Found 4 inspections:

# 622100233671
Unscheduled inspection
Start date: 2021-06-01, end date: —, duration:
Authority:
Purpose of inspection:


# 622004476157
Unscheduled inspection
Start date: 2020-07-30, end date: 2020-07-30, duration: 1
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Ryazanskoi oblasti
Purpose of inspection: checking the completed construction of the object


# 622004417843
Unscheduled inspection
Start date: 2020-05-25, end date: 2020-05-25, duration:
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Ryazanskoi oblasti
Purpose of inspection: Organizational and legal order of construction


# 621800668313
Unscheduled inspection
Start date: 2018-07-11, end date: 2018-07-26, duration:
Authority: Glavnoe upravlenie MCHS Rossii po Ryazanskoi oblasti
Purpose of inspection: This inspection is carried out in order to fulfill the instructions of the Deputy Chairman of the Government of the Russian Federation AG Khloponin dated December 07, 2017, AHP98184. The objectives of this inspection are compliance by the local government with fire safety requirements and taking measures based on the results of the inspection.


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.