Found 19 inspections:

# 472004470933
Unscheduled inspection
Start date: 2020-04-09, end date: 2020-05-14, duration: 20
Authority: Gosudarstvennaya inspekciya truda v Leningradskoi oblasti
Purpose of inspection: Verification of compliance with labor legislation


# 472005297819
Unscheduled inspection
Start date: 2020-04-09, end date: 2020-05-14, duration:
Authority: Gosudarstvennaya inspekciya truda v Leningradskoi oblasti
Purpose of inspection: Verification of compliance with labor legislation


# 472005297791
Unscheduled inspection
Start date: 2020-02-11, end date: 2020-03-11, duration:
Authority: Gosudarstvennaya inspekciya truda v Leningradskoi oblasti
Purpose of inspection: Verification of compliance with labor legislation


# 472004470923
Unscheduled inspection
Start date: 2020-02-20, end date: 2020-03-20, duration: 20
Authority: Gosudarstvennaya inspekciya truda v Leningradskoi oblasti
Purpose of inspection: Verification of compliance with labor legislation


# 471902866353
Unscheduled inspection
Start date: 2019-07-10, end date: 2019-08-06, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of works at the beginning of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban planning activities committed by the developer, the technical customer, the person carrying out the construction, including technical regulations and project documentation


# 471902866347
Unscheduled inspection
Start date: 2019-07-10, end date: 2019-08-06, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of works at the beginning of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban planning activities committed by the developer, the technical customer, the person carrying out the construction, including technical regulations and project documentation


# 471902866333
Unscheduled inspection
Start date: 2019-07-10, end date: 2019-08-06, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of works at the beginning of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban planning activities committed by the developer, the technical customer, the person carrying out the construction, including technical regulations and project documentation


# 471902876438
Unscheduled inspection
Start date: 2019-07-18, end date: —, duration:
Authority:
Purpose of inspection:


# 471902876431
Unscheduled inspection
Start date: 2019-07-18, end date: —, duration:
Authority:
Purpose of inspection:


# 471902876425
Unscheduled inspection
Start date: 2019-07-18, end date: 2019-08-14, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of works at the beginning of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban planning activities committed by the developer, the technical customer, the person carrying out the construction, including technical regulations and project documentation


# 471902839060
Unscheduled inspection
Start date: 2019-06-27, end date: 2019-07-24, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of works at the beginning of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban planning activities committed by the developer, the technical customer, the person carrying out the construction, including technical regulations and project documentation


# 471902830654
Unscheduled inspection
Start date: 2019-06-27, end date: —, duration:
Authority:
Purpose of inspection:


# 471902830641
Unscheduled inspection
Start date: 2019-06-27, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection:


# 471902830629
Unscheduled inspection
Start date: 2019-06-27, end date: 2019-07-24, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of works at the beginning of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban planning activities committed by the developer, the technical customer, the person carrying out the construction, including technical regulations and project documentation


# 471902830619
Unscheduled inspection
Start date: 2019-06-27, end date: 2019-07-24, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of works at the beginning of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban planning activities committed by the developer, the technical customer, the person carrying out the construction, including technical regulations and project documentation


# 471902830684
Unscheduled inspection
Start date: 2019-06-27, end date: 2019-07-24, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of works at the beginning of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban planning activities committed by the developer, the technical customer, the person carrying out the construction, including technical regulations and project documentation


# 471902830675
Unscheduled inspection
Start date: 2019-06-27, end date: 2019-07-24, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of works at the beginning of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban planning activities committed by the developer, the technical customer, the person carrying out the construction, including technical regulations and project documentation


# 471902830611
Unscheduled inspection
Start date: 2019-06-27, end date: 2019-07-24, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of works at the beginning of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban planning activities committed by the developer, the technical customer, the person carrying out the construction, including technical regulations and project documentation


# 471902830662
Unscheduled inspection
Start date: 2019-06-27, end date: 2019-07-24, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of works at the beginning of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban planning activities committed by the developer, the technical customer, the person carrying out the construction, including technical regulations and project documentation