# 782100096509
Unscheduled inspection
Start date: 2021-03-15, end date: 2021-04-09, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: proverki ispolneniya vydannogo predpisaniya ob ustranenii vyyavlennogo narusheniya № P804-BS-19 ot "04" oktyabrya 2019 goda, srok ispolneniya kotorogo istek "31" yanvarya 2020 goda;
vypolnenie predpisanii komiteta gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti;
# 782100096680
Unscheduled inspection
Start date: 2021-03-15, end date: 2021-04-09, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: proverki ispolneniya vydannogo predpisaniya ob ustranenii vyyavlennogo narusheniya № P801-BS-19 ot "04" oktyabrya 2019 goda, srok ispolneniya kotorogo istek "31" yanvarya 2020 goda;
vypolnenie predpisanii komiteta gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti;
# 782100096627
Unscheduled inspection
Start date: 2021-03-15, end date: 2021-04-09, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: proverki ispolneniya vydannogo predpisaniya ob ustranenii vyyavlennogo narusheniya № P802-BS-19 ot "04" oktyabrya 2019 goda, srok ispolneniya kotorogo istek "31" yanvarya 2020 goda;
vypolnenie predpisanii komiteta gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti;
# 472004439144
Unscheduled inspection
Start date: 2020-06-23, end date: 2020-07-22, duration: 14
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of completion of work on the implementation of construction reconstruction of the capital construction facility specified in the notice of the developer technical customer on completion of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for used energy resources compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out construction
# 472004329330
Unscheduled inspection
Start date: 2020-03-02, end date: 2020-03-30, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose of checking the execution of the issued instruction on the elimination of identified violations The subject of this audit is the fulfillment of the instructions of the Committee of State Construction Supervision and State expertise of the Leningrad Region the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations, and the design objectives of this audit are to prevent identify and suppress by the developer, the technical customer, the person carrying out the construction of violations of the legislation on urban planning activities, including technical regulations and project documentation
# 472004348576
Unscheduled inspection
Start date: 2020-03-11, end date: —, duration: —
Authority: —
Purpose of inspection:
# 472004348561
Unscheduled inspection
Start date: 2020-03-11, end date: 2020-04-07, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose of checking the execution of the issued instruction on the elimination of identified violations The subject of this audit is the fulfillment of the instructions of the Committee of State Construction Supervision and State expertise of the Leningrad Region the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations, and the design objectives of this audit are to prevent identify and suppress by the developer, the technical customer, the person carrying out the construction of violations of the legislation on urban planning activities, including technical regulations and project documentation
# 472004370935
Unscheduled inspection
Start date: 2020-03-19, end date: 2020-04-15, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose of checking the execution of the issued instruction on the elimination of identified violations The subject of this audit is the fulfillment of the instructions of the Committee of State Construction Supervision and State expertise of the Leningrad Region the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations, and the design objectives of this audit are to prevent identify and suppress by the developer, the technical customer, the person carrying out the construction of violations of the legislation on urban planning activities, including technical regulations and project documentation
# 471904069267
Unscheduled inspection
Start date: 2019-12-02, end date: 2019-12-27, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of elimination of violations of the mandatory requirements specified in the notice of the person carrying out the construction on elimination of the identified violations The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the facility capital construction metering devices for energy resources used to comply with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out the construction
# 471903785140
Unscheduled inspection
Start date: 2019-10-02, end date: 2019-10-29, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose of checking the execution of the issued instruction on the elimination of identified violations The subject of this audit is the fulfillment of the instructions of the Committee of State Construction Supervision and State expertise of the Leningrad Region the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations, and the design objectives of this audit are to prevent identify and suppress by the developer, the technical customer, the person carrying out the construction of violations of the legislation on urban planning activities, including technical regulations and project documentation
# 471903785061
Unscheduled inspection
Start date: 2019-10-02, end date: 2019-10-29, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose of checking the execution of the issued instruction on the elimination of identified violations The subject of this audit is the fulfillment of the instructions of the Committee of State Construction Supervision and State expertise of the Leningrad Region the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations, and the design objectives of this audit are to prevent identify and suppress by the developer, the technical customer, the person carrying out the construction of violations of the legislation on urban planning activities, including technical regulations and project documentation
# 471903785158
Unscheduled inspection
Start date: 2019-10-02, end date: 2019-10-29, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose of checking the execution of the issued instruction on the elimination of identified violations The subject of this audit is the fulfillment of the instructions of the Committee of State Construction Supervision and State expertise of the Leningrad Region the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations, and the design objectives of this audit are to prevent identify and suppress by the developer, the technical customer, the person carrying out the construction of violations of the legislation on urban planning activities, including technical regulations and project documentation
# 471903785154
Unscheduled inspection
Start date: 2019-10-02, end date: 2019-10-29, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose of checking the execution of the issued instruction on the elimination of identified violations The subject of this audit is the fulfillment of the instructions of the Committee of State Construction Supervision and State expertise of the Leningrad Region the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations, and the design objectives of this audit are to prevent identify and suppress by the developer, the technical customer, the person carrying out the construction of violations of the legislation on urban planning activities, including technical regulations and project documentation
# 471903864959
Unscheduled inspection
Start date: 2019-10-14, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection:
# 471903804582
Unscheduled inspection
Start date: 2019-09-02, end date: 2019-09-27, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of elimination of violations of the mandatory requirements specified in the notice of the person carrying out the construction on elimination of the identified violations The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the facility capital construction metering devices for energy resources used to comply with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out the construction
# 471902852536
Unscheduled inspection
Start date: 2019-07-03, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection:
# 471902852525
Unscheduled inspection
Start date: 2019-07-03, end date: —, duration: —
Authority: —
Purpose of inspection:
# 471902761190
Unscheduled inspection
Start date: 2019-06-03, end date: 2019-07-01, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose of checking the execution of the issued instruction on the elimination of identified violations The subject of this audit is the fulfillment of the instructions of the Committee of State Construction Supervision and State expertise of the Leningrad Region the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations, and the design objectives of this audit are to prevent identify and suppress by the developer, the technical customer, the person carrying out the construction of violations of the legislation on urban planning activities, including technical regulations and project documentation
# 471902761182
Unscheduled inspection
Start date: 2019-06-03, end date: —, duration: —
Authority: —
Purpose of inspection:
# 471902761158
Unscheduled inspection
Start date: 2019-06-03, end date: 2019-07-01, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose of checking the execution of the issued instruction on the elimination of identified violations The subject of this audit is the fulfillment of the instructions of the Committee of State Construction Supervision and State expertise of the Leningrad Region the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations, and the design objectives of this audit are to prevent identify and suppress by the developer, the technical customer, the person carrying out the construction of violations of the legislation on urban planning activities, including technical regulations and project documentation
# 781902559576
Unscheduled inspection
Start date: 2019-03-14, end date: —, duration: —
Authority: —
Purpose of inspection:
# 471902562403
Unscheduled inspection
Start date: 2019-03-06, end date: 2019-04-03, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose of checking the execution of the issued instruction on the elimination of identified violations The subject of this audit is the fulfillment of the instructions of the Committee of State Construction Supervision and State expertise of the Leningrad Region the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations, and the design objectives of this audit are to prevent identify and suppress by the developer, the technical customer, the person carrying out the construction of violations of the legislation on urban planning activities, including technical regulations and project documentation
# 471902562337
Unscheduled inspection
Start date: 2019-03-06, end date: 2019-04-03, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose of checking the execution of the issued instruction on the elimination of identified violations The subject of this audit is the fulfillment of the instructions of the Committee of State Construction Supervision and State expertise of the Leningrad Region the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations, and the design objectives of this audit are to prevent identify and suppress by the developer, the technical customer, the person carrying out the construction of violations of the legislation on urban planning activities, including technical regulations and project documentation
# 471902562393
Unscheduled inspection
Start date: 2019-03-06, end date: 2019-04-03, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose of checking the execution of the issued instruction on the elimination of identified violations The subject of this audit is the fulfillment of the instructions of the Committee of State Construction Supervision and State expertise of the Leningrad Region the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations, and the design objectives of this audit are to prevent identify and suppress by the developer, the technical customer, the person carrying out the construction of violations of the legislation on urban planning activities, including technical regulations and project documentation
# 471902602525
Unscheduled inspection
Start date: 2019-03-25, end date: —, duration: —
Authority: —
Purpose of inspection:
# 471902602517
Unscheduled inspection
Start date: 2019-03-25, end date: 2019-04-19, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose of checking the execution of the issued instruction on the elimination of identified violations The subject of this audit is the fulfillment of the instructions of the Committee of State Construction Supervision and State expertise of the Leningrad Region the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations, and the design objectives of this audit are to prevent identify and suppress by the developer, the technical customer, the person carrying out the construction of violations of the legislation on urban planning activities, including technical regulations and project documentation
# 471802306206
Unscheduled inspection
Start date: 2018-12-10, end date: 2019-01-14, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of the execution of the issued instruction on the elimination of identified violations The subject of this audit is the fulfillment of the instructions of the Committee of State Construction Supervision and State expertise of the Leningrad region
# 471802137408
Unscheduled inspection
Start date: 2018-11-22, end date: 2018-12-19, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of the execution of the issued instruction on the elimination of identified violations The subject of this audit is the fulfillment of the instructions of the Committee of State Construction Supervision and State expertise of the Leningrad region
# 471802137403
Unscheduled inspection
Start date: 2018-11-22, end date: 2018-12-19, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of the execution of the issued instruction on the elimination of identified violations The subject of this audit is the fulfillment of the instructions of the Committee of State Construction Supervision and State expertise of the Leningrad region
# 471802137391
Unscheduled inspection
Start date: 2018-11-22, end date: 2018-12-19, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of the execution of the issued instruction on the elimination of identified violations The subject of this audit is the fulfillment of the instructions of the Committee of State Construction Supervision and State expertise of the Leningrad region
# 781802065080
Unscheduled inspection
Start date: 2018-11-22, end date: —, duration: —
Authority: —
Purpose of inspection:
# 781802032933
Unscheduled inspection
Start date: 2018-10-04, end date: —, duration: —
Authority: —
Purpose of inspection:
# 471801898344
Unscheduled inspection
Start date: 2018-10-04, end date: 2018-10-31, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of the works specified in the notice of the person carrying out the construction on the completion dates of the works that are subject to verification The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the facility capital construction with metering devices for used energy resources compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 471801898334
Unscheduled inspection
Start date: 2018-10-04, end date: 2018-10-31, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of the execution of the issued instruction on the elimination of identified violations The subject of this audit is the fulfillment of the instructions of the Committee of State Construction Supervision and State expertise of the Leningrad region
# 471801425448
Unscheduled inspection
Start date: 2018-09-17, end date: 2018-09-21, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Cel proverka ispolneniya AO GSK trebovanii predpisaniya ot 08062018 VV1432018 ob ustranenii narushenii zakonodatelstva ob uchastii v dolevom stroitelstve mnogokvartirnyh domov i ili inyh obektov nedvizhimosti Zadachi presechenie dopuschennyh narushenii trebovanii zakonodatelstva RF v oblasti dolevogo stroitelstva mnogokvartirnyh domov i ili inyh obektov nedvizhimosti pri ih vyyavlenii Predmet soblyudenie obyazatelnyh trebovanii ustanovlennyh Federalnym zakonom ot 30122004 214FZ «Ob uchastii v dolevom stroitelstve mnogokvartirnyh domov i inyh obektov nedvizhimosti i o vnesenii izmenenii v nekotorye zakonodatelnye akty Rossiiskoi Federacii»
# 471801321664
Unscheduled inspection
Start date: 2018-09-10, end date: —, duration: —
Authority: —
Purpose of inspection:
# 471801112527
Unscheduled inspection
Start date: 2018-09-04, end date: 2018-10-01, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose of the audit is to verify the application of citizens, including individual entrepreneurs, legal entities, information from public authorities, officials of the state supervisory authority, local governments, and the media. The subject of this audit is compliance with mandatory requirements, including compliance with the performance of work and the construction materials used during construction, reconstruction of a capital construction facility, as well as the results of such work with technical requirements. regulations of the project documentation, including the requirements for energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation, the objectives of this audit are to prevent identify and suppress violations of legislation on urban development by the developer, the technical customer, and the person carrying out the construction, including technical regulations and design documentation
# 471800636428
Unscheduled inspection
Start date: 2018-08-16, end date: 2018-09-12, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose of checking the execution of the issued instruction on the elimination of identified violations The subject of this audit is the fulfillment of the instructions of the Committee of State Construction Supervision and State expertise of the Leningrad Region the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations, and the design objectives of this audit are to prevent identify and suppress by the developer, the technical customer, the person carrying out the construction of violations of the legislation on urban planning activities, including technical regulations and project documentation
# 471800636411
Unscheduled inspection
Start date: 2018-08-16, end date: 2018-09-12, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose of checking the execution of the issued instruction on the elimination of identified violations The subject of this audit is the fulfillment of the instructions of the Committee of State Construction Supervision and State expertise of the Leningrad Region the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations, and the design objectives of this audit are to prevent identify and suppress by the developer, the technical customer, the person carrying out the construction of violations of the legislation on urban planning activities, including technical regulations and project documentation
# 471800502287
Unscheduled inspection
Start date: 2018-06-21, end date: 2018-07-18, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose of checking the execution of the issued instruction on the elimination of identified violations The subject of this audit is the fulfillment of the instructions of the Committee of State Construction Supervision and State expertise of the Leningrad Region the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations, and the design objectives of this audit are to prevent identify and suppress by the developer, the technical customer, the person carrying out the construction of violations of the legislation on urban planning activities, including technical regulations and project documentation
# 781801950803
Unscheduled inspection
Start date: 2018-05-14, end date: 2018-06-08, duration: —
Authority: Gosudarstvennaya inspekciya truda v gorode SanktPeterburge
Purpose of inspection: Osuschestvleniya federalnogo gosudarstvennogo nadzora za soblyudeniem rabotodatelem trudovogo zakonodatelstva i inyh normativnyh pravovyh aktov soderzhaschih normy trudovogo prava v svyazi s informaciei o nalichii priznakov
# 471800403611
Unscheduled inspection
Start date: 2018-05-24, end date: 2018-06-21, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of elimination of violations of the mandatory requirements specified in the notice of the person carrying out the construction on elimination of the identified violations The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the facility capital construction metering devices for energy resources used to comply with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out the construction
# 471800197502
Unscheduled inspection
Start date: 2018-03-12, end date: 2018-04-06, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: verification of the execution of the issued instruction on the elimination of identified violations The subject of this audit is the fulfillment of the instructions of the Committee of State Construction Supervision and State expertise of the Leningrad Region The objectives of this audit are to prevent identify and suppress violations of the legislation on urban development by the developer, the technical customer, the person carrying out construction, including technical regulations and design objectives of this audit are to prevent identify and suppress violations committed by the developer the technical customer is a person engaged in construction of violations of the legislation on urban planning activities, including technical regulations and project documentation
# 471800206764
Unscheduled inspection
Start date: 2018-03-14, end date: 2018-04-10, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: verification of the execution of the issued instruction on the elimination of identified violations The subject of this audit is the fulfillment of the instructions of the Committee of State Construction Supervision and State expertise of the Leningrad Region The objectives of this audit are to prevent identify and suppress violations of the legislation on urban development by the developer, the technical customer, the person carrying out construction, including technical regulations and design objectives of this audit are to prevent identify and suppress violations committed by the developer the technical customer is a person engaged in construction of violations of the legislation on urban planning activities, including technical regulations and project documentation
# 781800060367
Unscheduled inspection
Start date: 2018-02-05, end date: 2018-03-05, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po gorodu SanktPeterburgu
Purpose of inspection: Nadzor za soblyudeniem obyazatelnyh trebovanii zakonodatelstva v oblasti zaschity prav potrebitelei
# 471800065705
Unscheduled inspection
Start date: 2018-02-08, end date: —, duration: —
Authority: —
Purpose of inspection:
# 471800000882
Unscheduled inspection
Start date: 2018-01-12, end date: 2018-02-08, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of completion of work on the implementation of construction reconstruction of the capital construction facility specified in the notice of the developer technical customer on completion of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for used energy resources compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out construction
# 47170701848131
Unscheduled inspection
Start date: 2017-08-14, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: