Found 21 inspection:

# 242100037890
Unscheduled inspection
Start date: 2021-03-02, end date: 2021-03-30, duration: 20
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: 6. Establish that: this audit is conducted for the purpose of state control and supervision in the field of shared-equity construction of apartment buildings and (or) other real estate objects based on the identification of signs of violation of mandatory requirements established by legislation on participation in shared-equity construction of apartment buildings and (or) other real estate objects during the analysis of the project declaration (reasoned submission based on the results of the preliminary audit dated 02/24/2021 No. 7); The objectives of this audit are: prevention, detection and suppression of violations of the requirements of legislation in the field of shared-equity construction of apartment buildings and (or) other real estate objects. 7. The subject of this audit is: compliance with mandatory requirements and (or) requirements established by municipal legal acts.


# 242004237570
Unscheduled inspection
Start date: 2020-01-29, end date: 2020-02-26, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: To establish that this audit is conducted for the purpose of state control and supervision in the field of shared-equity construction of apartment buildings and or other real estate objects based on the identification during the analysis of the developer's quarterly reports on activities related to attracting funds from participants in shared-equity construction for the construction of apartment buildings and or other real estate objects of signs of violation of mandatory requirements motivated presentation based on the results preliminary inspection dated 25/12/2019 359 the objectives of this inspection are to prevent identify and suppress violations of the requirements of legislation in the field of shared-equity construction of apartment buildings and or other real estate


# 242004204290
Unscheduled inspection
Start date: 2020-01-20, end date: 2020-02-14, duration: 20
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility on the basis of the received notice 1 dated 13012020 on the completion of the construction of the capital construction facility. The objectives of this inspection are to prevent identify and suppress violations of legislation on urban development activities, including project documentation


# 241904053042
Unscheduled inspection
Start date: 2019-12-05, end date: 2020-01-09, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility on the basis of the received notification 292 dated 28/12/2019 on the completion of the construction of the capital construction facility. The objectives of this inspection are to prevent identify and suppress violations of legislation on urban development activities, including project documentation


# 241903810583
Unscheduled inspection
Start date: 2019-10-10, end date: —, duration:
Authority:
Purpose of inspection:


# 24190803382450
Unscheduled inspection
Start date: 2019-04-01, end date: 2019-04-26, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: The purpose of checking the implementation of regional state construction supervision during the construction of the specified capital construction facility in connection with the deadline for completion of work that is subject to verification in accordance with the approved program from 05052016 inspections during the construction of the capital construction facility The tasks of the inspection are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation The subject of the inspection is verification compliance of the work performed and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations and design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used verification of the certificate of admission to the types of work on the construction of the capital construction facility that affect the safety of the facility capital construction


# 241902343511
Unscheduled inspection
Start date: 2019-01-09, end date: 2019-01-31, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility in connection with the timing of completion of work that is subject to inspection in accordance with the approved program of 05052016 inspections during the construction of the capital construction facility the objectives of this inspection are to prevent identify and suppress violations of legislation on urban development, including technical regulations and 7 The subject of this audit is 71 Verification of the compliance of the work performed and the building materials used during the construction of an investment facility, as well as the results of such work, with the requirements of the project documentation, including energy efficiency requirements, with the exception of capital construction facilities that are not subject to energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for energy resources used. 72 Meeting the requirements set out in Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation 73 Checking the availability of a building permit


# 241800556596
Unscheduled inspection
Start date: 2018-07-27, end date: 2018-08-09, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This audit is carried out in order to verify the fulfillment of the instruction dated 28062018 1852GSN on the elimination of identified violations at the specified capital construction facility, which expires on 26072018. The objectives of this audit are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed period 7. The subject of this audit is to comply with the instructions of the authority carrying out regional state construction supervision


# 241800471908
Unscheduled inspection
Start date: 2018-06-13, end date: 2018-07-10, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: in order to carry out state control and supervision in the field of shared-equity construction of apartment buildings and or other real estate objects based on the identification, during the analysis of the project declaration, of signs of violation of mandatory requirements established by legislation on participation in shared-equity construction of apartment buildings and or other real estate objects motivated submission based on the results of a preliminary audit dated 01062018 73 the objectives of this audit are to prevent identify and suppression of violations of the requirements of legislation in the field of shared-equity construction of apartment buildings and or other real estate objects 7 The subject of this audit is compliance with mandatory requirements and or requirements established by municipal legal acts


# 241800458093
Unscheduled inspection
Start date: 2018-06-07, end date: 2018-07-05, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This audit is conducted for the purpose of state control and supervision in the field of shared-equity construction of apartment buildings and or other real estate objects based on the identification during the analysis of the developer's quarterly reports on activities related to attracting funds from participants in shared-equity construction for the construction of apartment buildings and or other real estate objects of signs of violation of mandatory requirements motivated by the results of preliminary inspections dated 01062018 72 The objectives of this audit are to prevent identify and suppress violations of the requirements of legislation in the field of shared-equity construction of apartment buildings and or other real estate objects The subject of this audit is compliance with mandatory requirements and or requirements established by municipal legal acts


# 241800385794
Unscheduled inspection
Start date: 2018-06-01, end date: 2018-06-29, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility in connection with the timing of completion of work that is subject to inspection in accordance with the approved program of 05052016 inspections during the construction of the capital construction facility the objectives of this inspection are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation 7 The subject of this audit is 71 Verification of the compliance of the work performed and the building materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used 72 Compliance with the requirements established by parts 2 3 and 31 of the Article 52 of the Urban Planning Code of the Russian Federation 73 Checking the availability of a building permit


# 241800192669
Unscheduled inspection
Start date: 2018-03-12, end date: —, duration:
Authority:
Purpose of inspection:


# 241800026251
Unscheduled inspection
Start date: 2018-02-01, end date: 2018-02-28, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility in connection with the timing of completion of work that is subject to inspection in accordance with the approved program of 05052016 inspections during the construction of the capital construction facility the objectives of this inspection are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation 7 The subject of this audit is 71 Verification of the compliance of the work performed and the building materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used 72 Compliance with the requirements established by parts 2 3 and 31 of the Article 52 of the Urban Planning Code of the Russian Federation 73 Checking the availability of a building permit


# 24170802926650
Unscheduled inspection
Start date: 2017-12-08, end date: —, duration:
Authority:
Purpose of inspection:


# 24170803029330
Unscheduled inspection
Start date: 2017-12-26, end date: —, duration:
Authority:
Purpose of inspection:


# 24170802888930
Unscheduled inspection
Start date: 2017-11-20, end date: 2017-12-15, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: the purpose of state control and supervision in the field of shared-equity construction of apartment buildings and or other real estate objects based on a reasoned submission dated 09/12017 g 254 tasks prevention detection and suppression of violations of legislation in the field of shared-equity construction of apartment buildings and or other real estate objects subject to compliance with mandatory requirements and or requirements established by municipal legal acts


# 24170802655094
Unscheduled inspection
Start date: 2017-09-28, end date: —, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection:


# 24170801910333
Unscheduled inspection
Start date: 2017-09-01, end date: —, duration:
Authority:
Purpose of inspection:


# 24170701742342
Unscheduled inspection
Start date: 2017-06-19, end date: 2017-07-14, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: In order to carry out state control and supervision in the field of shared-equity construction of apartment buildings and or other real estate objects, the tasks are to prevent identify and suppress violations of legislation in the field of shared-equity construction of apartment buildings and or other real estate objects. The subject is compliance with mandatory requirements and or requirements established by municipal legal acts


# 24170701380306
Unscheduled inspection
Start date: 2017-03-03, end date: 2017-03-31, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility in connection with the timing of completion of work that is subject to inspection in accordance with the approved program of 05052016 inspections during the construction of the capital construction facility the objectives of this inspection are to prevent identify and suppress violations of legislation on urban development, including technical regulations and The subject of this audit is to verify the compliance of the work performed and the building materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, Checking the availability of a certificate of admission to the types of work on the construction of the capital construction facility that have an impact on the safety of a capital construction facility


# 24170701334753
Unscheduled inspection
Start date: 2017-02-02, end date: —, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection:


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.