# 162004478283
Unscheduled inspection
Start date: 2020-08-10, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161904113182
Unscheduled inspection
Start date: 2019-12-18, end date: 2019-12-27, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the eliminated violations with the requirements of technical regulations, project documentation, other regulations, norms and rules for determining the fact of execution of the order, as well as for the purpose of drawing up an act on the elimination of violations of the order based on the notice received by the Inspectorate from 10122019 12740 on the elimination of violations during the construction of the reconstruction of the capital construction facility, which was ordered to be eliminated within the time limit set by regulation dated 31102019 1712026301 to 10122019 and the expiration date of the regulation dated 31102019 1712026301, the deadline for which expired 10122019 The objectives of this audit are to prevent as well as identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, violations of compliance performed during the construction of a capital construction facility with the requirements of technical regulations, other regulatory legal acts and The subject of this audit is the fulfillment of the requirements of the state control bodies, supervision of municipal control bodies.
# 161903877662
Unscheduled inspection
Start date: 2019-10-25, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 161903798493
Unscheduled inspection
Start date: 2019-10-15, end date: 2019-10-23, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program dated 01042019 case 171120170016the objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation7 carried out by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation7the subject of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by municipal legal acts
# 161902862443
Unscheduled inspection
Start date: 2019-07-11, end date: 2019-07-12, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the eliminated violations with the requirements of technical regulations, project documentation, other regulations, norms and rules for determining the fact of execution of the order, as well as for the purpose of drawing up an act on the elimination of violations of the order based on the notice received by the Inspectorate from 04072019 5630 on the elimination of violations during the construction of the reconstruction of the capital construction facility, which was ordered to be eliminated within the time limit set by the order dated 24062019 1712012201 to 01072019 and the expiration of the order dated 24062019 1712012201, the deadline for which expired on 01072019the objectives of this audit are to prevent, identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other regulatory legal acts and design documentation. documentation7 The subject of this audit is to select the necessary fulfillment of the instructions of the state control bodies supervision of municipal control bodies
# 161902782356
Unscheduled inspection
Start date: 2019-06-17, end date: 2019-06-24, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program dated 01042019 case 171120170016the objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation7 carried out by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation7the subject of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by municipal legal acts
# 161902655624
Unscheduled inspection
Start date: 2019-04-18, end date: 2019-04-26, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program dated 01042019 case 171120170016 The objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation performed during the construction of a capital construction facility by the developer, customer, or person carrying out construction on the basis of a contract with the developer or customer. 7 The subject of this inspection is to select the necessary compliance with mandatory requirements and or the requirements established by municipal legal acts
# 16170701838402
Unscheduled inspection
Start date: 2017-08-01, end date: 2017-08-09, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the fact of fulfillment of the order dated 26052017 1719010701, the deadline for which expired on 31072017, and to draw up an act based on the results of the inspection. The objectives of this inspection are to prevent, as well as identify and prevent violations of compliance by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations and other regulatory legal acts performed during the construction of a capital construction facility. acts and project documentation7 The subject of this audit is to select the necessary fulfillment of the instructions of the state control bodies, supervision bodies of municipal control
# 16170701649726
Unscheduled inspection
Start date: 2017-05-26, end date: 2017-06-01, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to establish compliance with the requirements of part 5 of Article 52 of the Urban Planning Code of the Russian Federation on the basis of the notice received by the Inspectorate on the start of construction of the reconstruction of the capital construction facility from 19052017 3841the objectives of this inspection are to prevent as well as identify and suppress violations of conformity committed by the developer customer the person carrying out construction on the basis of a contract with the developer or the customer performed during the construction of the facility capital construction works to meet the requirements of technical regulations, other regulatory legal acts and project documentation6 The subject of this audit is compliance with mandatory requirements