Found 31 inspection:

# 742101396778
Unscheduled inspection
Start date: 2021-12-01, end date: 2021-12-03, duration: 3
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1. Compliance of works on landscaping, compliance with fire-fighting and sanitary-epidemiological requirements, as well as measures to ensure access for low-mobility groups and construction materials used during construction, reconstruction of a capital construction facility, as well as the results of such work, with the requirements of the design documentation approved in accordance with Parts 15, 15.2 and 15.3 of Article 48 of this Code. documentation (subject to changes made to the project documentation in accordance with Parts 3.8 and 3.9 of Article 49 of this Code) and (or) an information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of this Code), including energy efficiency requirements (with the exception of capital construction facilities which are not covered by energy efficiency requirements) and the requirements for equipping a capital construction facility with metering devices for used energy resources. 2. Availability of a building permit. 3. Meeting the requirements of Parts 2.3 and 3.1 of art. 52 of the Urban Planning Code of the Russian Federation.


# 742101396741
Unscheduled inspection
Start date: 2021-12-01, end date: —, duration:
Authority:
Purpose of inspection:


# 742101365577
Unscheduled inspection
Start date: 2021-11-23, end date: 2021-11-29, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1. Compliance with the work performed on the roof (after completion of work), interior walls and partitions, facade, filling of window and door openings, internal engineering networks, interior finishing works (during work) and the construction materials used during the construction, reconstruction of the capital construction facility, as well as the results of such work, to the requirements of the project documentation approved in accordance with Parts 15, 15.2 and 15.3 of Article 48 of this Code (subject to changes made to the project documentation in accordance with parts 3.8 and 3.9 of Article 49 of this Code) and (or) an information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of this Code), including energy efficiency requirements (with the exception of capital construction facilities to which energy efficiency requirements do not apply) and requirements for equipping the capital construction facility with metering devices for used energy resources. 2. Availability of a building permit. 3. Meeting the requirements of Parts 2.3 and 3.1 of art. 52 of the Urban Planning Code of the Russian Federation.


# 742101365601
Unscheduled inspection
Start date: 2021-11-24, end date: —, duration:
Authority:
Purpose of inspection:


# 742101358113
Unscheduled inspection
Start date: 2021-11-19, end date: —, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection:


# 742101321292
Unscheduled inspection
Start date: 2021-11-16, end date: 2021-11-22, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1. Compliance of the work on the installation of outdoor lighting networks, rough floors of the first and second floors, staircase structures in axes 15-16 / D-E, internal partitions of the first floor, installation of windows on the first floor, brickwork of applications and building materials used during construction, reconstruction of the capital construction facility, as well as the results of such work with the requirements the project documentation approved in accordance with Parts 15, 15.2 and 15.3 of Article 48 of this Code (subject to changes made to the project documentation in accordance with parts 3.8 and 3.9 of Article 49 of this Code) and (or) the information model (if the formation and maintenance of the information model are mandatory in accordance with the requirements of this Energy efficiency requirements (with the exception of capital construction facilities, to which energy efficiency requirements do not apply) and the requirements for equipping a capital construction facility with metering devices for used energy resources. 2. Availability of a building permit. 3. Meeting the requirements of Parts 2.3 and 3.1 of art. 52 of the Urban Planning Code of the Russian Federation.


# 742101244773
Unscheduled inspection
Start date: 2021-10-25, end date: 2021-10-29, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1. Compliance with the performance of work on the installation of a railway frame (after completion of work), roofing (during work), installation of outdoor power supply networks, lighting (after completion of work) and the construction materials used during the construction, reconstruction of the capital construction facility, as well as the results of such work, to the requirements of the project documentation approved in accordance with Parts 15, 15.2 and 15.3 of Article 48 of this Code (subject to changes made to the project documentation in accordance with parts 3.8 and 3.9 of Article 49 of this Code) and (or) an information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of this Code), including energy efficiency requirements (with the exception of capital construction facilities to which energy efficiency requirements do not apply) and requirements for equipping the capital construction facility with metering devices for used energy resources. 2. Availability of a building permit. 3. Meeting the requirements of Parts 2.3 and 3.1 of art. 52 of the Urban Planning Code of the Russian Federation.


# 742101244146
Unscheduled inspection
Start date: 2021-10-25, end date: 2021-10-29, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1. Compliance of the work on the installation of a gas boiler house, roofing (during the work), installation of an outdoor heating network (before backfilling) and the construction materials used during the construction, reconstruction of a capital construction facility, as well as the results of such work with the requirements approved in accordance with parts 15, 15.2 and 15.3 of Article 48 of this Code project documentation (subject to the changes made to the project documentation in accordance with Parts 3.8 and 3.9 of Article 49 of this Code) and (or) an information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of this Code), including energy efficiency requirements (with the exception of capital construction facilities buildings that are not covered by energy efficiency requirements) and the requirements for equipping a capital construction facility with metering devices for used energy resources. 2. Availability of a building permit. 3. Compliance with the requirements of Parts 2.3 and 3.1 of art.52 of the Urban Planning Code of the Russian Federation.


# 742100729227
Unscheduled inspection
Start date: 2021-09-24, end date: —, duration:
Authority:
Purpose of inspection:


# 742100715313
Unscheduled inspection
Start date: 2021-09-22, end date: 2021-09-28, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1. Compliance of the work on the masonry of the exterior walls during the work, with the installation of the HVAC (after completion of the work) and the construction materials used during the construction, reconstruction of the capital construction facility, as well as the results of such work, to the requirements of the project documentation approved in accordance with Parts 15, 15.2 and 15.3 of Article 48 of this Code (subject to changes made to the project documentation in accordance with parts 3.8 and 3.9 of Article 49 of this Code) and (or) information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of this Code), including energy efficiency requirements (with the exception of capital construction facilities to which energy efficiency requirements do not apply) and requirements for equipping the capital construction facility with metering devices for energy resources used. 2. Availability of a building permit. 3. Meeting the requirements of Parts 2.3 and 3.1 of art. 52 of the Urban Planning Code of the Russian Federation.


# 742100459068
Unscheduled inspection
Start date: 2021-08-18, end date: 2021-08-24, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1. Compliance of the work performed on the masonry of the exterior walls (during the work), the construction of the w / w frame, the installation of the NVK (before backfilling), the installation of internal walls and partitions (during the work) and the construction materials used during the construction, reconstruction of the capital construction facility, as well as the results of such work with the requirements approved in in accordance with Parts 15, 15.2 and 15.3 of Article 48 of this Code, the project documentation (subject to changes made to the project documentation in accordance with parts 3.8 and 3.9 of Article 49 of this Code) and (or) the information model (if the formation and maintenance of the information model are mandatory in accordance with the requirements of this Code), including energy efficiency requirements (with the exception of capital construction facilities, to which energy efficiency requirements do not apply) and requirements for equipping a capital construction facility with metering devices for used energy resources. 2. Availability of a building permit. 3. Meeting the requirements of Parts 2.3 and 3.1 of art. 52 of the Urban Planning Code of the Russian Federation.


# 742100446989
Unscheduled inspection
Start date: 2021-08-16, end date: 2021-08-20, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1. Compliance with the work on the construction of the railway frame (in the process of work) and the construction materials used during the construction, reconstruction of the capital construction facility, as well as the results of such work, to the requirements of the project documentation approved in accordance with Parts 15, 15.2 and 15.3 of Article 48 of this Code (subject to changes made to the project documentation in accordance with parts 3.8 and 3.9 of Article 49 of this Code) and (or) an information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of this Code), including energy efficiency requirements (with the exception of capital construction facilities to which energy efficiency requirements do not apply) and requirements for equipping the capital construction facility with metering devices for used energy resources. 2. Availability of a building permit. 3. Meeting the requirements of Parts 2.3 and 3.1 of art. 52 of the Urban Planning Code of the Russian Federation.


# 742100276921
Unscheduled inspection
Start date: 2021-06-16, end date: 2021-06-22, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1. Compliance of the work on the construction of the railway frame of residential building No. 1, 2 (in the process of work) and the construction materials used during the construction, reconstruction of the capital construction facility, as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15, 15.2 and 15.3 of Article 48 of this Code (taking into account changes made to the project documentation in accordance with Parts 3.8 and 3.9 of Article 49 of this Code) and (or) the information model (if the formation and maintenance of the information model are mandatory in accordance with the requirements of this Code), including energy efficiency requirements (with the exception of capital construction facilities for which the requirements energy efficiency does not apply) and the requirements for equipping a capital construction facility with metering devices for used energy resources. 2. Availability of a building permit. 3. Meeting the requirements of Parts 2.3 and 3.1 of art. 52 of the Urban Planning Code of the Russian Federation.


# 742100260862
Unscheduled inspection
Start date: 2021-06-07, end date: —, duration:
Authority:
Purpose of inspection:


# 742100185886
Unscheduled inspection
Start date: 2021-05-11, end date: 2021-05-14, duration: 4
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1. Verification of the execution of the order dated 03/19/2021, due on 04/19/2021. 2. Availability of a building permit. 3. Meeting the requirements of Parts 2.3 and 3.1 of art. 52 of the Urban Planning Code of the Russian Federation.


# 742100185890
Unscheduled inspection
Start date: 2021-05-11, end date: 2021-05-14, duration: 4
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1. Verification of the execution of the regulation dated 03/22/2021, due on 04/22/2021. 2. Availability of a building permit. 3. Meeting the requirements of Parts 2.3 and 3.1 of art. 52 of the Urban Planning Code of the Russian Federation.


# 742100151642
Unscheduled inspection
Start date: 2021-04-19, end date: 2021-04-23, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1. Compliance of the foundation construction (after completion of the work) and the construction materials used during the construction, reconstruction of the capital construction facility, as well as the results of such work, with the requirements of the project documentation approved in accordance with Parts 15, 15.2 and 15.3 of Article 48 of this Code (subject to changes made to the project documentation in accordance with 3.8 and 3.9 of Article 49 of this Code) and (or) an information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of this Code), including energy efficiency requirements (with the exception of capital construction facilities to which energy efficiency requirements do not apply) and facility equipment requirements capital construction with metering devices for used energy resources. 2. Availability of a building permit. 3. Meeting the requirements of Parts 2.3 and 3.1 of art. 52 of the Urban Planning Code of the Russian Federation.


# 742100145643
Unscheduled inspection
Start date: 2021-04-15, end date: 2021-04-21, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1. Compliance with the work on the foundation (after completion of the work) and the construction materials used during the construction, reconstruction of the capital construction facility, as well as the results of such work, to the requirements of the project documentation approved in accordance with Parts 15, 15.2 and 15.3 of Article 48 of this Code (subject to changes made to the project documentation in accordance with parts 3.8 and 3.9 of Article 49 of this Code) and (or) an information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of this Code), including energy efficiency requirements (with the exception of capital construction facilities to which energy efficiency requirements do not apply) and requirements for equipping the capital construction facility with metering devices for used energy resources. 2. Availability of a building permit. 3. Meeting the requirements of Parts 2.3 and 3.1 of art. 52 of the Urban Planning Code of the Russian Federation.


# 742100060152
Unscheduled inspection
Start date: 2021-03-15, end date: 2021-03-19, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1. Compliance of the work on the organization of the construction site according to the PIC, the installation of foundations (in the process of work) and the construction materials used during the construction, reconstruction of the capital construction facility, as well as the results of such work, to the requirements of the project documentation approved in accordance with Parts 15, 15.2 and 15.3 of Article 48 of this Code (subject to changes made to the project documentation in accordance with parts 3.8 and 3.9 of Article 49 of this Code) and (or) an information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of this Code), including energy efficiency requirements (with the exception of capital construction facilities to which energy efficiency requirements do not apply) and requirements for equipping the capital construction facility with metering devices for used energy resources. 2. Availability of a building permit. 3. Meeting the requirements of Parts 2.3 and 3.1 of art. 52 of the Urban Planning Code of the Russian Federation.


# 742100063140
Unscheduled inspection
Start date: 2021-03-16, end date: 2021-03-22, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1. Compliance of the work on the organization of the construction site in accordance with the PIC, the installation of foundations (in the course of work) and the construction materials used during the construction, reconstruction of the capital construction facility, as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15, 15.2 and 15.3 of Article 48 of this Code (subject to changes made to the project documentation in accordance with parts 3.8 and 3.9 of Article 49 of this Code) and (or) the information model (if the formation and maintenance of the information model are mandatory in accordance with the requirements of this Code), including energy efficiency requirements (with the exception of capital construction facilities for which energy efficiency requirements are not they are distributed) and the requirements for equipping the capital construction facility with metering devices for used energy resources. 2. Availability of a building permit. 3. Meeting the requirements of Parts 2.3 and 3.1 of art. 52 of the Urban Planning Code of the Russian Federation.


# 742004410851
Unscheduled inspection
Start date: 2020-05-20, end date: 2020-05-26, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 1 Compliance of the work on the installation of technological equipment, compliance with fire and sanitary epidemiological measures, measures to ensure access for low-mobility groups of the population after the actual completion of work and the construction materials used during the construction of the reconstruction of the capital construction facility, as well as the results of such work, with the requirements of the project documentation approved in accordance with Parts 15 152 and 153 of Article 48 of this Code, subject to changes included in the project documentation in accordance with parts 38 and 39 of Article 49 of this Code and or an information model if the formation and maintenance of an information model are mandatory in accordance with the requirements of this Code, including energy efficiency requirements, with the exception of capital construction facilities to which energy efficiency requirements do not apply and the requirements for equipping the capital construction facility with devices accounting for the energy resources used2 Availability of a construction permit3 Compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation


# 742004387650
Unscheduled inspection
Start date: 2020-04-06, end date: —, duration:
Authority:
Purpose of inspection:


# 742004399455
Unscheduled inspection
Start date: 2020-04-23, end date: 2020-04-29, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the work on the installation of the fire alarm system of the building materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of this Code, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of this Code and or information model in the event that the formation and maintenance of an information model are mandatory in accordance with the requirements of this Code, including energy efficiency requirements, with the exception of capital construction facilities to which energy efficiency requirements do not apply and the requirements for equipping the capital construction facility with metering devices for used energy resources 2 The availability of a construction permit 3 Compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code Russian Federation


# 742004355645
Unscheduled inspection
Start date: 2020-03-18, end date: 2020-03-24, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 1 Compliance of the installation of the heating and power supply system and the construction materials used during the construction reconstruction of the capital construction facility, as well as the results of such work, with the requirements of the project documentation approved in accordance with Parts 15 152 and 153 of Article 48 of this Code, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of this Code and or an information model, if the formation and maintenance of an information model are mandatory in accordance with the requirements of this Code, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply and the requirements for equipping the capital construction facility with metering devices for energy resources used2 The availability of a construction permit3 Meeting the requirements of hh 23 and 31 st52 The Urban Planning Code of the Russian Federation


# 742004296627
Unscheduled inspection
Start date: 2020-02-26, end date: 2020-03-03, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1The compliance of the installation of internal engineering systems for ventilation, water supply, drainage and construction materials used during the construction and reconstruction of a capital construction facility, as well as the results of such work, with the requirements of the design documentation approved in accordance with Parts 15 152 and 153 of Article 48 of this Code, taking into account the changes made to the design documentation in accordance with parts 38 and 39 of Article 49 of this Code. If the formation and maintenance of an information model are mandatory in accordance with the requirements of this Code, including energy efficiency requirements, with the exception of capital construction facilities to which energy efficiency requirements do not apply and the requirements for equipping the capital construction facility with metering devices for energy resources used2 The availability of a construction permit3 Meeting the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation


# 741903948041
Unscheduled inspection
Start date: 2019-11-14, end date: 2019-11-20, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Verification of the execution of the regulation from 11102019 with a deadline until 01/12/2019 2 Availability of a construction permit 3 Compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation


# 741903733047
Unscheduled inspection
Start date: 2019-10-07, end date: —, duration:
Authority:
Purpose of inspection:


# 661903252198
Unscheduled inspection
Start date: 2019-09-09, end date: 2019-10-04, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: The purpose is to monitor the implementation of the previously issued instruction on the elimination of the identified violation of mandatory requirements 291707307P2 dated May 31, 2019application of the regional state construction supervision on the implementation of the previously issued instruction on the elimination of the identified violation of mandatory requirements 291707307P2 dated May 31, 2019


# 741903132211
Unscheduled inspection
Start date: 2019-09-09, end date: —, duration:
Authority:
Purpose of inspection:


# 661902928289
Unscheduled inspection
Start date: 2019-08-08, end date: —, duration:
Authority:
Purpose of inspection:


# 661902641734
Unscheduled inspection
Start date: 2019-05-06, end date: —, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection:


Information about inspections