelnogo nadzora Moskovskoi oblasti
Purpose of inspection: verification of the elimination of violations within the framework of regulation 0980018400502 of 17092018 with a deadline of 17102018


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.