# 052004216290
Unscheduled inspection
Start date: 2020-01-18, end date: 2020-02-08, duration: —
Authority: Ministerstvo stroitelstva i zhilischnokommunalnogo hozyaistva Respubliki Dagestan
Purpose of inspection: prevention detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance of works performed during the construction and reconstruction of capital construction facilities with the requirements of technical regulations and other regulatory legal acts of project documentation and compliance with the requirements of Article 54 of the Urban Planning Code of the Russian Federation in accordance with the program of inspections of the facility for 2020
# 612101355458
Unscheduled inspection
Start date: 2021-11-01, end date: —, duration: 4
Authority: Regionalnaya sluzhba gosudarstvennogo stroitelnogo nadzora Rostovskoi oblasti
Purpose of inspection: To establish that the present inspection is carried out in order to perform the following works :Inspection program: Inspection of a capital construction facility completed (subject to the actual completion of all work provided for in the project documentation and notification of completion of the facility)
the objectives of this inspection are: prevention, identification and suppression of violations committed by the developer, the customer, as well as the person carrying out construction on the basis of a contract with the developer or the customer (hereinafter referred to as the contractor), violations of legislation on urban planning, including project documentation
The subject of this audit is verification of: compliance with mandatory requirements and (or) requirements established by municipal legal acts
# 612100887862
Unscheduled inspection
Start date: 2021-10-18, end date: —, duration: 10
Authority: Regionalnaya sluzhba gosudarstvennogo stroitelnogo nadzora Rostovskoi oblasti
Purpose of inspection: To establish that this inspection is carried out in order to perform the following work: Inspection program: Installation and commissioning of automatic fire protection systems. Installation of outdoor networks. The arrangement of internal networks and engineering support systems. Installation of elevators. Installation of equipment. Landscaping and landscaping of the territory. Boiler room installation. Landscaping.
The objectives of this audit are: prevention, detection and suppression of violations of the legislation on urban development, including project documentation, committed by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer (hereinafter referred to as the contractor).
The subject of this audit is verification of: compliance with mandatory requirements and (or) requirements established by municipal legal acts
# 612100289686
Unscheduled inspection
Start date: 2021-07-01, end date: —, duration: —
Authority: —
Purpose of inspection:
# 612005227575
Unscheduled inspection
Start date: 2020-11-26, end date: 2020-12-18, duration: 17
Authority: Regionalnaya sluzhba gosudarstvennogo stroitelnogo nadzora Rostovskoi oblasti
Purpose of inspection: The inspection is carried out in order to fulfill the p6 inspection program The installation of monolithic structures of the technical floor of an apartment building The installation of a fire tank The waterproofing device The laying of exterior and interior walls the installation of partitions The installation of window and door blocks The installation of floors The installation of floors the installation of soil reinforcement The objectives of this inspection are to prevent identify and suppress violations committed by the developer the customer as well as by the person carrying out construction based on a contract with the developer or by the customer hereinafter referred to as the contractor for violations of legislation on urban planning activities, including technical regulations and project documentation, the subject of this audit is to verify compliance with mandatory requirements and or requirements established by municipal legal acts
# 612004474119
Unscheduled inspection
Start date: 2020-07-27, end date: 2020-07-31, duration: 5
Authority: Regionalnaya sluzhba gosudarstvennogo stroitelnogo nadzora Rostovskoi oblasti
Purpose of inspection: The inspection is carried out in order to verify the execution of Regulation 0100223884 from 22052020 to 03072020 issued by BLAGOSTROY CONSTRUCTION COMPANY LLC TIN 2308237133 The objectives of this inspection are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, hereinafter referred to as the contractor. The subject of this inspection The purpose of the audit is to verify compliance with the regulations of state control bodies and municipal control bodies
# 612004405023
Unscheduled inspection
Start date: 2020-04-24, end date: —, duration: —
Authority: —
Purpose of inspection:
# 612004235498
Unscheduled inspection
Start date: 2020-01-27, end date: 2020-02-04, duration: 7
Authority: Regionalnaya sluzhba gosudarstvennogo stroitelnogo nadzora Rostovskoi oblasti
Purpose of inspection: The inspection is carried out in order to verify the execution of Regulation 0100223883 from 15112019 to 27122019 issued by BLAGOSTROY CONSTRUCTION COMPANY LLC TIN 2308237133 The objectives of this inspection are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, hereinafter referred to as the contractor. The subject of this inspection The purpose of the audit is to verify compliance with the regulations of state control bodies and municipal control bodies
# 052004216290
Unscheduled inspection
Start date: 2020-01-18, end date: 2020-02-08, duration: —
Authority: Ministerstvo stroitelstva i zhilischnokommunalnogo hozyaistva Respubliki Dagestan
Purpose of inspection: prevention detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance of works performed during the construction and reconstruction of capital construction facilities with the requirements of technical regulations and other regulatory legal acts of project documentation and compliance with the requirements of Article 54 of the Urban Planning Code of the Russian Federation in accordance with the program of inspections of the facility for 2020
# 611903895796
Unscheduled inspection
Start date: 2019-10-28, end date: 2019-11-15, duration: —
Authority: Regionalnaya sluzhba gosudarstvennogo stroitelnogo nadzora Rostovskoi oblasti
Purpose of inspection: n 3 Inspection programs Soil reinforcement Installation of a monolithic reinforced concrete building frame up to the 5th floor Masonry of exterior and interior walls up to the 5th floor Installation of partitions up to the 5th floor Installation of window and door blocks up to the 3rd floor Installation of external engineering networks
# 611902786984
Unscheduled inspection
Start date: 2019-06-07, end date: 2019-06-21, duration: —
Authority: Regionalnaya sluzhba gosudarstvennogo stroitelnogo nadzora Rostovskoi oblasti
Purpose of inspection: this audit is conducted in order to verify the fulfillment of Regulation 0100223382 from 19042019 to 27052019 issued by LLC IC BLAGOSTROY TIN 2308237133 The objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, hereinafter referred to as the contractor. The subject of this audit The purpose of the audit is to verify compliance with the regulations of state control bodies and municipal control bodies
# 611902622756
Unscheduled inspection
Start date: 2019-04-08, end date: 2019-04-19, duration: —
Authority: Regionalnaya sluzhba gosudarstvennogo stroitelnogo nadzora Rostovskoi oblasti
Purpose of inspection: This audit is conducted in order to fulfill the p2 program of inspections in case 010022388. The objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, hereinafter referred to as the contractor. The subject of this audit is to verify compliance with mandatory requirements and or requirements established by municipal legal acts
# 611802152878
Unscheduled inspection
Start date: 2018-11-13, end date: 2018-11-16, duration: —
Authority: Regionalnaya sluzhba gosudarstvennogo stroitelnogo nadzora Rostovskoi oblasti
Purpose of inspection: This audit is conducted in order to monitor the implementation of Regulation 0100223881 from 21092018 to 05112018. The objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, hereinafter referred to as the contractor. The subject of this audit is to verify compliance with government regulations. Control supervision
# 611801290409
Unscheduled inspection
Start date: 2018-09-12, end date: —, duration: —
Authority: —
Purpose of inspection: