# 342101390478
Unscheduled inspection
Start date: 2021-12-01, end date: —, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: a) this inspection is carried out in accordance with the inspection program received by a representative of the developer, LLC "Spetsstroyresheniya", in order to assess the compliance of activities carried out at the facility with the requirements of urban planning legislation of the Russian Federation, fire safety requirements and the requirements of project documentation;
b) the purpose of this audit is to prevent, identify and suppress violations of the legislation of the Russian Federation and project documentation.
7. The subject of this audit is compliance with mandatory requirements regarding:
1) compliance of the work performed and the construction materials and products used during the construction, reconstruction of the capital construction facility, as well as the results of such work, with the requirements of the project documentation approved in accordance with parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation (hereinafter referred to as the GsK RF) (including changes made to working documentation and which, in accordance with Part 1.3 of Article 52 of the GsK RF, are part of such project documentation) and (or) an information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of the GsK RF);
2) building permit requirements;
3) the requirements established by Parts 2 and 3.1 of Article 52 of the Civil Code of the Russian Federation;
4) the requirements established by part 4 of Article 52 of the Civil Code of the Russian Federation to ensure the conservation of the capital construction facility;
5) requirements to the procedure for the implementation of construction control established by the GSK of the Russian Federation and other regulatory legal acts.
# 342101299551
Unscheduled inspection
Start date: 2021-11-11, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection:
# 342100520242
Unscheduled inspection
Start date: 2021-09-28, end date: —, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: a) this inspection is carried out in accordance with the inspection program received by a representative of the developer, LLC "Spetsstroyresheniya", in order to assess the compliance of activities carried out at the facility with the requirements of urban planning legislation of the Russian Federation, fire safety requirements and the requirements of project documentation;
b) the purpose of this audit is to prevent, identify and suppress violations of the legislation of the Russian Federation and project documentation.
The subject of this audit is compliance with mandatory requirements regarding:
1) compliance of the work performed and the construction materials and products used during the construction, reconstruction of the capital construction facility, as well as the results of such work, with the requirements of the project documentation approved in accordance with parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation (hereinafter referred to as the GsK RF) (including changes made to working documentation and which, in accordance with Part 1.3 of Article 52 of the GsK RF, are part of such project documentation) and (or) an information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of the GsK RF);
2) building permit requirements;
3) the requirements established by Parts 2 and 3.1 of Article 52 of the Civil Code of the Russian Federation;
4) the requirements established by part 4 of Article 52 of the Civil Code of the Russian Federation to ensure the conservation of the capital construction facility;
5) requirements to the procedure for the implementation of construction control established by the GSK of the Russian Federation and other regulatory legal acts.
# 342100403139
Unscheduled inspection
Start date: 2021-08-03, end date: —, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: a) this inspection is carried out in accordance with the inspection program received by a representative of the developer, LLC "Spetsstroyresheniya", in order to assess the compliance of activities carried out at the facility with the requirements of the urban planning legislation of the Russian Federation and project documentation;
b) the purpose of this audit is to prevent, identify and suppress violations of the legislation of the Russian Federation and project documentation.
The subject of this review is compliance with:
1) compliance of the work performed and the construction materials and products used during the construction, reconstruction of the capital construction facility, as well as the results of such work, with the requirements of the project documentation approved in accordance with parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation (hereinafter referred to as the GsK RF) (including changes made to working documentation and which, in accordance with Part 1.3 of Article 52 of the GsK RF, are part of such project documentation) and (or) an information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of the GsK RF);
2) building permit requirements;
3) the requirements established by parts 2 and 3.1 of Article 52 of the GsK of the Russian Federation;
4) the requirements established by part 4 of Article 52 of the Civil Code of the Russian Federation to ensure the conservation of the capital construction facility;
5) requirements to the procedure for the implementation of construction control established by the GSK of the Russian Federation and other regulatory legal acts.
# 342100270684
Unscheduled inspection
Start date: 2021-06-23, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection:
# 342100225764
Unscheduled inspection
Start date: 2021-05-18, end date: —, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: This inspection is carried out in accordance with the inspection program received by a representative of the developer, LLC "Spetsstroyresheniya", in order to assess the compliance of activities carried out at the facility with the requirements of urban planning legislation of the Russian Federation and fire safety requirements.;
b) the purpose of this audit is to prevent, identify and suppress violations of the legislation of the Russian Federation and project documentation.
The subject of this audit is compliance with the mandatory requirements regarding:
a) compliance of the work performed and the construction materials used during the construction, reconstruction of the capital construction facility, as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation (hereinafter referred to as the Code) (as amended included in the project documentation in accordance with Parts 3.8 and 3.9 of Article 49 of the Code) and (or) an information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of the Code), including energy efficiency requirements (with the exception of capital construction projects for which energy efficiency requirements are not met are distributed) and the requirements for equipping the capital construction facility with metering devices for used energy resources;
b) the availability of a building permit;
c) compliance with the requirements set out in Parts 2.3 and 3.1 of art.52 of the Code.
# 342100040538
Unscheduled inspection
Start date: 2021-03-04, end date: 2021-03-11, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: This inspection is carried out in accordance with the inspection program received by the customer's representative, LLC "Spetsstroyresheniya", in order to assess the compliance of activities carried out at the facility with the requirements of urban planning legislation of the Russian Federation, fire safety requirements and requirements of project documentation.
The purpose of this audit is to prevent, identify and suppress violations of the legislation of the Russian Federation and the requirements of the project documentation.
The subject of this audit is compliance with the mandatory requirements regarding:
a) compliance of the work performed and the building materials used during the construction, reconstruction of the capital construction facility, as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation (hereinafter referred to as the Code) (as amended included in the project documentation in accordance with Parts 3.8 and 3.9 of Article 49 of the Code) and (or) an information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of the Code), including energy efficiency requirements (with the exception of capital construction projects for which energy efficiency requirements are not met are distributed) and the requirements for equipping the capital construction facility with metering devices for used energy resources;
b) availability of a building permit;
c) compliance with the requirements established by parts 2.3 and 3.1 of Article 52 of the Code.