# 342101443827
Unscheduled inspection
Start date: 2021-12-16, end date: —, duration: 10
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: Purpose: this inspection is carried out in accordance with the inspection program received by the representative of the developer LLC "Parity-Agro" in order to assess the compliance of activities carried out at the facility with the requirements of urban planning legislation of the Russian Federation, including technical regulations and project documentation;
The purpose of this audit is to prevent, identify and suppress violations of the legislation of the Russian Federation, including technical regulations, and project documentation.
The subject of this audit is compliance with mandatory requirements in relation to:
a) compliance of the work performed and the construction materials and products used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements approved in accordance with parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation (hereinafter — the Code) project documentation (including taking into account the changes made to the working documentation and which, in accordance with Part 1.3 of Article 52 of the Code, are part of such project documentation) and (or) an information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of the Code);
b) requirements for a construction permit;
c) the requirements established by parts 2 and 3.1 of Article 52 of the Code;
d) the requirements established by part 4 of Article 52 of the Code to ensure the conservation of the capital construction facility;
e) requirements for the procedure for the implementation of construction control established by the Code and other regulatory legal acts.
# 342100750199
Unscheduled inspection
Start date: 2021-09-15, end date: —, duration: 8
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: In order to assess the compliance of activities carried out at the Facility with the requirements of urban planning legislation of the Russian Federation, legislation of the Russian Federation in the field of environmental protection, fire safety requirements and sanitary and epidemiological welfare of the population, project documentation. The purpose of this audit is to prevent, identify and suppress violations of the legislation of the Russian Federation and project documentation.
The subject of this audit is compliance:
1) compliance of the work performed and the construction materials and products used in the process of construction, reconstruction of the capital construction facility, as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation (hereinafter – GsK RF) (including taking into account the changes made to working documentation and which, in accordance with Part 1.3 of Article 52 of the GsK of the Russian Federation, are part of such project documentation) and (or) an information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of the GsK of the Russian Federation);
2) requirements for a construction permit;
3) the requirements established by Parts 2 and 3.1 of Article 52 of the Civil Code of the Russian Federation;
4) the requirements established by Part 4 of Article 52 of the Civil Code of the Russian Federation to ensure the conservation of the capital construction facility;
5) requirements for the procedure for the implementation of construction control established by the GSK of the Russian Federation and other regulatory legal acts.
# 342100232520
Unscheduled inspection
Start date: 2021-05-21, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection:
# 342004409334
Unscheduled inspection
Start date: 2020-05-18, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection:
# 341903683889
Unscheduled inspection
Start date: 2019-09-25, end date: 2019-10-22, duration: —
Authority: Gosudarstvennaya inspekciya truda v Volgogradskoi oblasti
Purpose of inspection: this audit is carried out in order to carry out federal state supervision over the employer's compliance with labor legislation and other regulatory legal acts containing labor law norms in connection with the receipt of information from government authorities on the facts of violations by employers of the requirements of labor legislation and other regulatory legal acts containing labor law norms that led to incomplete payment of wages within the prescribed period or the establishment of wages The objectives of this audit are to ensure that the employer complies with labor legislation and other regulatory legal acts containing labor law norms the subject of this audit is compliance with mandatory requirements