Found 12 inspections:

# 661800036772
Unscheduled inspection
Start date: 2018-02-01, end date: —, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection:


# 661800079908
Unscheduled inspection
Start date: 2018-02-26, end date: 2018-03-07, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: This inspection is carried out in order to implement the inspection program 110830811, as amended on 06062016. The purpose of this inspection is to carry out regional state construction supervision. The subject of this inspection is to verify the compliance of the work and applicable building materials during the construction of the capital construction facility "Underground parking lot of box type 7 A B at GP 5 launch Complex" located at Yekaterinburg ul. Yasnaya ul. Shahumyan ul. Volgogradskaya ul. Gromova the results of such work meet the requirements of technical regulations, fire safety requirements, safety rules and state standards for project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used, as well as the availability of a construction permit and compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation


# 66170701794064
Unscheduled inspection
Start date: 2017-07-17, end date: 2017-07-28, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: This inspection is carried out in order to implement the inspection program 110830811, as amended on 06062016. The purpose of this inspection is to carry out regional state construction supervision. The purpose of this inspection is to verify the compliance of the work and applicable building materials during the construction of the capital construction facility "Underground parking lot of box type 7 AB at GP 5 launch Complex" located at hEkaterenburg Yasnaya ul. Shahumyan Volgogradskaya St. Gromova St. the results of such work meet the requirements of technical regulations, fire safety requirements, safety rules and state standards for project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used, as well as the availability of a construction permit and compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation


# 66170701649218
Unscheduled inspection
Start date: 2017-06-05, end date: 2017-06-30, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: inspection of a capital construction facility completed on the basis of the notice of completion of the capital construction facility VH 29018219300 dated 18052017


# 66170701556169
Unscheduled inspection
Start date: 2017-05-02, end date: —, duration:
Authority:
Purpose of inspection:


# 66170701538068
Unscheduled inspection
Start date: 2017-04-17, end date: 2017-04-21, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: verification of the compliance of the work and applicable building materials during the construction of the capital construction facility "Underground parking lot of box type 7AB according to GP 5 launch complex" located at Yekaterinburg Yasnaya ul. Shahumyan ul. Volgogradskaya ul. Gromova the results of such work with the requirements of technical regulations sanitary and epidemiological rules and regulations safety rules and state standards of project documentation, including energy requirements the efficiency and requirements of equipping the capital construction facility with metering devices for the energy resources used, as well as the availability of a construction permit and compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation


# 66170701504583
Unscheduled inspection
Start date: 2017-04-05, end date: —, duration:
Authority:
Purpose of inspection:


# 66170701496497
Unscheduled inspection
Start date: 2017-04-03, end date: 2017-04-14, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: The subject of this audit is to verify the compliance of the work performed and the applicable building materials during the construction of the capital construction facility "Underground parking lot of box type 7AB at GP 5 start-up complex" located at hEkaterenburg Yasnaya ul. Shahumyan ul. Volgogradskaya ul. Gromova the results of such work with the requirements of technical regulations of the project documentation, including energy efficiency requirements and equipment requirements of the capital construction facility construction with metering devices for energy resources used, as well as the availability of a construction permit and compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation


# 66170701445607
Unscheduled inspection
Start date: 2017-03-16, end date: 2017-04-03, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: In order to implement the inspection program 645073 dated July 04, 2016, the objectives of this inspection are to carry out regional state construction supervision.


# 66170701350840
Unscheduled inspection
Start date: 2017-02-06, end date: 2017-02-17, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: verification of the conformity of work performed and applicable building materials during the construction of the capital construction facility "Two sections of variable storeys of a ten-section residential building with built-in office space on the ground floor and built-in retail space in the basement 5B 5G according to GP8 launch complex" located at Yekaterinburg Leninsky district Yasnaya ul. Shahumyan ul. Volgogradskaya ul. Gromova the results of such work requirements of technical regulations, sanitary and epidemiological rules and regulations, safety rules and state standards for project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used, as well as the availability of a construction permit and compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation


# 66170701296624
Unscheduled inspection
Start date: 2017-01-30, end date: —, duration:
Authority:
Purpose of inspection:


# 66170701317219
Unscheduled inspection
Start date: 2017-01-24, end date: 2017-02-06, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: control of the execution of the previously issued order on the elimination of identified violations of mandatory requirements 291604771P1 dated October 14, 2016


Information about inspections