# 77180803169629
Unscheduled inspection
Start date: 2018-06-26, end date: 2018-07-06, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803119561
Unscheduled inspection
Start date: 2018-04-09, end date: 2018-05-08, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803102361
Unscheduled inspection
Start date: 2018-03-14, end date: 2018-03-31, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803081877
Unscheduled inspection
Start date: 2018-01-17, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803064426
Unscheduled inspection
Start date: 2018-01-17, end date: 2018-01-19, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803079517
Unscheduled inspection
Start date: 2018-01-22, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803066190
Unscheduled inspection
Start date: 2018-01-22, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170802897185
Unscheduled inspection
Start date: 2017-11-27, end date: 2017-12-22, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77170802792459
Unscheduled inspection
Start date: 2017-10-30, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170801954853
Unscheduled inspection
Start date: 2017-08-30, end date: 2017-09-04, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170701793133
Unscheduled inspection
Start date: 2017-07-10, end date: —, duration: —
Authority: —
Purpose of inspection: