# 772100026005
Unscheduled inspection
Start date: 2021-02-24, end date: 2021-02-26, duration: 3
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The purpose of the audit: carrying out control measures in connection with the verification of compliance with the instruction; The tasks of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: verification of the elimination of violations specified in the instruction issued by Mosgosstroynadzor
# 772100026011
Unscheduled inspection
Start date: 2021-02-24, end date: 2021-02-26, duration: 3
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The purpose of the audit: carrying out control measures in connection with the verification of compliance with the instruction; The tasks of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: verification of the elimination of violations specified in the instruction issued by Mosgosstroynadzor
# 772100026043
Unscheduled inspection
Start date: 2021-02-24, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772005288074
Unscheduled inspection
Start date: 2020-12-24, end date: 2020-12-25, duration: 2
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the implementation of the audit program The tasks of the audit are to prevent identify and suppress violations of the requirements of the design documentation of the legislation on urban development by the audited person The subject of verification is the compliance of the work and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of project documentation identified during construction control and state construction supervision
# 772005196150
Unscheduled inspection
Start date: 2020-10-20, end date: 2020-10-26, duration: 5
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the implementation of the audit program The tasks of the audit are to prevent identify and suppress violations of the requirements of the design documentation of the legislation on urban development by the audited person The subject of verification is the compliance of the work and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of project documentation identified during construction control and state construction supervision
# 772004496403
Unscheduled inspection
Start date: 2020-08-20, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772004433083
Unscheduled inspection
Start date: 2020-06-15, end date: —, duration: —
Authority: —
Purpose of inspection:
# 771904016011
Unscheduled inspection
Start date: 2019-11-25, end date: 2019-11-26, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the verification of compliance with the requirements of the task of the audit, to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to verify the elimination of violations specified in the order issued by Mosgosstroynadzor
# 771903838732
Unscheduled inspection
Start date: 2019-10-21, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77190803481875
Unscheduled inspection
Start date: 2019-08-20, end date: 2019-08-26, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: carrying out control measures in connection with the implementation of the verification program to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban development activity by the person being audited. compliance of the work and construction materials used during the construction of the reconstruction of the capital construction facility, as well as the results of such work, with the requirements of the technical regulations of the project documentation, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with devices accounting for the energy resources used
# 77190803467633
Unscheduled inspection
Start date: 2019-07-30, end date: 2019-08-02, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: carrying out control measures in connection with the verification of compliance with the prescriptionrevention detection and suppression of violations of the requirements of the design documentation of the legislation on urban development activity by the person being checked, verification of the elimination of violations specified in the prescription issued by Mosgosstroynadzor
# 77190803435342
Unscheduled inspection
Start date: 2019-06-20, end date: 2019-07-01, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: carrying out control measures in connection with the implementation of the verification program to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban development activity by the person being audited. compliance of the work and construction materials used during the construction of the reconstruction of the capital construction facility, as well as the results of such work, with the requirements of the technical regulations of the project documentation, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with devices accounting for the energy resources used
# 77190803398559
Unscheduled inspection
Start date: 2019-04-15, end date: 2019-04-17, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: carrying out control measures in connection with the verification of compliance with the prescriptionrevention detection and suppression of violations of the requirements of the design documentation of the legislation on urban development activity by the person being checked, verification of the elimination of violations specified in the prescription issued by Mosgosstroynadzor
# 77190803358489
Unscheduled inspection
Start date: 2019-02-27, end date: 2019-03-05, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the capital construction facility with the requirements of technical regulations and design documentationthe prevention of detection and suppression of violations of technical regulations and design documentationthe compliance of the work performed and the construction materials used during the construction of the reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of the project documentation, including the requirements of energy efficiency and the requirements of equipping the capital construction facility with metering devices used energy resources
# 77190803313035
Unscheduled inspection
Start date: 2019-01-09, end date: 2019-01-11, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803272615
Unscheduled inspection
Start date: 2018-11-08, end date: —, duration: —
Authority: —
Purpose of inspection: