Found 24 inspections:

# 662005140467
Unscheduled inspection
Start date: 2020-10-12, end date: 2020-11-06, duration: 20
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: 6 To establish that this inspection is carried out in order to implement the inspection program 30120443914 dated 16112018. The purpose of this inspection is to carry out regional state construction supervision.7 The subject of this inspection is to verify the compliance of the work and construction materials used during the construction of the capital construction facility "Multi-storey administrative building 17 on ROM instead of the demolished facility unfinished construction of lit F" located at 39 Mira Street, Yekaterinburg, Sverdlovsk Region, as well as the results of such work to the requirements of project documentation specified in paragraph 1 of part 5 of Article 49 of the Urban Planning Code of the Russian Federation, including project documentation that takes into account the changes made in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation, including energy efficiency requirements and equipment requirements for the capital construction facility construction of metering devices for used energy resources


# 662004431134
Unscheduled inspection
Start date: 2020-06-15, end date: 2020-07-03, duration: 15
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: The purpose of the inspection program 30120443914 dated 20181116 Tasks the implementation of regional state construction supervision The subject is to verify the compliance of the work and applicable building materials during the construction of a capital construction facility A multi-storey administrative building 17 on ROM instead of the demolished facility unfinished construction of lit F located at 39 Mira Street, Sverdlovsk region, Yekaterinburg, the results of such work with the requirements approved in accordance with with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, project documentation, including energy efficiency requirements, with the exception of capital construction facilities to which energy efficiency requirements do not apply, and the requirements for equipping a capital construction facility with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation Federations


# 662004359377
Unscheduled inspection
Start date: 2020-03-17, end date: —, duration:
Authority:
Purpose of inspection:


# 662004190007
Unscheduled inspection
Start date: 2020-01-20, end date: 2020-02-14, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: 6 To establish that this inspection is being conducted in order to implement the inspection program 29170117317 dated January 14, 2019. The objectives of this inspection are to carry out regional state construction supervision.7 The subject of this inspection is to verify the compliance of the work and applicable building materials during the construction of the capital construction facility "Office building with underground parking and integrated transformer substation 1 2 on ROM" located at the address Sverdlovsk region Yekaterinburg Dobrolyubova str. d 4 Chernyshevsky str. d 3 Chernyshevsky str. d 5 the results of such work meet the requirements of project documentation, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply and the requirements for equipping the capital construction facility with metering devices for energy resources used, as well as the availability of a construction permit and meeting the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 661903912934
Unscheduled inspection
Start date: 2019-11-05, end date: 2019-11-29, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: 6 To establish that this inspection is being conducted in order to implement the inspection program 30120443914 dated November 16, 2018. The objectives of this inspection are to carry out regional state construction supervision.7 The subject of this inspection is to verify the compliance of work and applicable building materials during the reconstruction of the capital construction facility "Multi-storey Administrative Building 17 on ROM instead of the demolished facility unfinished construction of lit F" located at 39 Mira Street, Yekaterinburg, Kirovsky District, the results of such work meet the requirements of the project documentation approved in accordance with Parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation and or the information model if the formation of and the maintenance of an information model are mandatory in accordance with the requirements of the Urban Planning Code of the Russian Federation, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements set out in Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation. Federations


# 661903912980
Unscheduled inspection
Start date: 2019-11-11, end date: —, duration:
Authority:
Purpose of inspection:


# 661902912623
Unscheduled inspection
Start date: 2019-08-19, end date: —, duration:
Authority:
Purpose of inspection:


# 661902912612
Unscheduled inspection
Start date: 2019-08-05, end date: 2019-08-30, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: This inspection is carried out in order to implement the inspection program 30120443914 dated November 16, 2018. The objectives of this inspection are to carry out regional state construction supervision. The subject of this inspection is to verify the compliance of the work and construction materials used in the reconstruction of the capital construction facility "Multi-storey Administrative Building 17 on ROM instead of the demolished facility unfinished construction of lit F" located at 39 Mira Street, Yekaterinburg, Kirovsky District, the results of such work, including the requirements for energy efficiency, with the exception of capital construction facilities for which energy efficiency requirements do not apply, and the requirements for equipping the capital construction facility with metering devices for energy resources used, as well as the availability of a construction permit and compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code Of the Russian Federation


# 661902849952
Unscheduled inspection
Start date: 2019-07-22, end date: —, duration:
Authority:
Purpose of inspection:


# 661902702408
Unscheduled inspection
Start date: 2019-05-20, end date: —, duration:
Authority:
Purpose of inspection:


# 661902588805
Unscheduled inspection
Start date: 2019-05-06, end date: —, duration:
Authority:
Purpose of inspection:


# 661902543379
Unscheduled inspection
Start date: 2019-03-04, end date: 2019-03-29, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: The purpose is to implement the inspection program 30120443914 dated November 16, 2018. The task is to carry out regional state construction supervision. The subject is to verify the compliance of the work and applicable building materials during the reconstruction of the capital construction facility "Multi-storey administrative building 17 on ROM instead of the demolished facility unfinished construction of lit F" located at 39 Mira Street, Yekaterinburg, Kirovsky district. the requirements of the project documentation, including energy efficiency requirements, with the exception of capital construction facilities to which energy efficiency requirements do not apply, and the requirements for equipping the capital construction facility with metering devices for energy resources used, as well as the availability of a construction permit and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 661902490062
Unscheduled inspection
Start date: 2019-02-11, end date: —, duration:
Authority:
Purpose of inspection:


# 661802179175
Unscheduled inspection
Start date: 2018-12-03, end date: 2018-12-28, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: The purpose is to implement the inspection program 30120443914 dated November 16, 2018. The task is to carry out regional state construction supervision. The subject is to verify the compliance of the work and construction materials used in the reconstruction of the capital construction facility "Multi-storey administrative building 17 on ROM instead of the demolished facility unfinished construction of lit F" located at 39 Mira Street, Yekaterinburg, Kirovsky district. The results of such the requirements of the project documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for the energy resources used, as well as the availability of a construction permit and compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 661802179211
Unscheduled inspection
Start date: 2018-12-03, end date: 2018-12-28, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: The purpose is to implement the inspection program 30120443914 dated November 16, 2018. The task is to carry out regional state construction supervision. The subject is to verify the compliance of the work and construction materials used in the reconstruction of the capital construction facility "Multi-storey administrative building 17 on ROM instead of the demolished facility unfinished construction of lit F" located at 39 Mira Street, Yekaterinburg, Kirovsky district. The results of such the requirements of the project documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for the energy resources used, as well as the availability of a construction permit and compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 661802091963
Unscheduled inspection
Start date: 2018-11-26, end date: —, duration:
Authority:
Purpose of inspection:


# 661802019131
Unscheduled inspection
Start date: 2018-11-13, end date: 2018-11-23, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: This inspection is carried out in order to implement the inspection program 29170117317 dated 22122017. The purpose of this inspection is to carry out regional state construction supervision. The subject of this inspection is to verify the compliance of the work and applicable building materials during the construction of the capital construction facility "Office building with underground parking and integrated transformer substation 1 2 on ROM" located at the address Sverdlovsk region Yekaterinburg Dobrolyubova str. d 4 Chernyshevsky str. d 3 Chernyshevsky str. d 5 the results of such work meet fire safety requirements safety regulations and state standards for project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used, as well as the availability of a construction permit and compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation Federations


# 661800615828
Unscheduled inspection
Start date: 2018-08-27, end date: 2018-09-07, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: The purpose is to implement the inspection program 29170117317 dated December 22, 2017. The task is to carry out regional state construction supervision. The subject is to verify the conformity of work and construction materials used in the construction of the capital construction facility "Office building with underground parking and integrated transformer substation 1 2 on ROM" located at the address Sverdlovsk region Yekaterinburg Dobrolyubova str. d 4 Chernyshevsky str. 3 Chernyshevsky St. 5 the results of such work meet the requirements of the technical regulations of the project documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, as well as the availability of a construction permit and compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 661800480036
Unscheduled inspection
Start date: 2018-06-25, end date: 2018-07-20, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: The purpose is to implement the inspection program 30120443914 dated July 04, 2017. The task is to carry out regional state construction supervision. The subject is to verify the compliance of work and applicable building materials during the reconstruction of the capital construction facility "Multi-storey administrative building 17 on ROM instead of the demolished facility unfinished construction of lit F" located at 39 Mira Street, Yekaterinburg, Kirovsky district. The results of such the requirements of the technical regulations of the project documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for the energy resources used, as well as the availability of a construction permit and compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 661800376723
Unscheduled inspection
Start date: 2018-05-28, end date: 2018-06-22, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: The purpose is to implement the inspection program 29170117317 dated December 22, 2017. Tasks are to carry out regional state construction supervision on the subject of checking the compliance of work and applicable building materials during the construction of the capital construction facility "Office building with underground parking and integrated transformer substation 1 2 on ROM" located at the address Sverdlovsk region Yekaterinburg Dobrolyubova str. d 4 Chernyshevsky str. 3 Chernyshevsky St. 5 the results of such work meet the requirements of the technical regulations of the project documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, as well as the availability of a construction permit and compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 661800105427
Unscheduled inspection
Start date: 2018-02-26, end date: —, duration:
Authority:
Purpose of inspection:


# 66170701735051
Unscheduled inspection
Start date: 2017-06-26, end date: 2017-07-07, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: This inspection is carried out in order to notify the developer of the start of construction of the capital construction facility. The objectives of this inspection are to carry out regional state construction supervision. The purpose of this inspection is to verify the compliance of the work and applicable building materials during the construction of the capital construction facility "Office building with underground parking and integrated transformer substation 1 2 on ROM" located in the Sverdlovsk region Yekaterinburg Dobrolyubova St. 4 Chernyshevsky St. 3 Chernyshevsky St. 5 the results of such work meet the requirements of the technical regulations of the project documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, as well as the availability of a construction permit and compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation


# 66170701734768
Unscheduled inspection
Start date: 2017-06-26, end date: 2017-07-07, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: This inspection is carried out in order to implement the inspection program 30120443914 dated September 27, 2016. The objectives of this inspection are to carry out regional state construction supervision. The subject of this inspection is to verify the compliance of the work and applicable building materials during the reconstruction of the capital construction facility "Multi-storey Administrative Building 17 on ROM instead of the demolished facility unfinished construction of lit F" located at 39 Mira Street, Yekaterinburg, Kirovsky District, the results of such work meet the requirements of the technical regulations of the project documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, as well as the availability of a construction permit and compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation


# 66170701500733
Unscheduled inspection
Start date: 2017-04-03, end date: 2017-04-28, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: This inspection is carried out in order to implement the inspection program 30120443914 dated September 27, 2016. The objectives of this inspection are to carry out regional state construction supervision. The subject of this inspection is to verify the compliance of the work and applicable building materials during the reconstruction of the capital construction facility "Multi-storey Administrative Building 17 on ROM instead of the demolished facility unfinished construction of lit F" located at 39 Mira Street, Yekaterinburg, Kirovsky District, the results of such work meet the requirements of the technical regulations of the project documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, as well as the availability of a construction permit and compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.