# 782201513172
Unscheduled inspection
Start date: 2022-01-10, end date: 2022-02-04, duration: 17
Authority: Komitet pravoporyadka i bezopasnosti Leningradskoi oblasti
Purpose of inspection: kontrolya ispolneniya punktov №№ 2 - 3 predpisaniya organa gosudarstvennogo nadzora ob ustranenii narushenii obyazatelnyh trebovanii v oblasti zaschity naseleniya i territorii ot chrezvychainyh situacii prirodnogo i tehnogennogo haraktera ot «02» fevralya 2021 goda P VP № 1, Zadachami nastoyaschei proverki yavlyayutsya: - preduprezhdenie, vyyavlenie i presechenie narushenii obektom nadzora obyazatelnyh trebovanii v oblasti zaschity naseleniya i territorii ot chrezvychainyh situacii;, - sistematicheskoe nablyudenie za ispolneniem obyazatelnyh trebovanii v oblasti zaschity naseleniya i territorii ot chrezvychainyh situacii;, - predotvraschenie vozmozhnogo prichineniya vreda zhizni i zdorovyu grazhdan., Predmetom nastoyaschei proverki yavlyaetsya: - vypolnenie predpisanii (predpisaniya) ob ustranenii narushenii obyazatelnyh trebovanii v oblasti zaschity naseleniya i territorii ot chrezvychainyh situacii prirodnogo i tehnogennogo haraktera.
# 472105293063
Unscheduled inspection
Start date: 2021-01-01, end date: —, duration: —
Authority: —
Purpose of inspection:
# 471903973827
Unscheduled inspection
Start date: 2019-11-15, end date: 2019-12-12, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of elimination of violations of the mandatory requirements specified in the notice of the person carrying out the construction on elimination of the identified violations The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the facility capital construction metering devices for energy resources used to comply with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out the construction
# 471902961897
Unscheduled inspection
Start date: 2019-08-14, end date: 2019-09-05, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po Leningradskoi oblasti
Purpose of inspection: nastoyaschaya proverka provoditsya s celyu ispolneniya protokola operativnogo soveschaniya Soveta Bezopasnosti Rossiiskoi Federacii ot 30052019 utverzhdennogoPrezidentom Rossiiskoi Federacii 06062019zadacha vyyavlenie presechenie i preduprezhdenie vozmozhnyh narushenii trebovanii pozharnoi bezopasnosti osuschestvlenie sistematicheskogo nablyudeniya za ispolneniem trebovanii pozharnoi bezopasnosti predmet soblyudenie trebovanii pozharnoi bezopasnosti na obekte zaschity ispolzuemom ekspluatiruemom organizaciei v processe osuschestvleniya svoei deyatelnosti
# 471903775858
Unscheduled inspection
Start date: 2019-08-23, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection:
# 471902683851
Unscheduled inspection
Start date: 2019-04-24, end date: —, duration: —
Authority: —
Purpose of inspection:
# 471902455973
Unscheduled inspection
Start date: 2019-01-23, end date: 2019-02-19, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of elimination of violations of the mandatory requirements specified in the notice of the person carrying out the construction on elimination of the identified violations The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the facility capital construction with metering devices for used energy resources compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 471800527722
Unscheduled inspection
Start date: 2018-07-05, end date: 2018-08-01, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of completion of work on the implementation of construction reconstruction of the capital construction facility specified in the notice of the developer technical customer on completion of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for used energy resources compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out construction
# 47170803030540
Unscheduled inspection
Start date: 2017-12-22, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection:
# 47170701507831
Unscheduled inspection
Start date: 2017-04-03, end date: 2017-04-28, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose of checking the elimination of violations of the mandatory requirements specified in the notice of the person carrying out the construction on the elimination of the identified violations. The subject of this check is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the capital construction facility metering devices for used energy resourcescompliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation
# 47160701261078
Unscheduled inspection
Start date: 2016-12-22, end date: 2017-01-25, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of completion of work on the implementation of construction reconstruction of the capital construction facility specified in the notice of the developer of the technical customer on the completion of construction The subject of this audit is compliance with mandatory requirements including compliance of the work and the construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations design documentation including energy efficiency requirements and requirements equipment of the capital construction facility with accounting devices for the energy resources used, compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation