# 001902822086
Unscheduled inspection
Start date: 2019-07-25, end date: 2019-07-26, duration: —
Authority: Priokskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: implementation of the previously issued regulation 22510EPB dated 20032019
# 001902789245
Unscheduled inspection
Start date: 2019-03-14, end date: 2019-03-20, duration: —
Authority: Priokskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: prevention detection and suppression of violations of mandatory requirements in the field of energy security
# 772100852965
Unscheduled inspection
Start date: 2021-09-21, end date: 2021-09-27, duration: 5
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The purpose of the audit: carrying out control measures in connection with the verification of compliance with the instruction; The tasks of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: verification of the elimination of violations specified in the instruction issued by Mosgosstroynadzor
# 772100300444
Unscheduled inspection
Start date: 2021-07-01, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772100151662
Unscheduled inspection
Start date: 2021-04-13, end date: 2021-04-30, duration: 14
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the audit program; The tasks of the audit: prevention, identification and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements design documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of design documentation identified during construction control and state construction supervision
# 772105323644
Unscheduled inspection
Start date: 2021-02-09, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 001902822086
Unscheduled inspection
Start date: 2019-07-25, end date: 2019-07-26, duration: —
Authority: Priokskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: implementation of the previously issued regulation 22510EPB dated 20032019
# 001902789245
Unscheduled inspection
Start date: 2019-03-14, end date: 2019-03-20, duration: —
Authority: Priokskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: prevention detection and suppression of violations of mandatory requirements in the field of energy security