# 00170802717299
Unscheduled inspection
Start date: 2017-09-25, end date: 2017-09-29, duration: —
Authority: BaltiiskoArkticheskoe mezhregionalnoe upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya
Purpose of inspection: verification of the fulfillment of the previously issued instruction VD56131 from 10032016
# 00170802717296
Unscheduled inspection
Start date: 2017-09-25, end date: —, duration: —
Authority: BaltiiskoArkticheskoe mezhregionalnoe upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya
Purpose of inspection:
# 00170802717294
Unscheduled inspection
Start date: 2017-09-25, end date: 2017-09-29, duration: —
Authority: BaltiiskoArkticheskoe mezhregionalnoe upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya
Purpose of inspection: verification of the fulfillment of the previously issued instruction VD56135 from 10032016
# 00170802717293
Unscheduled inspection
Start date: 2017-09-25, end date: 2017-09-29, duration: —
Authority: BaltiiskoArkticheskoe mezhregionalnoe upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya
Purpose of inspection: verification of the fulfillment of the previously issued instruction VD56133 from 10032016
# 782100272079
Unscheduled inspection
Start date: 2021-06-09, end date: —, duration: 15
Authority: Glavnoe upravlenie MCHS Rossii po g. Sankt-Peterburgu
Purpose of inspection: Purpose: to monitor the elimination of violations of fire safety requirements specified in the regulation on the elimination of identified violations of fire safety requirements dated 06/05/2020 № 42-1-252/1/1 (the deadline for eliminating violations is 06/01/2021)
The objectives of this inspection are:
– identification, suppression and prevention of possible violations of fire safety requirements;
– implementation of systematic monitoring of compliance with fire safety requirements.
The subject of this audit is:
– compliance with fire safety requirements at the protection facility used (operated) by the organization in the course of its activities (compliance with the instructions of the federal state fire supervision authority).
# 782005254299
Unscheduled inspection
Start date: 2020-12-01, end date: —, duration: —
Authority: —
Purpose of inspection:
# 782004413637
Unscheduled inspection
Start date: 2020-05-25, end date: 2020-06-15, duration: 15
Authority: Glavnoe upravlenie MCHS Rossii po g SanktPeterburgu
Purpose of inspection: control of elimination of violations of fire safety requirements specified in the regulation on elimination of identified violations of fire safety requirements dated 22032019 22416211 elimination period 01042020the objectives of this audit are to identify, suppress and prevent possible violations of fire safety requirements carry out systematic monitoring of compliance with fire safety requirements 7 The subject of this audit is compliance with fire safety requirements at the protection facility used operated by the organization in the process of implementation their activities
# 782004320919
Unscheduled inspection
Start date: 2020-02-26, end date: 2020-03-25, duration: —
Authority: Gosudarstvennaya zhilischnaya inspekciya SanktPeterburga
Purpose of inspection: verification of the measures taken by the Administration aimed at ensuring the safety of funds for the formation of a capital repair fund on a special account of the HOA "Sofiyskaya house 48 building 3" spent from 2017 to the present
# 781902541235
Unscheduled inspection
Start date: 2019-03-11, end date: 2019-03-29, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po g SanktPeterburgu
Purpose of inspection: control over the elimination of violations of fire safety requirements specified in the regulation on the elimination of identified violations of fire safety requirements dated 01042018 22418711, the deadline for which expired on 01032019, the objectives of this audit are to identify, suppress and prevent possible violations of fire safety requirements and carry out systematic monitoring of compliance with fire safety requirements 7 The subject of this audit is compliance with fire safety requirements at the protection facility used and operated by the organization in the course of carrying out its activities
# 78180803257307
Unscheduled inspection
Start date: 2018-10-16, end date: 2018-10-16, duration: —
Authority: Gosudarstvennaya zhilischnaya inspekciya SanktPeterburga
Purpose of inspection: Strengthening control over the activities of management organizations
# 78180803173763
Unscheduled inspection
Start date: 2018-06-29, end date: 2018-06-29, duration: —
Authority: Gosudarstvennaya zhilischnaya inspekciya SanktPeterburga
Purpose of inspection: fulfilling the instructions of the Vice-governor of St. Petersburg N. Bondarenko
# 78180803169527
Unscheduled inspection
Start date: 2018-06-22, end date: 2018-06-22, duration: —
Authority: Gosudarstvennaya zhilischnaya inspekciya SanktPeterburga
Purpose of inspection: fulfilling the instructions of the Vice-governor of St. Petersburg N. Bondarenko
# 78180803127019
Unscheduled inspection
Start date: 2018-04-12, end date: 2018-04-12, duration: —
Authority: Gosudarstvennaya zhilischnaya inspekciya SanktPeterburga
Purpose of inspection: fulfilling the instructions of the Vice-governor of St. Petersburg N. Bondarenko
# 781800278091
Unscheduled inspection
Start date: 2018-04-16, end date: 2018-04-30, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po g SanktPeterburgu
Purpose of inspection: control over the elimination of violations of fire safety requirements specified in the regulation on the elimination of identified violations of fire safety requirements dated 29032017 22414211, the deadline for which expired on 02042018. The objectives of this audit are to identify, suppress and prevent possible violations of fire safety requirements and carry out systematic monitoring of compliance with fire safety requirements 7 The subject of this audit is compliance with fire safety requirements at the protection facility used and operated by the organization in the course of carrying out its activities
# 781800278040
Unscheduled inspection
Start date: 2018-04-16, end date: 2018-04-30, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po g SanktPeterburgu
Purpose of inspection: control over the elimination of violations of fire safety requirements specified in the regulation on the elimination of identified violations of fire safety requirements dated 29032017 22414311, the deadline for which expired on 02042018. The objectives of this audit are to identify, suppress and prevent possible violations of fire safety requirements and carry out systematic monitoring of compliance with fire safety requirements 7 The subject of this audit is compliance with fire safety requirements at the protection facility used and operated by the organization in the course of carrying out its activities
# 78180803134912
Unscheduled inspection
Start date: 2018-04-26, end date: 2018-04-26, duration: —
Authority: Gosudarstvennaya zhilischnaya inspekciya SanktPeterburga
Purpose of inspection: fulfilling the instructions of the Vice-governor of St. Petersburg N. Bondarenko
# 78180803126308
Unscheduled inspection
Start date: 2018-04-06, end date: 2018-04-06, duration: —
Authority: Gosudarstvennaya zhilischnaya inspekciya SanktPeterburga
Purpose of inspection: Strengthening control over the activities of management organizations
# 78180803097030
Unscheduled inspection
Start date: 2018-02-18, end date: —, duration: —
Authority: —
Purpose of inspection:
# 78170802995825
Unscheduled inspection
Start date: 2017-12-03, end date: 2017-12-03, duration: —
Authority: Gosudarstvennaya zhilischnaya inspekciya SanktPeterburga
Purpose of inspection: fulfilling the instructions of the Vice-governor of St. Petersburg N. Bondarenko
# 78170802768167
Unscheduled inspection
Start date: 2017-10-17, end date: —, duration: —
Authority: —
Purpose of inspection:
# 78170802742861
Unscheduled inspection
Start date: 2017-10-11, end date: —, duration: —
Authority: —
Purpose of inspection:
# 78170802713865
Unscheduled inspection
Start date: 2017-10-11, end date: 2017-11-08, duration: —
Authority: Gosudarstvennaya zhilischnaya inspekciya SanktPeterburga
Purpose of inspection: Control over the fulfillment of the inspection order
# 00170802717299
Unscheduled inspection
Start date: 2017-09-25, end date: 2017-09-29, duration: —
Authority: BaltiiskoArkticheskoe mezhregionalnoe upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya
Purpose of inspection: verification of the fulfillment of the previously issued instruction VD56131 from 10032016
# 00170802717296
Unscheduled inspection
Start date: 2017-09-25, end date: 2017-09-29, duration: —
Authority: BaltiiskoArkticheskoe mezhregionalnoe upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya
Purpose of inspection: verification of the fulfillment of the previously issued instruction VD56132 from 10032016
# 00170802717294
Unscheduled inspection
Start date: 2017-09-25, end date: 2017-09-29, duration: —
Authority: BaltiiskoArkticheskoe mezhregionalnoe upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya
Purpose of inspection: verification of the fulfillment of the previously issued instruction VD56135 from 10032016
# 00170802717293
Unscheduled inspection
Start date: 2017-09-25, end date: 2017-09-29, duration: —
Authority: BaltiiskoArkticheskoe mezhregionalnoe upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya
Purpose of inspection: verification of the fulfillment of the previously issued instruction VD56133 from 10032016
# 78170701589032
Unscheduled inspection
Start date: 2017-04-13, end date: 2017-05-15, duration: —
Authority: Gosudarstvennaya zhilischnaya inspekciya SanktPeterburga
Purpose of inspection: fulfilling the instructions of the Vice-governor of St. Petersburg N. Bondarenko
# 78170701464545
Unscheduled inspection
Start date: 2017-03-20, end date: —, duration: —
Authority: —
Purpose of inspection:
# 78170701464494
Unscheduled inspection
Start date: 2017-03-20, end date: —, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po g SanktPeterburgu
Purpose of inspection:
# 78160700814039
Unscheduled inspection
Start date: 2016-09-22, end date: —, duration: —
Authority: Territorialnyi organ Federalnoi sluzhby po nadzoru v sfere zdravoohraneniya po g SanktPeterburgu i Leningradskoi oblasti
Purpose of inspection: verification of Sokolov LL's appeal
# 78160601515611
Unscheduled inspection
Start date: 2016-03-15, end date: —, duration: —
Authority: —
Purpose of inspection:
# 78160601515599
Unscheduled inspection
Start date: 2016-03-15, end date: —, duration: —
Authority: —
Purpose of inspection:
# 78150600009039
Unscheduled inspection
Start date: 2015-07-14, end date: —, duration: —
Authority: —
Purpose of inspection: