Found 7 inspections:

# 002005243827
Unscheduled inspection
Start date: 2020-11-16, end date: 2020-11-18, duration: 3
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this inspection is carried out in order to control the compliance of the completed works with the mandatory requirements of the design documentation requirements for energy conservation and energy efficiency improvement during the construction of a capital construction facility on the basis of a notice of completion of construction Case 2569 "Administrative building of the Prosecutor's Office of Kuznetsk, Kuznetsky district, Komsomolskaya street 34A" located at the address Russian Federation Penza region, Kuznetsk, Komsomolskaya Street 34 The tasks of this inspection are verification of compliance with mandatory requirements of legislation on urban planning activities, including design documentation, as well as requirements for energy conservation and energy efficiency improvement during the construction of a capital construction facility by the developer, the technical customer, as well as the person carrying out construction on the basis of an agreement with the developer or technical customer, the subject of this audit is the compliance of the work and the construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work, the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, including energy efficiency requirements, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements for equipping the capital construction facility with metering devices for energy resources used on the basis of a notice of completion of construction, the availability of a permit for construction compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 002005195437
Unscheduled inspection
Start date: 2020-10-14, end date: 2020-11-11, duration: 20
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the real test is conducted to monitor compliance of the performed works with the mandatory requirements of the project documentation requirements on energy saving and increase of energy efficiency in the construction of capital construction object on the basis of a programme of inspections Thing 2569 "Administrative building of the Prosecutor's office g Kuznetsk Kuznetsk district ul Komsomolskaya 34A" located at Russian Federation, Penza region, Kuznetsk, ulitsa Komsomolskaya 34Азадачами of this test is to verify compliance with the mandatory requirements of the legislation on town-planning including project documentation and requirements on energy saving and increase of energy efficiency in the construction of capital construction object developer technical customer and the person in charge of the construction on the basis of the contract with the developer or technical customer the Subject of this review alleycatallies works and construction materials used in the construction process of reconstruction of capital construction object and the results of such work requirements approved in accordance with paragraphs 152 and 153 of 15 of article 48 of the town planning code of the Russian Federation the project documentation according changes in the design documentation in accordance with paragraphs 38 and 39 of article 49 of the town planning code of the Russian Federation or the information model, including the energy efficiency standards and requirements of the equipment of a capital construction object metering devices of energy resources used in accordance with the program of carrying out checks of the building permit compliance with the requirements of parts 2 3 and 31 St 52 of the town planning code of the Russian Federation


# 002004392180
Unscheduled inspection
Start date: 2020-02-19, end date: —, duration:
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:


# 002005243827
Unscheduled inspection
Start date: 2020-11-16, end date: 2020-11-18, duration: 3
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this inspection is carried out in order to control the compliance of the completed works with the mandatory requirements of the design documentation requirements for energy conservation and energy efficiency improvement during the construction of a capital construction facility on the basis of a notice of completion of construction Case 2569 "Administrative building of the Prosecutor's Office of Kuznetsk, Kuznetsky district, Komsomolskaya street 34A" located at the address Russian Federation Penza region, Kuznetsk, Komsomolskaya Street 34 The tasks of this inspection are verification of compliance with mandatory requirements of legislation on urban planning activities, including design documentation, as well as requirements for energy conservation and energy efficiency improvement during the construction of a capital construction facility by the developer, the technical customer, as well as the person carrying out construction on the basis of an agreement with the developer or technical customer, the subject of this audit is the compliance of the work and the construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work, the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, including energy efficiency requirements, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements for equipping the capital construction facility with metering devices for energy resources used on the basis of a notice of completion of construction, the availability of a permit for construction compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 002005195437
Unscheduled inspection
Start date: 2020-10-14, end date: 2020-11-11, duration: 20
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the real test is conducted to monitor compliance of the performed works with the mandatory requirements of the project documentation requirements on energy saving and increase of energy efficiency in the construction of capital construction object on the basis of a programme of inspections Thing 2569 "Administrative building of the Prosecutor's office g Kuznetsk Kuznetsk district ul Komsomolskaya 34A" located at Russian Federation, Penza region, Kuznetsk, ulitsa Komsomolskaya 34Азадачами of this test is to verify compliance with the mandatory requirements of the legislation on town-planning including project documentation and requirements on energy saving and increase of energy efficiency in the construction of capital construction object developer technical customer and the person in charge of the construction on the basis of the contract with the developer or technical customer the Subject of this review alleycatallies works and construction materials used in the construction process of reconstruction of capital construction object and the results of such work requirements approved in accordance with paragraphs 152 and 153 of 15 of article 48 of the town planning code of the Russian Federation the project documentation according changes in the design documentation in accordance with paragraphs 38 and 39 of article 49 of the town planning code of the Russian Federation or the information model, including the energy efficiency standards and requirements of the equipment of a capital construction object metering devices of energy resources used in accordance with the program of carrying out checks of the building permit compliance with the requirements of parts 2 3 and 31 St 52 of the town planning code of the Russian Federation


# 002004472019
Unscheduled inspection
Start date: 2020-07-07, end date: 2020-08-03, duration: 20
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the real test is conducted to monitor compliance of the performed works with the mandatory requirements of the project documentation requirements on energy saving and increase of energy efficiency in the construction of capital construction object on the basis of a programme of inspections Thing 2569 "Administrative building of the Prosecutor's office g Kuznetsk Kuznetsk district ul Komsomolskaya 34A" located at Russian Federation, Penza region, Kuznetsk, ulitsa Komsomolskaya 34Азадачами of this test is to verify compliance with the mandatory requirements of the legislation on town-planning including project documentation and requirements on energy saving and increase of energy efficiency in the construction of capital construction object developer technical customer and the person in charge of the construction on the basis of the contract with the developer or technical customer the Subject of this review alleycatallies works and construction materials used in the construction process of reconstruction of capital construction object and the results of such work requirements approved in accordance with paragraphs 152 and 153 of 15 of article 48 of the town planning code of the Russian Federation the project documentation according changes in the design documentation in accordance with paragraphs 38 and 39 of article 49 of the town planning code of the Russian Federation or the information model, including the energy efficiency standards and requirements of the equipment of a capital construction object metering devices of energy resources used in accordance with the program of carrying out checks of the building permit compliance with the requirements of parts 2 3 and 31 St 52 of the town planning code of the Russian Federation


# 002004392180
Unscheduled inspection
Start date: 2020-02-19, end date: 2020-03-18, duration:
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the real test is conducted to monitor compliance of the performed works with the mandatory requirements of the project documentation requirements on energy saving and increase of energy efficiency in the construction of capital construction object on the basis of a programme of inspections Thing 2569 "Administrative building of the Prosecutor's office g Kuznetsk Kuznetsk district ul Komsomolskaya 34A" located at Russian Federation, Penza region, Kuznetsk, ulitsa Komsomolskaya 34Азадачами of this test is to verify compliance with the mandatory requirements of the legislation on town-planning including project documentation and requirements on energy saving and increase of energy efficiency in the construction of capital construction object developer technical customer and the person in charge of the construction on the basis of the contract with the developer or technical customer the Subject of this review alleycatallies works and construction materials used in the construction process of reconstruction of capital construction object and the results of such work requirements approved in accordance with paragraphs 152 and 153 of 15 of article 48 of the town planning code of the Russian Federation the project documentation according changes in the design documentation in accordance with paragraphs 38 and 39 of article 49 of the town planning code of the Russian Federation or the information model, including the energy efficiency standards and requirements of the equipment of a capital construction object metering devices of energy resources used in accordance with the program of carrying out checks of the building permit compliance with the requirements of parts 2 3 and 31 St 52 of the town planning code of the Russian Federation


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.